Run 10 Start-up Status

Slides:



Advertisements
Similar presentations
AGS Status and Plans RHIC Spin Collaboration Meeting 2/4/11.
Advertisements

RHIC Status Time Meeting 2/10/2015 Then said to us: "You can no farther go Forward upon this crag, because is lying All shattered, at the bottom, the sixth.
Note: most of the slides shown here are picked from CERN accelerator workshops. Please refer to those workshop for further understanding of the accelerator.
APEX Report April 28-29, 2009 May 4, 2009 Fulvia Pilat Time Meeting, May
AGS pp Status Feb. 6, 2015 RSC Meeting Haixin Huang.
Run 9 polarized proton Log 9 Jan begin 45 degree cool down from room temp (3 MW-NEW) 2 Feb, Cool-down to 4.5 degrees begins 5 Feb, Blue ring cold but still.
RHIC Status Haixin Huang Time Meeting 02/1/2011. Jan. 26 Ring access for six hours to fix jet and many other jobs. Difficulty to provide 28X28 store overnight.
Accelerator Support and Maintenance Run 14. Maintenance/Changeover Day Major efforts RHIC: Major efforts RHIC: Access hrs. Access hrs.
1 RHIC Run-7 Au-Au Operation A. Drees APEX workshop, Nov 2 nd 2006 Run organization Previous run and expectation for Run7 Start-Up plan Problem areas.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 5 Apr 2011 Agenda: Open.
APEX Report: March 31 – April 1, 2009 Fulvia Pilat Time Meeting, April 7, 2009.
1 Near-term machine performance — The next 5 years, before e-cooling — Wolfram Fischer Run Coordinator for RHIC Run-4 Open Meeting on RHIC Planning Berkner.
AGS/Booster PP Setup Plan Jan. 11, 2013 RSC Meeting Haixin Huang.
Maintenance and Accelerator Support RHIC run10. Last Wednesday: Nice recovery Nice recovery Good work all especially: Good work all especially: HP, RF,
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Possible Run 10 plan based on 25 Nov Revised Plan Run10, 25 cryo-weeks (my guesses after Dec 27) – Dec. 1, Begin cooldown to 4.5K – Dec. 4, Cooldown to.
Overview Run-6 - RHIC Vadim Ptitsyn C-AD, BNL. V.Ptitsyn RHIC Spin Workshop 2006 RHIC Run-6 Timeline  1 Feb – Start of the Run-6. Start of the cooldown.
RHIC Status Haixin Huang Time Meeting 01/18/2011.
Machine - Experiments January 12, 2005 Machine status.
RHIC Status Time Meeting 2/3/2015 He is fixed into the ice at the center to which flow all the rivers of guilt; and as he beats his great wings as if to.
Injector PP Setup Plan and Status November 18, 2008 Haixin Huang.
May 17, 2005Wednesday Experiment Meeting BNL, Upton Acceleration beyond 100 GeV  Goal To evaluate the spin dynamics beyond 100 GeV  What’s the impact.
Preparation for RHIC PP Run in 2011 Wednesday 20, 2010 RHIC Machine Planning Meeting Haixin Huang RUN website: RUN.
RHIC Run14 Time Meeting. Run14 Status – Apr. 29 Operations running well, 11 full stores over the past 7 days; setting STAR ZDC rates to 50 khz is now.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Machine status – December 28  Machine status - overview  Blue ring: ramp development  Yellow ring: obstruction update  Set-up and ramp-up.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
RHIC pp 500 GeV development M. Bai C-A Department.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 12 Apr 2011 Agenda: Open.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 14 Mar 2011 Agenda: Status – cryo/budget Experiment priorities.
AP2 Line & Debuncher Studies Status Keith Gollwitzer Antiproton Source January 9, 2006 Many people involved with providing the hardware and software that.
RHIC Run11 Summary May 6, 2011 RSC Meeting Haixin Huang Luminosity Availability Polarization RHIC setup issues.
Run 10 plan based on 25 Nov Revised Plan and  s=200 extended by 1 week Dec. 1, Begin cool down to 4.5K Dec. 4, Cooldown to 4.5K complete in both rings!
AGS/Booster PP Setup Status Feb. 5, 2013 Time Meeting Haixin/Vincent.
Run 12 RHIC Machine/Experiments Meeting 17 Apr 2012 Agenda: Status reports Polarization issues update (E. Aschenauer) Other business With 17 April update.
Feb. 23, 2005Wednesday Experiment Meeting BNL, Upton Status on AGS cold snake  Cold mass is now in the cryostat. It is in the phase of wiring, and because.
Preparation Status of pp Run11 Haixin Huang Time Meeting 12/21/
RHIC status Chuyu Liu Time meeting Apr. 28, 2015.
AGS Run-9 Preparations, Status and Plans Dec. 16, 2008 Haixin Huang.
Crossing transition at RHIC V.Ptitsyn, N.Abreu, M. Brennan, M.Blaskiewicz, W. Fischer, C. Montag, R. Lee, S.Tepikian.
RHIC Run14 Time Meeting. Run14 Status – May 27 Operations running well, 11 full stores over the past 7 days. Getting high intensity again from injectors,
RHIC Run14 Time Meeting. Run14 Status – June 24 Run14 He3-Au physics declared on 6/20 with Fill #18460; stochastic cooling is ON for Au beam, longitudinal.
Run 12 RHIC Machine/Experiments Meeting 24 Apr 2012 Agenda: Status reports Other business.
Agenda Safety Schedule Machine and system reports 2/26/2016G. Robert-Demolaize, Time Meeting1.
Agenda Safety Schedule Machine and system reports 2/29/2016G. Robert-Demolaize, Time Meeting1.
ELENA: Commissioning & operation ELENA beam commissioning Operation 12/11/2015T.Eriksson CERN BE/OP/AD1.
 Safety  Schedule: Past, Present and Future  RHIC and Experiments Reports  Machine and Systems Reports  AOB.
APEX Schedule April :30am12:30pm5pm IBS suppression lattice Litvinenko, Tepikian +team Back 2 Phys 4pm Nonlinear Chromaticity (Response.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
RHIC 250 GeV Polarized Proton Run 2009 Mei Bai RUN website: 12/16/2008RHIC Spin Collaboration Meeting.
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Haixin Huang AGS Cold Snake: Status and Plans.
APEX Studies: Accelerating w. Near 3 rd Order Resonance Vincent, Al, Michiko, Steve, Don, Yun, Guillaume, Mei, Todd, Wolfram, Greg, …
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 7 Jun 2011 Agenda: √s = 200 GeV AuAu progress 27 GeV Run (or other)
RHIC Status Haixin Huang RSC Meeting 02/18/2011. l Fixed the blue dump kicker noise problem last Friday. l Declared physics last Friday. l Smooth run.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 31 May 2011 Agenda: √s = 200 GeV AuAu progress Update on 250 GeV integrated Lumi.
Accelerator Support and Maintenance Startup for Run 13.
Status of RHIC Polarization Studies. Summary of Polarization Studies during Run09 Tune scans: – Nearby 0.7 – Near integer tune Polarization ramp measurement.
ApEx needs for CeC PoP Experiment December 11, 2015.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 29 Mar 2011 Agenda: Open.
RUN 11 RHIC MACHINE/EXPERIMENTS MEETING 22 Mar 2011 Agenda: Open.
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
Possible Run 10 plan based on 25 Nov Revised Plan Run10, 25 cryo-weeks (my guesses after Jan 12) – Dec. 1, Begin cool down to 4.5K – Dec. 4, Cooldown to.
Run 10 plan based on 25 Nov Revised Plan and  s=200 extended by 1 week Dec. 1, Begin cool down to 4.5K Dec. 4, Cooldown to 4.5K complete in both rings!
A RHIC Low-Energy Test Run With Protons Todd Satogata (W. Fischer, T. Roser, J. DeLong, M. Brennan, D. Bruno, and others) April 11, 2006 Driven by discussions.
RHIC Status Haixin Huang Time Meeting 01/25/2011.
Aims for the week Recover from technical stop and precycle at 10A/s
Presentation transcript:

Run 10 Start-up Status

Schedule Oct. 1 begin FEC/Controls Turn-on Oct. 6 Begin Cryo Scrubbing Nov. 2 Begin 45 K waves Nov. 16Booster/AGS Setup Nov. 16 – 20 RHIC Dry Run Dec K waves – Started Dec. 4 Beam in RHIC (blue) Dec. 14Store devel., physics setup (conditions:  *=60 cm, intensity = 1e9, # of bunches > 50) Dec. 22 Projected Physics Start

What’s been done? injection is setup in both rings –Kickers timed in –Injection orbit corrected –Tunes are set to correct values –Frequency is set (Blue with hysteresis, Yellow without) LLRF commissioning has started –RF Capture is done in both rings –Acceleration and Transition phase jumped in blue. Instrumentation check-out has started –BBQ is working for tune feedback in Blue –BPM’s are timed in and orbits are working –Orbit feedback in blue is working and being commissioned. P.S. check-out is progressing very well –Yellow check-out is in progress

Hold Ups Blue MMPS development –New IBS lattice = some quad polarity changes –Quench detection system configuration Reversed quadrupole in Yellow (Sat.) AGS MMPS Motor Generator Oil Leak. So we are behind by a day or so, but working to stay on track.

This Week (12/14-12/21) Setup Ramp in Blue and Yellow –Get beam to store Setup Yellow Injection and Ramp Commission new LLRF –Acceleration in Yellow –Cogging and rebucketing Development now with Exp. Magnets on. Working 24 hour shifts Over the weekend – working at Store