Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,

Similar presentations


Presentation on theme: "Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,"— Presentation transcript:

1

2 Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo, S. Burger, D. Gerard, C. Zamantzas, B. Dehning. LIU-PSB meeting, 21 st Speptember 2015

3 Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS 2016-17 −LS2 Summary 3

4 LIU-PSB-BI Work Package Total budget: 3635 kCHF 5 budget codes 4 cost drivers represent 79.8 % of the WP budget −Wire Scanners: 970 kCHF −Booster TMS: 750 kCHF −Upgrade for L4:648 kCHF −BLMs: 532 kCHF 4 Machine sectorTotal: 20 Work Units BI line2 H - Injection & Half Sector Test6 + 3 Ring5 Extraction lines4

5 LIU-PSB Milestones LS1: 1.5 year Half Sector Test −Part 1: L4T  Q3 2016 −Part 2 : HST  Q4 2016 EYETS = Extended-Year-End Technical Stop −16 weeks, from Dec. 2016 to March 2017 −All WPs related to Linac4 connection: end 2016, should ● Linac2 fail all of a sudden. ● LHC experience a major problem LS2 for the PSB −Upgrade: 15.5 months, from 07 January 2018 to 16 April 2019 −All WPs related to PSB energy upgrade −Linac4 connection to PSB if not done during EYETS Presently there is no management decision to relax on the end-2016 deadline for the Linac4 connection to the PSB. Therefore this has to stay the baseline for our planning. 5

6 Upgrade of BPMs in BTM & BTP extraction lines −8 monitors + 2 spares −New front and back end electronics for compatibility with Linac4 beams −New lab test bench −Budget : 264 kCHF −COMPLETE 6 Work Units completed during LS1 BTP.BPM10

7 Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS 2016-17 −LS2 Summary 7

8 HST Part1 One BTV in L4T (permanent installation for stripping foil) HST Part2: Temporary installation One BTV in front of proton dump (AD type) Two FBCTs (cost free) One BTV system for foil inspection – To be re-used Courtesy: S. Burger New H - charge-exchange injection system Beam Profile and Foil Inspection Half Sector Test Part1Half Sector Test Part2BTV screens at stripping foil Budget91 KCHF110 kCHF StatusCabling: COMPLETEDesign, integration: COMPLETE Production of 4 monitors +2 spares: COMPLETE DIC: SUBMITTED 2015Q3: interlock system under test Q4: monitors’ assembly 2016Q3: InstallationQ4: Installation EYETS 2016-17Cabling and Installation BaselineQ3 2016Q4 2016End 2016 Open actionCF flanges for BTV exchange and spare status: can be closed

9 HTS Part1 only electronics for stripping foil current monitoring in L4T HST Part2 Titanium plates to be installed in front of one H0/H- dump for H0/H- current monitoring New H - charge-exchange injection system H0/H - Current Monitor Courtesy: F. Roncarolo Half Sector Test PART1Half Sector Test PART2H0/H- current monitoring Budget10 kCHF50 kCHF StatusDIC: SUBMITTED Mechanical design APPROVED Electronics design: REVIEWED WITH OP An Engineering Specification Document being prepared. To be discussed with OP. 2015Fall Q3: Amplifier prototypeQ4: Monitors’ production 4+4 2016Q1: Commissioning VME+ADC Q3: Installation Q4: Installation EYETS 2016-17Cabling BaselineQ3 2016Q4 2016End 2016 Open actionSpares status and cost (4 spares, aligned with magnets): can be closed

10 10 New H - charge-exchange injection system Beam Loss and Interlock Systems beam Half Sector TestBLMs for MonitoringBLMs for Observation BUDGET5 kCHF30 kCHF137 kCHF StatusBLM support design and integration: COMPLETE DIC: SUBMITTED 2015Installation + cablingElectronic board validationDiamond detector procurement 2016Q3: CommissioningElectronic board procurement EYETS 2016-17Installation and Cabling BaselineQ3 2016End 2016 Ionization chambers : x6 LHC type Monitoring foil degradation Machine protection (H0/H - dump) Interlock Diamond: x8 Monitor fast losses & foil degradation Optimize stripping efficiency, OASIS aqn. Both detectors share the same support system Courtesy: W. Weterings, C. Zamantzas

11 Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS 2016-17 −LS2 Summary 11

12 12 Courtesy: M Hourican New injection septum for 160 MeV beams Based on existing system: linear, no interlock, OASIS Specifications −Ensure the distributed beams are centered in their respective apertures for incoming beams only −input plates: stripped electrons charge deposition BEAM PROFILE BI.SMV position measurement plates w/ Linac4 New BI.SMV BI.SMV Position plates BUDGET50 kCHF Status Integration by ABT: COMPLETE 4 Ti plates assemblies, 3 assemblies for the instrumentation supports: DELIVERED. In metrology’s hands DIC: SUBMITTED 2015Q4 : Installation in BI.SMV EYETS 2016-17Cabling BaselineEnd 2016 Open actionPosition for outgoing beams ruled out: can be closed

13 BEAM PROFILE New Housing for BI.BTV30 Courtesy: D. Gerard MOTIVATION: The need of longer magnetic length for BI.SMV induced by Linac4 beam energy BI.BTV30 BUDGET60 kCHF StatusDesign: COMPLETED EN-MME jobs: STARTED 2015 ECR: to be issued in the shadow of BI.SMV’s ECR EYETS 2016-17installation BaselineEnd 2016 Open action2015: ECR pending

14 14 BEAM PROFILE Turn by turn meas. for injection matching w/ Linac4 Courtesy: F. Roncarolo Section 4L1 SEM H+V SEM grids for PSB ring3 BUDGET135 kCHF Status DIC: SUBMITTED No mechanical design started. Proposed SEM’s integration: section 4L1 Electronics design: only just started for PSB, but with slight modifications can also be used for PS, where it will probably first be tested. Radiation hot spot there: 22 kGy/year (2013). RadMons added by RP on Sept. 2 nd. 2015-2016fall 2015: SRR / Q1 2016: ECR EYETS 2016-17Installation and Cabling BaselineEnd 2016 Open actions BI proposes to postpone installation to YETS 17-18 – old PS SEM gets priority Decision on spare grids to be taken once the final design is clear Specifications : SEM grids injection of half a PSB turn to well separate turn-by-turn profiles (over 20turns) External condition interlock : to shorten the Linac4 pulse (1turn max) PPM In/Out: ruled out option Permament implementation for commissioning, MDs and operation

15 BEAM INTENSITY Measurement of injection efficiency with Linac4 15 Courtesy: P. Odier BR.TMD in 8L1 section BUDGET198 kCHF Status DIC: SUBMITTED One BCT available (without shielding) in the laboratory Bld 109 : not needed for machining. Dose rate in Section 8L1 is reasonably low: ~1.6 kGy/y Work Dose Planning for 30.3 man.days: submitted to RP 2016 Acquisition chain: HW production, SW specification Spare ceramic chamber EYETS 2016-17 Refurbish the monitors in the BI radioactive workshop; installation and cabling BaselineEnd 2016 Open actionsALARA: can be closed Specifications Four monitors BR.TMD in 8L1, installed in ’72, un-used since early 80s’ Analog turn by turn acquisition, up to 100 turns Watchdog : comparison with BI.BCT20 after 100 turns

16 BEAM INTENSITY Quantify total intensity transmission during PSB cycle 16 Courtesy: P. Odier DC Current Transformer BUDGET114 kCHF Status Acquisition chain: upgraded ADC and Expert GUI Front End Electronics: assembled but not installed due to higher priorities 2015 -2016 Test of the new B-Train Receiver Installation of the new Front End Electronics (YETS 15-16) EYETS 2016-17 Installation of the new B train Receiver Adaptation for Linac4 intensities BaselineEnd 2016 CommentNow with Linac2: Np=1E13p per ring. Is 2.5e13 per ring still realistic with Linac4 ? Can we relax this specs. ? Summary Four monitors BR.BCTDC in section 9 (DCCT) Upgrade of the acquisition chain

17 17 BEAM POSITION Ring Trajectory Measurement System Courtesy J. Belleman Booster Trajectory Measurement System BUDGET750 kCHF Status DIC: SUBMITTED One full ring can be acquired, multiplexed Software: FESA interface, with hooks for YASP and the Sampler + Expert GUI TS3: Three new passive front ends installed. We’re still using the old front-end electronics 2015 -2016 Amplifiers still need some work but are located outside the tunnel Fall 2015: Demonstrating 200  m resolution down to a beam intensity of 1e10p/b EYETS 2016-17 Cabling: About 250 cables to converge towards BOR ! Electronics deployment Software upgrade for Gain, Calibration, etc… BaselineEnd 2016 Comments Decommissioning of old system : no way back After cabling complete, at least one month needed to fully test the system: will this be available ? Open action Demonstrating reliable operation with new firmware/software: can be closed Fall 2015: Demonstrating 200  m resolution down to a beam intensity of 1e10p/b Specifications − Bunch-by-bunch, turn-by-turn trajectories over the whole cycle − Various derived averages (Orbits, MRP) − Position resolution 200μm − No more multiplexing over the four rings − New front-end electronics with settable gain Front-end boxes: dated from 1974

18 18 BEAM POSITION Wide Band BPM in the BTP line Courtesy J. Belleman Wide Band Pick-Up in BTP line BUDGET75 kCHF Status DIC: SUBMITTED Production design: under approval FE electronics: being assembled 2015 ECR approved but for installation during YETS 15-16: we are not ready Q4: BPM production EYETS 2016-17Installation and Cabling BaselineEnd 2016 Comments ECR: modification for installation in EYETS 16-17 Specifications Spot transverse instabilities during beam transfer between PSB and PS Based on existing PS design (section 94) Acquisition : OASIS WB pick-up Proposed layout in BTP

19 19 BEAM LOSS PSB and Transfer lines BLM system ICs for L2 sectionICs for Transfer linesFICs for L3 sections Budget127 kCHF211 kCHF164 KCHF StatusCKC50 cables: produced. Supports: installed. Rack: Installed & connected. Electronics:produced, tested DIC, DIR, DEC: submitted monitors & electronics: procured. L3 section supports: designed. BLM supports: tested during TS DIC, DIR, DEC: submitted 2015Validation of electronic board. ICs and spare channels to be installed September: integration check and then production 2016Electronic board productionECR EYETS 2016-17Cabling : DIC, DIR, DEC submitted BaselineLS1End 2016 CommentsBLM’s specs: Partial agreement of Rende, who needs internal discussion with PS team. Will finalize soon. Ionization Chambers in Transfer lines : 36 ICs +7 spares from LHC, not paid by LIU Flat Ionization Chambers in L3 section: 32 new FICs

20 20 BEAM TUNE New Tune pick-ups in 3L1 Present capacitive pick-up in 3L1 3L1 Tune pick-ups BUDGET100 kCHF Status Specifications: under discussion New WU request. Not approved yet BaselineEnd 2016 Comments Deadline is unrealistic Need to prioritise w/ BI-ML between Ring3 SEMs, BWS, and tune PUs Availability of EN-MME to be discussed Budget not yet allocated MOTIVATION: Poor sensitivity of present pick-ups for LHCPROBE beams

21 Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS 2016-17 −LS2 Summary 21

22 BEAM PROFILE New Housings for BT.BTV10 and 30 Courtesy: D. Gerard MonitorBT.BTV10BT.BTV30 Budget84 KCHF StatusTanks installedDesign: COMPLETE ECR: approval closed. To be released mechanical parts : production ECR: approval closed. To be released Tank, mechanical parts : production EYETS 2016-17 Modification of adjacent pipes LS2Monitors installation – earlier if possible (EYETS 16-17) BaselineLS2 MOTIVATION: The need of longer magnetic length for Septa induced by increased beam energy

23 23 BEAM PROFILE Wire Scanner Aim : adaption of the scanner design for the PS and SPS to the limited space in the PSB First proposal : Section 11L1 Courtesy: B. Dehning 2nd section: 4L1, shared with SEMs Wire scanner BUDGET970 kCHF Status Development of control end acquisition electronics advancing Integration: sections 11L1 + 4L1 possible Two prototypes (SPS + Lab) are used for optimisation and development of controls electronics 2015 To do: SRR + ECR + DIC EYETS 16-17 production of a prototype scanner for installation in the PSB 2017 PSB Prototype commissioning BaselineLS2 Comments WU is out of the critical path Fall 2015: Engineering specification Mid 2016: Final cost updated once prototype is built

24 Summary LS1: one WU completed HST: on time Part 1 & Part 2 Open actions: a few left to be addressed EYETS 16-17 −H - injection section, BLMs and BTMS: A large cabling effort required −Late WU request: Tune pick-ups in 3L1. Baseline unrealistic for BI YETS 17-18 −Proposed installation date for the injection matching monitor, ie 1 year after baseline LS2 −BWS: A prototype for test in the PSB during the run 2017. WU is out of the critical path, Budget −All planned activities are within the budget… BUT −BWS: final cost known by Mid’ 2016 −Missing 100 kCHF for the tune pick-ups −Most WUs includes spares 24