Network Operating Committee Meeting December 18, 2015 1.

Similar presentations


Presentation on theme: "Network Operating Committee Meeting December 18, 2015 1."— Presentation transcript:

1 Network Operating Committee Meeting December 18, 2015 1

2 Roll Call –Identify all NorthWestern Employees in presentation room. –Identify All NorthWestern Energy Employees on the Phone. –Identify All Network Customers on the phone. Who is participating in the meeting? 2

3 Opening Remarks Casey Johnston Director of Grid Operations & Services 3

4 WEQ Glossary Definition –“Network Operating Committee” o Committee responsible for coordinating operating criteria to determine each party’s responsibilities under the network operating agreement. What is a Network Operating Committee? 4

5 Who is the Network Operating Committee? –The Network Operating Committee shall be composed of representatives from the Transmission Customers taking service under the Tariff and the Transmission Provider or their Designated Agents. Who is the Network Operating Committee? 5

6 ELECTRIC INFORMATION REGISTRY (EIR) 6

7 REVIEW POSTINGS ON OASIS 7

8 EIR Be mindful of your expiration date. Don’t let your entity code expire. Cost of Emergency Run $1,000.00 EIR 8

9 III. OATT BUSINESS PRACTICES DESIGNATIONS/TERMINATIONS ASR/TSR OASIS 9

10 IV. Rolling Service Over – We remind you to enter a new TSR(s) at least one year prior to the expiration. Rolling Service Over 10

11 V. If you are planning a scheduled outage send us an email so we know. Planning an Outage? 11

12 VI. Cathy Mathews in our planning department sends these out to customers in January each year please return in accordance with her instructions. * Remember This does not guarantee you Transmission. Forecast requirement 12

13 VII. If your load is going to increase by greater than 1MW you are required to apply for Transmission Service for the increase in load. * Schedule to your load. * Firm Transmission is listed in your contract and is what you designate. Secondary (6NN) Network Service is NOT Firm. Is Your Load Growing? What is Firm Transmission? 13

14 VIII. 03-01-2016 to 03-01-2017. Agreements are in the process of being Filed with FERC. We anticipate the 03-01-2017 to 03- 01-2018 Contingency Reserves to be rolled out in similar fashion. August 2016. CONTINGENCY RESERVES 14

15 IX. North American Energy Standards Board Wholesale Electric Quadrant Business Practice Standards Version 003 Issued 9/18/2014 Published 9/24/2014 Effective 10/24/2014 NITS 04/24/2016 – Compliance Date VERSION 003 15

16 NAESB Links https://www.naesb.org/misc/NAESB_ Nonmember_Evaluation.pdfhttps://www.naesb.org/misc/NAESB_ Nonmember_Evaluation.pdf https://www.naesb.org//pdf/ordrform. pdfhttps://www.naesb.org//pdf/ordrform. pdf 16

17 002-5.10.2 NITS IMPLMENTATION REQUIREMENTS –“No NITS request shall be permitted using PTP reservation templates after S&CP VERSION 2 conversation date.” o NO TSR’s for Network Customers permitted after 4/24/2016 NAESB Business Practice Standards Version 3 17

18 Timeline –1/24/2016 TP’s and customer resolve and data issues. –1/31/2016 Web Smart OASIS in Production. –2/01/2016 Release of NITS to Demo for training –03/01/2016 Release of NITS to Production NITS ON OASIS 18

19 IMPLEMENTATION OF NITS ON webSmartOASIS 19

20 Timeline Continued: –03/24/2016 – Data Migration Completed –04/24/2016 – NITS Transition Compliance Date NITS ON OASIS 20

21 QUESTIONS AND ANSWERS? Q&A 21

22 22