1 NPRR638 (Seasonality) Back-Cast Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public October 3, 2014.

Slides:



Advertisements
Similar presentations
1 Revisions to M2 and RT Final Component of UFTA CWG/MCWG ERCOT Public January 22, 2014.
Advertisements

1 M1 Calculation Options CWG/MCWG ERCOT Public December 16, 2013.
Credit Updates Vanessa Spells Credit Work Group ERCOT Public
Automation and Improvements to Default Uplift Methodology (summary/white paper of a draft NPRR)
Seasonal Adjustment Factor Discussion Technical Advisory Committee
NPRR Proposed Changes TPTF Meeting 26 Aug 2008.
1 NPRR638 Back-casting Updated Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public May 01, 2015.
Potential Future Exposure (PFE) Q Presentation Randy Baker Director, Credit Risk 19 January 2010 ERCOT Board of Directors Meeting.
SAWG Update to WMS February 4 th, 2015 Brandon Whittle.
Seasonal Adjustment Factor Mark Ruane Credit Work Group ERCOT Public July 23, 2014.
MCWG Update to WMS Loretta Martin LCRA, Chair Josephine Wan AE, Vice Chair 03/05/
Next Steps to Reduce the RTM Settlement Timeline August 29, 2013 COPS Workshop Update to TAC Harika Basaran COPS Chair September 5, 2013.
Capacity Forecast Report Sean Chang Market Analysis and Design Suresh Pabbisetty CQF, ERP, CSQA Credit CWG/MCWG September 16, 2015 ERCOT Public.
September 2012 Proposed CRR Auction Credit Changes: Summary of Draft NPRR.
January 14, New logic and invoices used in January 2015 when closing out December 2014 New Bill Determinants: CRRBAFA- CRR Balancing Account Fund.
1 NPRR 484/554 – Revisions to Congestion Revenue Rights Credit Calculations and Payments Market Call ERCOT Public July 31, 2013.
Market Credit Working Group update to the Wholesale Market Subcommittee 06/03/
MCWG Update to WMS 5/11/ Exposure / Collateral Update Nodal Total Potential Exposure reported by ERCOT as of 4/30/11 remains less than Zonal Estimated.
Market Credit Working Group update to the Wholesale Market Subcommittee 10/07/
MCWG Update to WMS 6/15/ Exposure / Collateral Update Nodal Total Potential Exposure reported by ERCOT as of 4/30/11 remains less than Zonal Estimated.
Nodal Credit Monitoring and Management – Business Requirements ERCOT CREDIT Department October 11, 2006.
May 03, UFE ANALYSIS Old – New Model Comparison Compiled by the Load Profiling Group ERCOT Energy Analysis & Aggregation May 03, 2007.
1 NPRR638 Back-casting Updated Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public April 22, 2015.
1 Draft NPRR – Revisions to Certain Price Components of EAL CWG/MCWG ERCOT Public January 22, 2014.
MCWG Update to WMS 08/14/2013. MCWG Update to WMS General Update -July 31 st Joint MCWG/CWG Meeting Review NPRRs All operational except – NPRR 552 – Additional.
Market Credit Working Group update to the Wholesale Market Subcommittee 04/06/
Resource Adequacy Task Force (RATF) Update to WMS June 12, 2013.
1 DAM Credit parameters review The “Procedures for Setting Nodal Day Ahead Market (DAM) Credit Requirements Parameters” is a document that is required.
Capacity Forecast Model Mark Ruane Credit Work Group ERCOT Public October 15, 2014.
Credit Updates Vanessa Spells Credit Work Group ERCOT Public February 18, 2015.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Settlement Invoices Business Requirements Settlements and.
MCWG Update to WMS 11/13/2013. MCWG Update to WMS General Update - October 30 th Joint MCWG/CWG Meeting Review September 25 Meeting Minutes - Approved.
1 Tab X ERCOT Confidential Credit Impact of Increased Caps The credit exposure impact of higher system-wide offer caps was estimated using an internal.
The credit exposure impact of higher system-wide offer caps was estimated using an internal ERCOT model under four scenarios: 1.(Base Case) “Normal” summer.
Market Credit Working Group update to the Wholesale Market Subcommittee 09/02/
M2:Shortened RTM Settlement Timeline Vanessa Spells CWG/MCWG Meeting April 24, 2013.
Credit Updates Vanessa Spells Credit Work Group ERCOT Public December 16, 2015.
Temperature Assumptions for Dynamic Ratings in ERCOT CRR Auctions Proposal to differentiate between Day (PeakWD & PeakWE) and Night (Off-peak) October.
1 Nodal Credit Update at WMS June 16, 2010.
1 Letter of Credit Issuer Concentration CWG/MCWG October 30, 2014 ERCOT Public.
1 NPRR638 Back-casting Supplementary Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public May 13, 2015.
Item 9: Provisions for Financial Statements CWG/MCWG Meeting ERCOT February 20, 2014.
Market Credit Working Group update to the Wholesale Market Subcommittee 02/04/2015.
1 ICE Price Data Analysis CWG/MCWG Suresh Pabbisetty, CQF, ERP, CSQA. ERCOT Public January 20, 2016.
1 Load to Price Correlation CWG/MCWG Suresh Pabbisetty, CQF, CSQA. ERCOT Public February 20, 2014.
Market Credit Working Group update to the Wholesale Market Subcommittee 03/04/
1 ORDC Curve Discussion ERCOT QSE Managers Working Group 9/4/2015.
1 NPRR 484/554 Phase 2 Suresh Pabbisetty, ERP, CQF, CSQA Lead Technical Analyst, Credit CWG / MCWG May 20, 2015 ERCOT Public.
Total Potential Exposure (TPE) Overview Credit Work Group May 28, 2008 Cheryl Yager.
1 Exposure Stress Testing CWG/MCWG Suresh Pabbisetty, CQF, CSQA. ERCOT Public June 12, 2014.
1 Credit Parameters Review TAC July 2, Protocol Section , “Credit Requirement for DAM Bids and Offers” specifies: Credit Requirement for.
1 Timeline for Activities in Breach CWG/MCWG ERCOT Public September
Nodal Credit Monitoring and Management – Business Requirements ERCOT CREDIT Department September 28, 2006.
WMS – Nodal Credit Integration Start Up May 19,
Capacity Forecast Report Fall Update Sean Chang Market Analysis and Design Suresh Pabbisetty CQF, ERP, CSQA Credit CWG/MCWG December 16, 2015 ERCOT Public.
1 NPRR638 Back-casting Updated and Supplementary Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public May 20, 2015.
Credit Exposure and Expected Loss update Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit February 17, 2016.
ICE Futures ERCOT North Hub Liquidity Analysis Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit April 20, 2016.
Revisions to Credit Exposure Calculations by using Electricity Futures Prices Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit May.
Credit Updates Vanessa Spells Credit Work Group ERCOT Public May 18, 2016.
Credit Exposure Analysis using ICE Prices Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit April 11, 2016.
Market Credit Working Group update to the Wholesale Market Subcommittee 3/02/
MCWG Update to WMS 3/9/2010. Exposure / Collateral Update Nodal Total Potential Exposure reported by ERCOT as of 1/31/11 remains less than Zonal Estimated.
Credit Exposure Analysis using ICE Prices Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit April 20, 2016.
ICE Futures ERCOT North Hub Liquidity Analysis Suresh Pabbisetty, FRM, ERP, CQF, CSQA. Lead Technical Analyst, Credit April 11, 2016.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Settlement Statements and Calendar Business Requirements Settlements.
Credit Reports Vanessa Spells COPS Meeting ERCOT Public
2017 Seasonal Adjustment Factors
Credit Updates Vanessa Spells Credit Work Group ERCOT Public
NPRR829 Incorporate Real-Time Telemetered Net Generation for Non-Modeled Generation into the Real-Time Liability Estimate ERCOT PRS Meeting May 11, 2017.
Presentation transcript:

1 NPRR638 (Seasonality) Back-Cast Results CWG/MCWG Suresh Pabbisetty, ERP, CQF, CSQA. ERCOT Public October 3, 2014

2 Background Background: At its September 17, 2014 meeting, CWG/MCWG requested analysis to estimate the impact of using the maximum, instead of the average, of recent statements to compute RTLE and DALE. ERCOT Public

3 Back-Casting Model Model Assumptions: Prices do not reflect replacement of historic price caps with current price caps which is in the NPRR. Model does not include the look-back of rolling averages over previous 40 days as proposed in the draft NPRR. This increases volatility of back-cast values. Model uses standard M1 extrapolation value. This will tend to understate back-tested credit exposure values. Prices do not include ORDC price adders. ERCOT Public

4 Back-Casting Prototype Results – DAM Price Spread DAM price spread was calculated as the difference between DAM Price Estimate based on proposed methodology and actual DAM Settlement Point Prices. ERCOT Public

5 Back-Casting Prototype Results – RTM Price Spread RTM price spread was calculated as the difference between the RTM price estimate based on NPRR 638 and actual RTM Settlement Point Prices. Summer prices are higher under NPRR 638. ERCOT Public

6 Back-Casting Prototype Results – RTLE comparison Seasonality RTLE using average statement amount compared to max. ERCOT Public Notes: Data points represent one day per month only.

7 Back-Casting Prototype Results – RTLE comparison RTLE based on NPRR638 methodology compared with RTLE based on current Protocol calculations. ERCOT Public Notes: Data points represent one day per month only.

8 Back-Casting Prototype Results – DALE comparison Seasonality DALE using average statement amount compared to max. ERCOT Public Notes: Data points represent one day per month only.

9 Back casting Prototype Results - Summary ERCOT Public DAM and RTM spreads: DAM and RTM prices are materially higher during summer peaks DAM and RTM spreads generally follow seasonal patterns Methodology does not account for unexpected price spikes RTLE comparison: Proposed methodology RTLE (Real-Time Liability Extrapolated) is higher during summer months and generally lower during non- summer months. Aggregated RTLE based on NPRR638 methodology appears more volatile than current methodology due to differential in lookbacks which is under review. Based on earlier back-testing, RTLE increases in the aggregate for a majority of Counter-Parties (decreases primarily for generators).

10 Questions ERCOT Public