1 PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
How to get reliable PSB sieve and PS&SPS dumps for 2006?

2 Overview Internal dumps Sieve Beam stoppers TIDVG Summary 13.01.05
PS/SPS days

3 PS internal dumps Installed dump 47 operational (control unit problems) Dump 48 mechanically ok Spare in radioactive storage, control problem? Transportation problem solved, lifting device will be tested these days Working space (bunker, INB) found by R. Brown, ready within 3 weeks PS/SPS days

4 PS internal dumps Reference dump Dump 48 mechanically updated
Water bellows to be changed Water and electrical connectors to replace Cabling to be replaced Power supply to be changed Check capturing magnet Test intensively Standardise control units Reference dump PS/SPS days

5 PS internal dumps Installed dump 47 stays Installation of dump 48
Upgrading of spare dump Depending on schedule start up with dump 47 or replacement of dump 47 by spare dump Upgrading of dump 47 New supports to simplify the alignment procedure PS/SPS days

6 PS Sieve Working since 1977 Originally designed for 1 mio. cycles, which has been reached in 1981 Material Graphite Movement with air pistons Water cooled Not working reliably No spare parts! PS/SPS days

7 PS Sieve Short term (2005): Demount sieve from the machine
Maintenance on mechanical parts (Piston, water and air connections, bearings) Adjust air and water pressure after lab tests Reinstall sieve PS/SPS days

8 PS Sieve Long term (2006/2007): Prepare two additional units with small design changes Re-use vacuum tank or build new modified vacuum tanks? Replace Graphite with CFC Replace sieve actually installed Prepare one complete spare unit PS/SPS days

9 PS beam stoppers 33 stopper in the PS complex Different types
Stoppers in good general condition Take stock of spare components Annual maintenance of installed stoppers PS/SPS days

10 SPS TIDVG Internal beam dump Length 4.5m C / Cu / Al / W core
22 tons cast iron shielding water cooled vacuum temp. measurement vertical deflection PS/SPS days

11 SPS TIDVG Ti foils to prevent from C particle contamination
Ti foil stretched over dump core materials 5 foils with overlap, not closed Each foil end is lifted PS/SPS days

12 SPS TIDVG Damaged Ti foil Length of damage: 30 mm
Height of foil displacement: 10 mm Position: End of first foil/ circulating beam PS/SPS days

13 SPS TIDVG Proposed modification:
Tests on graphite blocks covered by Ti foil (10-15mm from the edge). If successful remove all Ti foils by cutting with special tool on spare TIDVG. Same intervention on spare core Modify the spare cast ion body of the TED to get a full spare TIDVG Store the damaged TIDVG as back up Installation of modified dump in April 2005 PS/SPS days

14 Summary PS Dumps: Two upgraded dumps ready for startup 2006, spare in stand by. PS sieve: 3 month to maintain the existing sieve, construction of a spare on the same design principle (in 2006). PS beam stoppers: Inventory and annual maintenance, spare stoppers for 2006/07. TIDVG: “Light” solution for time, manpower and budget reasons. Reinstallation within 3 months. Preparation of spare 2007. PS/SPS days