Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Managing Construction Risks
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
Chapter 15 Closing the Bid. Objectives Upon completion of this chapter, you will be able to: –Describe the estimate summary process –Describe items that.
Presenter: Victor C. Tyler, P.E. Estimating and Bidding Strategies that Drive Best Practices.
Chapter 12 Estimate Summaries and Bids. Bid Summaries The format of the summary depends for what the estimate is to be used. –Ordering materials –Calculating.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Time Is Money - Delay Claims in Construction June 18, 2012
Closeout (Preparing for the End)
Presented By: John D. Miller
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
Contractors’ Day, June 2008 to the Framework Partnership Agreement & the Specific Grant Agreement Financial Guidelines for co-ordinators and co-partners.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Project Procurement Management
National Aeronautics and Space Administration ANSI/EIA-748-B Earned Value Management Systems (EVMS) 32 Guidelines ANSI/EIA-748-B Earned Value.
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Using Cost Accounting Documents in Construction Claims and Litigation By William Schwartzkopf Sage Consulting Group.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
ANSI/EIA -748 EVMS 32 Guidelines National Aeronautics and Space Administration.
Delay Claims from the Owner and Contractor’s Perspectives
XII- COST CONTROL, MONITORING & ACCOUNTING
EM15 – Contractors COST MANAGEMENT
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Valuations and interim certificates. Purpose Value the works taking account of: – the physical work done on site; – any extra work ordered by the client;
March 2005 UMORS 1 UMORS Vander Kooi and Associates, Inc Ultimate Multiple Overhead Recovery System.
State Auditor’s Office Change Order Pricing Practices Performance Audit of Eight Local Governments Puyallup City Council February 7, 2012 Chris Cortines,
Dryden Flight Research CenterNovember 8, Aerospace Ground Equipment Support Services Price Proposal & Evaluation Linda Gaugler Mathematician (Lead)
The Audit Toolkit - Empowering Employers To Take Control© The audit toolkit was developed to help employers focus on the key points of preparing for an.
KEEPING LABOR AND OVERHEAD COSTS DOWN Controlling Labor and Overhead Costs as a Long Term Strategy.
Contract Pricing Methods Ch 2. Lump Sum –Contractor bids 1 price for entire project –Estimate needs to be detailed –Design needs to be finished before.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Construction Contracts and Project Delivery Methods
Richard E. Thompson II, Esq.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Measurement and Payment
King Fahd University of Petroleum & Minerals
Nguyễn Văn Tâm Bsc of Civil Engineering, 1997 (CTU, VN) Lecture notes: TU Delft, Holand Geotextile and Structural Experiment, 2000 Construction equipment.
1 Expenditure Documentation Review. 2 The Purpose of the Expenditure Documentation Review Beginning with Fiscal Year , the Office of Family Planning.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
PwC Service Contracting DCAA Interests & Initiatives March 31, 2008.
Chapter 3 Financial Management Part 2 BCN 4772 Summer 2007.
Marketing & Tendering. Budget Forecasting Profit is the key to Business Success – Profit is amount of money after all expenses Materials Labour Insurances.
Cash Flow Analysis Part 2 King Saud UniversityCE511- Construction Planning & Control 1.
Jeff Sestokas Estimating the Budget and Cost (Part 2) Project Management for ARA Engineers and Scientists Developing an Estimate from the Top Down.
Volvox Understanding the Budget Angela Pettit – Contracts Officer.
Measurement and Payment Module #5 Prepared by Dr. Randy R. Rapp July 2005.
Copyright  Oracle Corporation, All rights reserved. ® 11 i Overview of Cost Management.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Construction Auditing Tuesday, September 15, :00-5:15 pm Presented By: John Humphries Kelly Business Consultants 8084 Watson Road, Suite 200 St Louis,
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
Measurement and Payment
Cost Estimating and Budgeting. Cost Estimating Initial Cost Estimate Initial Cost Estimate Underestimates are Initially a Big Problem Underestimates are.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Final Accounts. Accounts Submissions Last Bill for Contracted Works ( excluding Retention) Presented at Practical Completion Practical Definition dependant.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
COST PLUS. Reasons for Cost-Plus Can’t agree on a price Specialty work Notice of Changed Conditions.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Is There a Proper Accounting for Indirect Costs?
What Small and Emerging Contractors Need to Know Understanding Funds Administration © Copyright 2017 NASBP.
Project Manager Best Practices Workshop ASA Metro Washington
Project Manager Best Practices Workshop ASA Metro Washington
ARCH 435 PROJECT MANAGEMENT
Project Manager Best Practices Workshop ASA Metro Washington
C2 Follow the Capital Risks
“RED FLAGS” for Construction Payment Application Reviews Henry L
Presentation transcript:

Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005

June 27, 2000Rubino & McGeehin Consulting Group2 Cost Expert’s Role Understand the story behind the claim Understand the story behind the claim Understand the pricing of the claim Understand the pricing of the claim Understand the contractual relationships between the various parties Understand the contractual relationships between the various parties Analyze the cost data and underlying support to assess reasonableness and accuracy of the claim Analyze the cost data and underlying support to assess reasonableness and accuracy of the claim Assess the pricing methodologies for reasonableness Assess the pricing methodologies for reasonableness

June 27, 2000Rubino & McGeehin Consulting Group3 Typical Claim Issues Delay Delay Suspension Suspension Extra Work Extra Work Differing Site Conditions Differing Site Conditions Defective Specs Defective Specs Acceleration due to Delay Acceleration due to Delay Cumulative Impacts Cumulative Impacts

June 27, 2000Rubino & McGeehin Consulting Group4 Typical Claim Methods Total Cost Total Cost Modified Total Cost Modified Total Cost Inefficiency Percentage Estimates – Job Personnel/Experts/Published Manuals Inefficiency Percentage Estimates – Job Personnel/Experts/Published Manuals Measured Mile Measured Mile Other Discretely Priced Approaches Other Discretely Priced Approaches –Extra Work –Escalation –Overtime Premium due to Acceleration

June 27, 2000Rubino & McGeehin Consulting Group5 Typical Claimed Cost Types 1. General Conditions Costs – Extended Site Support and Supervision Extended Site Support and Supervision Additional Support due to Acceleration Additional Support due to Acceleration 2. Equipment Costs – Extended Time Extended Time Additional Extra Work Hours Additional Extra Work Hours Additional Fleet Items Brought to Job Additional Fleet Items Brought to Job Acceleration or Sequencing Changes Acceleration or Sequencing Changes

June 27, 2000Rubino & McGeehin Consulting Group6 Typical Claimed Cost Types (cont.) 3. Direct Labor Costs – Inefficiency Inefficiency Loss of Productivity Loss of Productivity Extra Work Extra Work 4. Home Office Overhead – Eichleay Eichleay Others Others 5. Subcontractor Costs – Pass thru Claims 6. Materials Costs – Increased Quantities

June 27, 2000Rubino & McGeehin Consulting Group7 What Value Does a Good Cost Expert Provide? Understanding of Construction Accounting and Impacts on Claims Understanding of Construction Accounting and Impacts on Claims Ability to Drill into Accounting Detail to Identify Actual versus Estimated Costs Ability to Drill into Accounting Detail to Identify Actual versus Estimated Costs –Equipment at Actual in Lieu of Rate Manuals –Labor Rates, including Insurance and other Fringe Issues Ability to Fully Evaluate and Consider Accounting Impacts on Claim Method Ability to Fully Evaluate and Consider Accounting Impacts on Claim Method –Eichleay Example on Billings versus Revenues Ability to Identify Cost Variances and Trends and Compare to Claimed Amounts and Events Ability to Identify Cost Variances and Trends and Compare to Claimed Amounts and Events

Construction Accounting Flow Divisional General Ledger Project Specific Job Cost Ledger Labor and Labor Burden Costs Permanent Material Costs Subcontractor Costs Equipment Costs Timesheets, Daily Reports Labor Distribution Reports Check Stubs, Cancelled Checks Burden Allocation Calculations Gov’t Filings, WC Audits, Other Invoices Purchase Orders Check Stubs Cancelled Checks Payment Applications Check Stubs Lien Release Cancelled Checks Rental Roll, Equipment Utilization Reports Contractor Daily Reports Internal Rate Memo and Support Vendor Invoices & Cancelled Checks Field Trailer Compound Vendor Costs and Typical Support Audited Corporate Financial Statements Divisional Financial Statements General Conditions Costs Supervisory Labor Costs and Typical Related Support

June 27, 2000Rubino & McGeehin Consulting Group9 General Conditions Costs Home Office Overhead versus Field Office Overhead (“FOO”) Home Office Overhead versus Field Office Overhead (“FOO”) –How are they different? –Items for Consideration What should be included in Field Office Overhead? What should be included in Field Office Overhead? –Thoroughly Check the Contract - twice (AIA Contract often Prohibits Home Office Folks from Charging Job) –Home Office versus Field Office Personnel Markup or Daily Rate Approach? Markup or Daily Rate Approach? –One or the other –If Use Both, Must Apply a Credit –One Time Costs – a few examples

June 27, 2000Rubino & McGeehin Consulting Group10 Extended General Conditions – Coordination of Cost and Scheduling Difference between incremental supervision and extended supervision Difference between incremental supervision and extended supervision Discussion of delay periods Discussion of delay periods –No damage for delay, Excusable, Compensable, Non-Compensable –Actual versus Claimed time periods –Post Completion field overhead –Effect of LD’s and/or overhead paid on previous changes –Weather days during extended period

June 27, 2000Rubino & McGeehin Consulting Group11 Equipment External versus Internal External versus Internal –Very different analysis required –Internal Rates may have some embedded overhead, profit recovery Is External Really External? Is External Really External? Internal Rates Internal Rates –How are rates set and charged to job cost –Comparison of charged and actual rates –How Internal Rates Used in the Bid? Appropriateness of Internal Rates - Contract Appropriateness of Internal Rates - Contract

June 27, 2000Rubino & McGeehin Consulting Group12 Owned Equipment Pricing Internal Rate Alternatives – Blue Book Internal Rate Alternatives – Blue Book Application of Blue Book Rates Application of Blue Book Rates Consistency of claim pricing and accounting methodologies Consistency of claim pricing and accounting methodologies –i.e. Was generator direct costs to job at 10K and then discretely claimed on an hourly basis resulting in a claim of $15K?

June 27, 2000Rubino & McGeehin Consulting Group13 Owned Equipment Utilization Hours – Contemporaneous Documents Hours – Contemporaneous Documents –Usage Reports for Hours – Rental Rolls, Daily Reports, Equipment Utilization Reports, etc. Rental Rolls, Daily Reports, Equipment Utilization Reports, etc. –Operating Time versus Standby Time – Need to know the difference and how the contractor accounts for the difference

June 27, 2000Rubino & McGeehin Consulting Group14 Equipment Collaboration Discussion of claimed equipment Discussion of claimed equipment –Extra Work or Delayed Work? Standby versus Operating Standby versus Operating –Stored Equipment versus Standby Equipment –Variations in planned and actual equipment usage Bid small loader, use large loader Bid small loader, use large loader Discussion of support for claimed hours, time frames Discussion of support for claimed hours, time frames –Daily Reports, Equipment Utilization Reports, Etc.

June 27, 2000Rubino & McGeehin Consulting Group15 Labor Costing Issues Direct Labor Versus Supervisory Labor Direct Labor Versus Supervisory Labor General Foremen – Direct or Overhead? General Foremen – Direct or Overhead? Provisional versus Actual Labor Rates Provisional versus Actual Labor Rates Overtime Premiums Overtime Premiums Evaluation of Claimed and Bid Wage Rates and Burden Markups Evaluation of Claimed and Bid Wage Rates and Burden Markups How does claimed labor burden markup compare to actual cost? How does claimed labor burden markup compare to actual cost?

June 27, 2000Rubino & McGeehin Consulting Group16 Labor Charging Issues What contemporaneous information is maintained by contractor to account for time? What contemporaneous information is maintained by contractor to account for time? –Timesheets, daily reports, job cost reports, etc Does labor data used in claim quantification make sense based on accounting information? Does labor data used in claim quantification make sense based on accounting information? Does Contractor Separately Account for Rework, Backcharge Work, etc.? Does Contractor Separately Account for Rework, Backcharge Work, etc.?

June 27, 2000Rubino & McGeehin Consulting Group17 Labor Collaboration Discussion of Claimed Hours Discussion of Claimed Hours –Hours expected versus actual –Timing of hours relative to the claim events –Are labor overruns consistent with claimed areas? Time sequencing of labor hours using accounting data Time sequencing of labor hours using accounting data Discussion of bid and actual productivity rates Discussion of bid and actual productivity rates

June 27, 2000Rubino & McGeehin Consulting Group18 Home Office Overhead Costs Markup Method Markup Method Eichleay – Eichleay – 1. 1.Delays sudden and of uncertain duration (standby) 2. 2.Stage of project completion 3. 3.Supervisory personnel dedicated during delay period 4. 4.Effects of change orders or substituted work

June 27, 2000Rubino & McGeehin Consulting Group19 Collaboration on Home Office Overhead Discussions regarding timing of standby period Discussions regarding timing of standby period –Ability to mitigate Discussion regarding replacement work Discussion regarding replacement work –Other active jobs and staffing –Change Order Work

June 27, 2000Rubino & McGeehin Consulting Group20 Subcontractor Costs Understand Subcontract Agreement Lump Sum, Cost Plus Understand Subcontract Agreement Lump Sum, Cost Plus Schedule of Values Billings – AIA G702, G703 Schedule of Values Billings – AIA G702, G703 Retention – Why do we care? Retention – Why do we care? Waivers Waivers GC, Equipment, Labor Issues all apply GC, Equipment, Labor Issues all apply

June 27, 2000Rubino & McGeehin Consulting Group21 Summary Need dialogue between experts to Need dialogue between experts to –Coordinate efforts –Develop mutual understanding of claim and job events and costs Accounting data can be used by entitlement/scheduling expert to analyze claims Accounting data can be used by entitlement/scheduling expert to analyze claims

June 27, 2000Rubino & McGeehin Consulting Group22 Summary (cont.) Actual Cost and actual losses preferred method to measure damages Actual Cost and actual losses preferred method to measure damages –Cost expert’s job is to determine actual cost and loss on project, subject to contract provisions giving definite approach to pricing of an element of cost Questions Questions