Progress of Shintake Monitor Work KEK site meeting August 26, 2009 T. Yamanaka.

Similar presentations


Presentation on theme: "Progress of Shintake Monitor Work KEK site meeting August 26, 2009 T. Yamanaka."— Presentation transcript:

1 Progress of Shintake Monitor Work KEK site meeting August 26, 2009 T. Yamanaka

2 IP Target Design was fixed. Fabrication is going on now.

3 Design of IP Target

4 Collimator Scan Preparation of hardware is almost finished. –Only just lead collimator block is not prepared. Remaining task is to write scanning program

5 Background Monitor Drive system of background monitor is prepared. It need just only lead converter sheet

6 Cherenkov Detector Fabrication was finished. Calibration of photon number using cosmic ray was almost finished. Put Cherenkov detector at the actual position as a trial

7 Cosmic Ray Data

8 Laser Transport Ordered a mount table for laser transport line as same as the EXT LW group It will be connected by PVC pipe to the mount table of EXT LW group. Put this optical table on a mount

9 Replacement of Actuators Mirror actuators are changed from old ones. New actuators (Thorlabs) need Windows’s based control –Windows machine is prepared –They are connected to PC by USB By using “AnywhereUSB” USB devices are converted to LAN –To control by program and communicate with EPICS, LabVIEW is installed Need to write LabVIEW program Now here