Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.

Similar presentations


Presentation on theme: "1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004."— Presentation transcript:

1 1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004

2 2 Focus on the following questions from the charge  Does the collaboration have a plausible plan for assembly and maintenance of the detector? Is the collaboration properly addressing issues of subsystem integration?  Does the collaboration have a sensible plan for management and are their estimates of manpower needs realistic? Also, does the collaboration have realistic milestones as they prepare for the CD-1 “Lehman” review and beyond to construction?

3 3 Matrioshka (Russian nesting dolls) site building electronics magnet detectors If you build them all separately, will they fit? If they fit, can they make music together?

4 4 Schematic layout

5 5

6 6 Civil construction timeline 200420052006200720082009201020112012 CD-0 CD-1 CD-2A, CD-3A CD-2B CD-3B Site Preparation Hall D Tagger building Tunnel

7 7 Interface issues  Mechanical  Detectors must fit together  Electrical  Grounding, power consumption, E&M waves  Environmental  Heat production, settling over time  Magnetic  Fringe field from solenoid, magnetic shielding effect on other detectors  Physics  Production of backgrounds

8 8

9 9 Space allocation for detectors  Some regions are more tightly constrained than others  In allocating space for each subsystem, we have grouped the detector into four regions, mostly independent  Upstream region – backwards veto  Target region – start counter, target  Inside magnet – Bcal, FDC and CDC  Downstream – Cherenkov, TOF and LGD

10 10 GlueX detector side view

11 11 3 Rollers Bolted to the Ring-girder Two concepts for Bcal installation Assembly outside of magnet Assembly in place Attached to yoke using ring-girders Details by Ravi Anumagalla

12 12 Chamber cabling and extraction  We need to maintain the relative alignment of tracking packages at the 100  level.  We need a system that verifies the alignment. (Note that in zero- field, the chamber calibrations will be significantly different than in full field.)  Details still need to be worked out!

13 13 Location of readout electronics Pb, CC, TOF FDC CDC Bcal, vertex 31 racks of readout electronics and auxiliary systems

14 14 Guidelines for maintenance  Identify and mitigate failure scenarios that require difficult access  Allow access to all systems without uncabling  Goal is to allow access to all systems in less than one day * All Sub Systems are separated by 1m

15 15 Signal interfaces SiPMs pre-amp post-amp / shaper cable Readout FADC or Disc, TDC source amplifier in base cable shaper Need interface documents for each detector detector electronics Example:

16 16 Critical paths 200420052006200720082009201020112012 CD-2A, CD-3A CD-2B CD-3B Site Preparation Hall D Solenoid installation Barrel construction Barrel installation Electronics

17 17 Manpower  GlueX collaboration is well organized and welcoming new members  Manpower at JLab  Plans for a Hall D group is under discussion at the highest levels  Support groups at the lab contribute substantial resources  Data-acquisition  Fast electronics  Computing center  Detector  Target

18 18 Staffing for Hall D FY05

19 19 Near term schedule Oct20-22GlueX detector review Oct2912-GeV project cost/schedule update DecInterim assessment of solenoid magnet JanUpdated GlueX Design Report Mar29Submission of CDR to DOE MayInternal cost/schedule/scope review Jun27Documents to Lehman Review Jul11-14Lehman review Note: DOE review of 12 GeV science program unscheduled

20 20 List of milestones?  Short term  Long term

21 21 Summary  Conservative technology choices for all systems – no showstoppers  Detector definition is (almost) complete  Space for Cherenkov detector allocated, but no final decisions on technology  Each aspect of the experiment is being reviewed in turn (electronics, detectors, magnet, …)  Budget profile for 12-GeV project is required as input to schedules and staffing plan  Progress will likely be limited by the budget profile

22 22 Extras

23 23 Charge to the committe  Is the GlueX detector design sound? Are there any special areas of concern that deserve special study?  Does the collaboration have a sensible plan for management and are their estimates of manpower needs realistic? Also, does the collaboration have realistic milestones as they prepare for the CD-1 “Lehman” review and beyond to construction?  Are there design studies and/or prototyping efforts that, if undertaken in a timely manner, could strengthen the estimates of performance and cost of the planned experiment? Are each of the studies currently in progress given the appropriate priority at this stage?  Does the collaboration have a plausible plan for assembly and maintenance of the detector? Is the collaboration properly addressing issues of subsystem integration?  Are there technologies or developments which we have overlooked that may allow cost savings and/or improved technical performance?

24 24 Preliminary cost estimates CD-0CD-1CD-2CD-3CD-4TotalConstr Civil Construction50 11004420444000100608860 Beamline000115717559886114511 Solenoid100 150520410145014251075 Detector Tracking40 200595143384549436473367 Start Counter40 140564805100016891469 Barrel Calorimeter2080180943151378026737823502 Cerenkov Counter40 1702482522541181122872 Forward Calorimeter40 16030643613001111871 Time-of-Flight Wall26 12651451538012441066 Computing80 180130 57376819421602 Electronics1481002507801040114780342683770 Hydrogen Target0000011739156 Photon Tagger45 1451286946289027562521 Assembly00000975 1950 Total62964128011146213674638040763966235591

25 25 Civil construction timeline

26 26 Critical Paths

27 27 Electronics TDCs, ADCs timeline *** Electronics Review Estimate ***


Download ppt "1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004."

Similar presentations


Ads by Google