1 TELUGU GANGA PROJECT (2 years period)
SRISAILAM DAM FRL: +885’ MDDL : 834’ VELIGODU BALANCING RESERVOIR FRL ’ Cap: 16.95TMC Ayacut : 1.25L Acs Sill: +841’ LINK CANAL KM T G P M A I N C A N A L KM SOMASILA PROJECT Ayacut: 4.14 Lakh Acres Cap: 78TMC FRL: +330’ KANDALERU RESERVOIR Cap: 68.03TMC FRL : +279’ Ayacut: 3.00L Acrs RESERVOIR POONDI SRI POTULURI VEERA BRAHENDRA SWAMY BALANCING RESERVOIR Capacity: FRL 730’ Ayacut: 1.5L Acs CHINNA MUKKAPALLI REGULATOR LINING PENNA RIVER LINING & DISTRIBUTARIES 7.83Km APPROACH CHANNEL SRMC 16.225Km SRBC (5000 c/s) Nippulavagu BANAKACHERLA REGULATOR Pothireddypodu Head Regulator Sill : (4 existing + 3 Addl) 3.4Km KRISHNA RIVER 45.172Km Km 25.275Km AP – TN Boarder Kurnool-Cuddapah District Boarder 11150 c/s Link canal 1000 c/s Capacity: 2.75 TMC 5000 C/s SR2 SR1 Capacity TMC Capacity TMC CC LINING COMPLETED Total length of the TGP Canal- 408 KM (from Pothireddypadu head regulator to AP Border Excavation of Main canal formation 4 balancing reservoirs (Velugodu Balancing Reservoir, SPV Balancing Reservoir, Somasila & Kandaleru Balancing Reservoir) and CM & CD works completed Lining of Balance Main Canal ( KM completed), balance distributory system and branch canal etc covered in 9 packages will be completed in 2 years period. Total ayacut proposed 5.75 Lakh acres Ayacut created : 1,00,000 Acres Balance ayacut of : 4.75 Lakh acres will be created by 6/2006

2 TELUGU GANGA PROJECT 1 Project Profile: 408 km length canal for Pothieddypadu Head regulator to Andhra Pradesh, Tamil Nadu Border with 4 BRs Viz., Velugodu, SPVBR, Somasila and Kandaleru BRs. 2 Administrative Sanction : G. O. Ms No. 2, Dt: for Rs Crs. G. O. Ms. No. 44, Dt: for Rs Crs, Govt.Memo.No.7019/bids of/14-2/05 dt for Rs Crs., Govt.Memo.No.7109/Bidsof/ , dt for Rs Crs. 3 No. of EPC Packages 9 No 4 Agreement value of 9 packages Rs Crs. (Inc. for 4 old ongoing works) 5 Budget provision for Rs Crs. 6 Expenditure of the project 2004 – 05 Rs Crs. 2005 – 06 Rs Crs. Cum. Exp. Rs Crs 7 Utilisation 29 tmc of Krishna flood waters through Velugodu and SPVBR 30 tmc of Penna flood waters through Kandaleru BR 15 tmc of divert water to Chennai for drinking purpose

3 8 I.P. to be Created : 5.75 Lakh Acres (Kurnool: 1.08 Lakh Acres, Kadapa: 1.67 Lakh Acres, Nellore: 2.54 Lakh Acres,Chittoor: 0.46 Lakh Acres) 9 Ayacut New Ayacut 6,22,335 acres 10 Land Acquisition Required 70,000 acres Requisitioned 68,920 acres Acquired 59,600 acres 11 Forest land 1838 acres 1,838 acres 1,342 acres 903 acres 12 Estimated Cost of LA Rs Crs. 13 Estimated Cost of R & R Rs Crs. 14 Mob. Advance (Rs. in Crores) Paid Recovered Total 15 Target date of completion Khariff /2006

4 TELUGU GANGA PROJECT Present Status Ayacut: 5.75Lakh Acres
29 TMC – Krishna Flood Flow, 15 TMC – Drinking Water to Chennai City Present Status Ayacut: 5.75Lakh Acres Balance Works Kurnool L Acres Cudapah L Acres Nellore L Acres Chittoor L Acres Total L Acres i). Lining of Balance length of Main Canal ii). Balance Protection works of Balancing Reservoirs. iii). Balance works of Branch Canals & its distributary systems i v). No. of Packages : Category-I - 5 Packages Category-II - 4 Packages. Entire length of 408 Km of Main Canal from Pothireddy padu Head requlator to AP boarder with formation of 4 Balancing Reservoirs (Velugodu BR, SPVBR, Somasila & Kandaleru BR) and lining of main canal for a length of Km completed. (13Km in Kurnool, Km in Kadapah, 29Km in Chittoor & 62Kms in Nellore). IP Created …. About 1 Lakh acres. With the completion of 9 packages, the balance 4.75 Lakh acres will come in to irrigation potential by Kharif 2006.

5 TELUGU GANGA PROJECT PKG No./ Category Description Awarded PACKAGES
CATEGORY-I : 5 Nos. (Rs Crs. for 4 Packages) CATEGORY-II: 4 Nos. (Rs Crs.) PKG No./ Category Description Awarded CAT-I Construction of SPVBR Left canal up to Porumamilla Tank and its distributary system, lining in Vulnerable reaches of TGP Main Canal etc. M/s. IVRCL – SEW & PRASAD Execution of SPVBR left canal beyond Porumallilla Tank from Km to Km including distributaries and SPVBR right canal from Km to Km and its distributaries, including CM & CD Works to irrigate 96,300 Acres 39 CAT-II Construction of Branch Canals No. 2A, 2B & 4 OF SATYA SAI GANGA CANAL together with distributary system creating an IP of 42,027 Ac M/s M.S.K. SURYACON 40 Construction of Branch Canals No. 5 & 5A OF SATYA SAI GANGA CANAL together with distributary system creating an IP of Ac M/s PIONEER BUILDERS 50 Providing Lining of TGP Main Canal Km to Km including widening and also to link canal from KM to KM (up to in fall point VBR) M/s E.C.C.I. & M.R.K.R.(J.V.) 51 Providing site and bed lining of TGP Main Canal from Km to Km excluding lining already done & including widening at required places M/s S.V.E.C. Constructions Ltd. 9 CC Lining of SKFF Canal between KM to KM and construction of KR Left Canal and Branch Canal No. 1 together with distributaries and field channels of Satya Sai Ganga canal to create Irrigation Potential of 22,400 Acres M/s K.C.L.-J.C.C.G 10 Providing CC Lining from Km 0.00 to km. and construction of branch canals Nos. 6 & and balance canal No. 7 together with distributary system of Satya Sai Ganga canal to create Irrigation Potentional of 69,548 Acres M/s. Harvins Const.Pvt. Ltd 11 Providing CC Lining from Km 42.4 to Km of Satya Sai Ganga cana, construction of tail channel with CM & CD works for escape regulator at KM etc., and construction of branch canals Nos. 8A, 8B & 9 together with distributary system to create irrigation potential of 53,000 Acres M/s ZVSTROY-GDD (JV)

6 TELUGU GANGA PROJECT Package No.50 / Cat-II : Lining to main canal from Km to Km i.e. upto Velugodu Balancing Reservoir. Lining of main canal from Km to Km Construction of high level D.L.B. at Km across Nippulavagu near Velpanur. Contractor Name : M/s E.C.C.I. & M.R.K.R.(J.V.) Agreement Amt. : Rs Crs. Agreement Date : Period of Completion : 24 Months (8 Mile Stones) Target date of Completion: 7/2007 Expenditure : Rs Crores (Inc. Mob. Adv.) Bottle Necks : Water released into Canal

7 TELUGU GANGA PROJECT Package No.51 / Cat-II :
Lining to Main canal from Km to Km i.e., upto Kurnool-Kadapa Border excluding where lining is already completed Name of the Contractor : M/s SVEC Constructions Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months (8 Mile Stones) Target date of Completion : 3/2007 Investigation : Completed Design : Approved Execution : 17 Km lining completed against Kms Qty. of work done : Sq.m against Sq.m Execution (Canal lining) : Km length in progress against Km Expenditure : Rs Crs Rs Crs. Cum. Exp. Inc. Mob. Adv. - Rs Crs. Bottlenecks : Water released into the canal. Work stopped.

8 TELUGU GANGA PROJECT Package No. 2
Construction of SPVBR Left Canal upto Porumamilla tank and the distributory system. Construction of Irrigation canal taking off from SR-II and its distributory system. Construction of Chennamukkapalli Canal and lining vulnerable reaches of main canal in Kadapa District. Name of the Contractor : IVRCL,SEW&PRASAD (JV), Hyd. Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months (8 Miles Stones) Target date of Completion : 10/2006 Investigation (canal) : Completed Designs (Canal) : Approved Execution : 152 Km in progress against total length of 434 Km Structures : 45 Nos. against 48. No. of Machinery deployed : 118 Nos (Poclains-15, Tippers-70, Dozers-6, SFR-3, VRR-4, Water Tankers-20) Qty. of earth work done : Lakh cum against lakh cum Qty. of concrete work done : 1.15,5 Lakh cum against 3.54 Lakh cum Expenditure : Rs Crs Rs Crs. Cum. Exp. Inc. Mob. Adv. - Rs Crs. Land Acquisition : Required Ac., Requisition – 1387 Ac., Acquired: Ac.

9 TELUGU GANGA PROJECT Name of the Contractor : IVRCL,SEW&PRASAD (JV), Hyd. Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months (8 Mile Stones) Target date of Completion : 10/2006 Package No.3 / Cat - I SPVBR Left Canal beyond Porumamilla tank and SPVBR right canal. Investigation : Completed Designs (Canal) : Approved (Structures) : 66 Nos. against 314 Nos. Execution : 60 Km in progress against total length of 120 Km No. of Machinery deployed : 174 Nos (Excavators-35, Dumpers-100, Dozers-8, Crusher-1, Batching Plant-2 & Mixer Machines-20 etc) Qty. of earth work done : 20 Lakh cum against 54 Lakh cum Qty. of concrete work done : 22,500 cum against 5,11,750 cum Expenditure : Rs Crs Rs Crs. Cum. Exp. Inc. Mob. Adv. - Rs Crs. Land Acquisition : Required Ac; Acquired Ac.

10 TELUGU GANGA PROJECT (Satya Sai Ganga Canal)
Pkg.No. 10 : Providing Cement Concrete lining to Satya Sai Ganga Canal with paver in between Km.0.0 and Km and construction of Branch canal No.6, balance works of branch canal no.7 together with the distributary system creating direct irrigation potential of 69,548Acs. Including investigation, design and estimation. Name of the Contractor : M/s. Harvins Const.Pvt. Ltd. Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months (8 milestones) Target date of completion : 3/2007 Investigation : 181 Kms against Kms Designs : H. Ps approved 22.6 KM against KM Structures : 15 Nos. against 800 Nos. Expenditure : Rs Crs. (Inc.Mob. Adv.) Land Acquisition : Required Acres, Acquired Acres

11 TELUGU GANGA PROJECT (Satya Sai Ganga Canal)
Pkg.No. 11/Cat-I : Lining to Satya Sai Ganga Canal in between Km and Km , Construction of tail channel with CM&CD works for escape regulator at Km , Construction of Satya Sai Canal and creating direct Irrigation potential of 53,000Acres including investigation, design and estimation. Name of the Contractor : Z.V. Story - - GDCL (JV) (P) Ltd. Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months (8 milestones) Target date of completion : 3/2007 Investigation : 320 Kms length against 320 Kms. Designs : 165 Kms against 320 Kms, HPs approved Strucutures approved : 200 Nos. against 900 Nos. Execution : Kms length against 171 Kms. Structures : 1 No. against 900 Nos. Qty. of earth work done : 5.00 lakh cum against Lakh cum Qty. of concrete work done : 29,324 cum against 2.14 Lakh cum No. of Machinery : 202 (Excavators-19, Tippers-81, Mixers-27, Paver-1 etc.) Expenditure : Rs Crs Rs Crs. Cum. Exp. Inc. Mob. Adv. - Rs Crs. Land Acquisition : Required 1299 Ac., Acquired Ac.

12 TELUGU GANGA PROJECT (SKFF)
Pkg.No. 9 : Providing cement concrete lining with paver to Somasila Kandaleru Flood Flow Canal between Km and Km , Construction of K.R. Left Canal, Branch canal No.1 of Satya Sai Ganga Canal together with distributary system creating an irrigation potential of 22,400 Acres Name of the Contractor : M/s. K.C.L. JCCG (JV) Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months (8 milestones) Target date of completion : 3/2007 Investigation : Km length against 346 K.M Designs approved : Kms length against 346 Kms Structures : 13 Nos. against 1025 Nos. Execution : Kms length against 346 Kms. Structures : 2 Nos. against 1025 Nos. Qty. of earth work done : 23,00,000 cum against 46,94,000 cum Qty. of concrete work done : 0.23 Lakhs cum against 3.7 Lakhs cum. No. of Machinery : 95 Nos. (Excavators 10, tippers 30, concrete mixture 12 etc.) Expenditure : Rs Crs Rs Crs. Cum. Exp. Inc. Mob. Adv. - Rs Crs. Land Acquisition : Required 1235 Acres, Acquired 28.77

13 TELUGU GANGA PROJECT (Satya Sai Ganga Canal)
Pkg.No. 39 : Construction of Branch canals No.2A, 2B & 4 of Satya Sai Ganga Canal together with distributary system creating an irrigation potential of Acres including investigation, design & estimation. Name of the Contractor : M/s. MSK Surya Con.(JV) Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months (8 milestones) Target date of completion : 3/2007 Investigation : Km length against Km. 375 Designs : Km length against 375 Km Structures : 59 Nos. against 652 Nos. Execution : 20 Kms length against 375 Kms. Structures : 1 No. against 652. Qty. of earth work done : 5.15 Lakhs cum against Lakhs cum Qty. of concrete work done : Lakh cum against 1,31,660 cum No. of Machinery : 33 Nos. (Excavators-5, Dumpers-7, concrete mixers-3, other mach.-10) Expenditure : Rs Crs. (Inc. Mob. Adv.) Land Acquisition : Required Acres, Acquired 40Acres

14 TELUGU GANGA PROJECT (Satya Sai Ganga Canal)
Pkg.No. 40 : Construction of Branch canals 5 and 5A of Satya Sai Ganga Canal together with distributary system creating an irrigation potential of 77,640 Acres including investigation, design & estimation. Name of the Contractor : M/s. Pioneer Builders Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months (8 milestones) Target date of completion : 3/2007 Investigation : 394 Km length against Km Designs : Km length against Km Structures : 400 Nos. against 2287 Nos. Execution : 50 Kms Length against Kms. Structures : 63 Nos. against 2287 Nos. Qty. of earth work done : Lakhs cum against 100 Lakhs cum Qty of concrete work done: 0.05 lakh cum against 2.00 Lakh cum. No. of Machinery : 119 Nos. (Excavators-26, Tippers-60,Mixer-0,JCB-2,Concrete Mixer-1 etc.) Expenditure : Rs Crs Rs Crs Cum. Exp. Inc. Mob. Adv. - Rs Crs. Land Acquisition : Required 3746 Acres, Acquired Acres