Progress of Shintake Monitor (ATF2 IP-BSM) KEK site meeting 2008/10/31 Takashi Yamanaka.

Slides:



Advertisements
Similar presentations
Passive isolation: Pre-isolation for FF quads A. Gaddi, H. Gerwig, A. Hervé, N. Siegrist, F. Ramos.
Advertisements

Compton gamma stability - Status of the drift source investigation - Nobuhiro Terunuma, KEK March 17 th, 2014, LAPP, FJPPL-FKPPL ATF2 Workshop 1.
ATF2 Interaction Point Beam Size Monitor (Shintake Monitor) Status T. Yamanaka, M. Oroku, Y. Yamaguchi, S. Komamiya ( Univ. of Tokyo ), T. Suehara, Y.
1/8 T. Kume, Y. Honda, and T. Tauchi High Energy Accelerator Research Organization (KEK) T. Suehara, H. Yoda, M. Oroku, T. Yamanaka and Y. Kamiya The univ.
Wed 15 Jul 2009 ATF2 weekly meeting Oxford MONALISA 1 MONALISA at ATF2 First installation report 15 July 09.
Taikan SUEHARA, ILC-Asia wg4 KEK, 2005/7/27 Laser interferometric beam size monitor (Shintake-monitor)
Investigation of the influence of suspended optic’s motion on LIGO detector sensitivity Sanichiro Yoshida Southeastern Louisiana University.
Wed 17 Jun 2009ATF2 weekly meeting Oxford MONALISA 1 MONALISA at ATF2 Plans for first installation 30 June to 19 July 2009.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
1 LAViSta Laboratories in Annecy working on Vibration and Stabilisation Catherine ADLOFF Andrea JEREMIE Jacques LOTTIN Benoît BOLZON Yannis KARYOTAKIS.
1 ATF2 project: Investigation on the honeycomb table vibrations Benoit BOLZON 33rd ATF2 meeting, 24th January 2007 Laboratories in Annecy working on Vibration.
ATF2 week meeting: Impact of cooling water on the final doublets vibrations Benoît BOLZON Laboratories in Annecy working on Vibration Stabilization 15/10/08.
Vibration measurements on the final doublets and the Shintake Monitor Benoît BOLZON7th ATF2 project meeting, 16/12/08.
Tue 22 Sept 2009 Stabilization Day 7 Oxford MONALISA 1 MONALISA update Could the messenger of bad vibration news be the cause of it? beam pipe Shintake.
Status on MONALISA presented by D. Urner 6 th stabilization day 9. June 09.
Update of the ground motion generator of A. Seryi for ATF2 thanks to ground motion measurements in the ATF2 beam line 1 Benoît BOLZONATF2 software task.
Installation of FD in September A.Jeremie, B.Bolzon, N.Geffroy, G.Gaillard, J.P.Baud, F.Peltier With the help of KEK, SLAC, KNU and CERN colleagues For.
IPBSM status and plan ATF project meeting M.Oroku.
IPBSM - Stability of the laser system - Nobuhiro Terunuma Feb. 12 th 2014, KEK, 17 th ATF2 project meeting.
QD0 stabilization L. Brunetti 1, N. Allemandou 1, J.-P. Baud 1, G. Balik 1, G. Deleglise 1, A. Jeremie 1, S. Vilalte 1 B. Caron 2, C. Hernandez 2, (LAViSta.
Taikan SUEHARA, 3 rd ATF2 project KEK, 2006/12/18 Status of Shintake-monitor Optics (focused on phase stabilization) Taikan SUEHARA The University.
ATF2 meeting LAPP; David Urner 1 David Urner Paul Coe Matthew Warden Armin Reichold Geoffrey Rayner MPhys alumnus MONALISA Monitoring, Alignment.
Southeastern Louisiana University / LIGO Livingston 1 Modeling the Input Optics using E2E R. Dodda, T. Findley, N. Jamal, K.Rogillio, and S. Yoshida, Southeastern.
31 May 2006Federico Paoletti Elba GWADW 1 Available traps (short sensors’ list) l Fast monitoring (50Hz < f sample < 20kHz)  vertical high frequency accelerometers.
Vibration Measurement on the Shintake Monitor and Final Doublet Takashi Yamanaka (Univ. of Tokyo) Benoît Bolzon (LAPP) ATF2 weekly meeting 26 November,
Stabilization of Focus at ATF2 David Urner University of Oxford.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
Commissioning Status of Shintake Monitor (IP-BSM) T. Yamanaka, M. Oroku, Y. Yamaguchi, Y. Kamiya, S. Komamiya (Univ. of Tokyo), T. Okugi, N. Terunuma,
BPM support and beam pipe length FD support status A.Jeremie.
Update of a ground motion generator to study the stabilisation usefulness of ATF2 final focus quadrupoles 1 Benoît BOLZON B. Bolzon, A. Jeremie (LAPP)
QF1 vibration status A.Jeremie A.Jeremie, N.Geffroy, drawings by Araki-san.
FD support Andrea JEREMIE N.Geffroy, B.Bolzon, G.Gaillard.
T. Suehara, H. Yoda, T. Sanuki, Univ. of Tokyo, T. Kume, Y. Honda, T. Tauchi, High Energy Accelerator Research Organization (KEK) ATF2-IN2P3-KEK kick-off.
E.Guschin (INR) 21 November 2003Integration EDR PRS/SPD static envelop, assembly and installation Detector layout Static envelop along the beam Detector.
E.Guschin (INR,Moscow) 3 May 2006Calorimeter commissioning meeting Status of PRS/SPD detector Cosmic test results Installation/tuning of monitoring system.
How high frequency we care if we need the stabilization of 1nm level?
LASER FRAME: Straightness monitor (Tentative results of resolution test) Third Mini-Workshop on Nano Project at ATF May 30-31,2005 KEK Nano BPM Group Y.Higashi,
1 ATF2 Project Meeting December 2006 Ground Stabilisation with the CERN STACIS 2000 Stable Active Control Isolation System LAViSta Laboratories in.
GM sensor tests and installation A.Jeremie K.Artoos, D. Kudryavtsev, Y.Renier, R.Tomas-Garcia, D.Schulte.
1/13 Tatsuya KUME Mechanical Engineering Center, High Energy Accelerator Research Organization (KEK) ATF2-IN2P3-KEK kick-off meeting (Oct. 9, 2006) Mount.
Taikan SUEHARA, IN2P3-KEK collaboration meeting on ATF2, Annecy, 2007/10/15 Shintake Monitor: Installation and Commissioning Schedule Taikan SUEHARA, The.
Progress of Shintake Monitor Work KEK site meeting August 26, 2009 T. Yamanaka.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Schematic of Laser Transport Vacuum enclosure Laser Room Interlocked, controlled area Laser Wall Periscope in vacuum enclosure Cathode Fiduciary Beam line.
Superconducting final doublet Support A.Jeremie. SC magnet steps Motivation: have an active stabilisation as planned in ILC and CLIC => need to evaluate.
MONALISA Update David Urner ATF2 Meeting Dec
ATF2 weekly meeting 4 July 2007 MONALISA: Attachment of Vacuum Vessels for ATF2 David Urner.
Vibrations studies for the nominal optics and the ultra-low beta optics Benoît BOLZON 1 B. Bolzon, A. Jeremie (LAPP) P. Bambade, Y. Renier (LAL) A. Seryi.
Ground motion studies at ATF2 June 11, 2014 Orbit jitter source identification via ground motion studies at ATF2 (Results of the June run) Marcin Patecki,
Taikan SUEHARA et al., LCWS2007 & DESY, 2007/06/01 R&D Status of ATF2 IP Beam Size Monitor (Shintake Monitor) Taikan SUEHARA, H.Yoda, M.Oroku,
1 KEK Hiroshi Yamaoka Vibration analysis of the ILD QD0-support system Oct, 2 nd '09 KEK H. Yamaoka - Results of Vibration analysis - Coherency measurement.
IP diagnostics Toshiyuki Okugi 2008 / 6 /19 ATF2 Software mini-workshop LAL, Orsay.
ATF2: final doublet support Andrea JEREMIE B.Bolzon, N.Geffroy, G.Gaillard, J.P.Baud, F.Peltier With constant interaction with colleagues from KEK, SLAC.
Vibration measurements with and without Monalisa 15/07/09 Benoît BOLZON (LAPP) David Urner (Oxford) Paul Coe (Oxford) 1 Benoît BOLZON.
Design for a New Optical Table of the Shintake Monitor Takashi Yamanaka The University of Tokyo ATF2 weekly meeting 2007/9/26.
Taikan SUEHARA, Joint Meeting of PRPPC in Honolulu, Hawaii, 2006/10/30 Laser Fringe Stabilization of 35nm IP Beam Size Monitor (Shintake monitor) for ATF2/ILC.
Progress of Shintake Monitor (ATF2 IP-BSM) ATF2 weekly meeting 2008/9/3 Takashi Yamanaka The University of Tokyo.
Gamma Detector of the Shintake monitor 2007/12/19 Masahiro Oroku, Takashi Yamanaka H.Yoda, T.Suehara Y.Kamiya S.Komamiya(Tokyo Univ) Y.Honda, T.Tauchi,
Layout of a Building Leveling Instruments Builders Level Level-Transit Laser Beam Level.
Alignment and stability session
Nanometer stabilisation at ATF2 within FJPPL and FKPPL
Summary FD Support System
Upgrade activities at Clermont-Ferrand
A.Jeremie, B.Bolzon, N.Geffroy, C.Girard, (G.Gaillard)
Topics on Vibration Issues
Laboratories in Annecy working on Vibration Stabilization
ATF2: final doublet support
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
IP configuration session
Presentation transcript:

Progress of Shintake Monitor (ATF2 IP-BSM) KEK site meeting 2008/10/31 Takashi Yamanaka

Contents Cabling Laser Transport Layout of DAQ room Vibration Measurement

Cabling signal cable and high voltage cable for Gamma-ray Detector signal cable for laser optics device (photodiode, PSD, CCD) cabling is now on going

Laser Transport Mirror boxes and plastic tubes are used (ready). Screwing for attachment of mirror boxes will be done in this week. Construction of transport line will be in next week Mirror box

Layout of DAQ room

Vibration Measurement (1) measured the vibration of Shintake Monitor vertical table with Benoît Bolzon (LAPP) on the lower table on the top table

Vibration Measurement (2) motion correlation between QD0 and top of Shintake Monitor table

Measurement Result Coherency between the ground and Shintake Monitor is good from 1 Hz to 50 Hz in all direction. Coherency between QD0 and Shintake Monitor is good from 1 Hz to 50 Hz in vertical direction (in horizontal coherency is bad above 20 Hz).