Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead.

Similar presentations


Presentation on theme: "Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead."— Presentation transcript:

1 Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead Date: 09.26.2013

2 Federal Aviation Administration DTAP SW Patch 5.0 Update Included Requirements: -SID NONE (EWR ATC) -MAINT ALT NONE (EWR ATC) -Double TO (MD-11 UM79 Map Redraw) -Dual Contact/Drop Down Remarks (EWR ATC) Discovered automation issues being corrected: -PTR #171 – Early P+30 AH processing -PTR #172 – AGDS Index Management (3000 limit) FAT scheduled for 10/7 @ Thales CC: -Early Thales Test Book look 2

3 Federal Aviation Administration DTAP SW Patch 5.0 Schedule WJHTC Install/SAT – 10/8: -Start of Data Comm lab Functional Testing -Thales and PO Ops Support -MEM/EWR Site Install Go/No-Go Trigger MEM Install/SAT – 10/14-16: -Holiday install -Pre-SAT/SAT procedure development (Airline support) -10/16 PM FDX will fly MD-11 UM79 DCT TO flight as part of SAT (voice read back) -Goal is DTAP RTS for 10/17 FDX AM push EWR Install/SAT – 10/21-23: -Pre-SAT/SAT procedure development (Airline support) -10/21 PM UPS will fly B767 flight as part of SAT (voice read back) -Goal is DTAP RTS for 10/23 evening DCL ops 3

4 Federal Aviation Administration Build 7 Req Update Down selected Requirements Proposal Evaluation Underway: -Harris/Thales proposal response pending 4 Requirements under consideration: -Flight Deck Response to AOC -Climb Via -Departure Processing -Arrival Processing Formal Harris Task Order CSP Trials Services and DTAP license pick up Oct 1 4

5 Federal Aviation Administration 5 Running 76% success FDX Crew DCL Familiarity Increasing 2 Performance Issues Discovered: -Early P+30 AH causes inactive SEND button -AGDS Index Management Over 3000 Causes Random DM25 UL Fails FDX GOC Revert to PDC Ops Success Proven Upon DTAP Outage (9/20 AM Push) Continued weekend ZME ERAM Testing: -HADDS Recons triggered -9/28-29 48 Hr ERAM run planned (0530z - 0300z)

6 Federal Aviation Administration EWR DCL Limited Ops Update UAL 10 Revenue DCL Ops Complete (9/3-17): -B767 ops (LSZH/ZRH, LTBA/IST, SAEZ/EZE) -UAL 757/767 Fleet Tech Mgr/Flight Standards on-site to brief each crew -Agreement with FAA AFS to complete 20-25 DCL ops before expanded UAL ops (B777 Oct +) DLH, UPS, BAW, FDX Continuing DCL Ops: -DLH 2/day schedule (EDDM, EDDL) -UPS, BAW, FDX continued limited ops -SAS no longer actively participating (Airbus CLR7+ FMS issue) Seeking expanded Airline Participation 6

7 Federal Aviation Administration Additional Misc. MEM/EWR Items 10/1 Outreach Briefing to the Newark International Carrier Committee (NICC): -Provide Trials overview to attending International Carriers -Solicit interest in new EWR Trials participants 9/18-19 Additional MEM Tech Ops technicians received DTAP Cert Training: -3 techs now certified at MEM -Expands DTAP Re-Cert time options MEM DTAP FDIO Connect Extension Out of Board Approval 9/13: -NAS CCB meeting acknowledge – 9/30 7

8 Federal Aviation Administration Questions ? KUSA


Download ppt "Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead."