1 Manufacturing contracts for RFQ
CDR2 RFQ| Vincent Hennion System engineering activities

2 Pour personnaliser le pied de page et la date :
« Insertion / En-tête et pied de page » Personnaliser la zone de de pied de page Cliquer sur appliquer partout Table of contents Chapter 01 Rules and purchasing P.04 List of RFQ Contracts P.05 Tendering documents file P.06 Contracts follow-up strategy P.07 Chapter 02 Focus on the 5 main contracts P.09 Questions P.15 CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

3 Chapter 1 CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

4 Rules and purchasing procedures
Fundamental rules European directives and associated French laws applicable to the procurement procedures The principles governing the public purchasing - equity, efficiency and transparency - from the first €uro CEA Internal rules Purchases below € 30,000 will be treated in connection with the IRFU budget group Purchases over € 30,000 will be made with the purchasing department Procedures The simplified procedure (not formalized) for purchases < € 207,000 The formalized procedure for purchases > € 207,000 Restricted call for tender (over 5 months) Open call for tender (over 4 months) CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

5 List of RFQ Contracts Contract 1: Copper raw material procurement
Contract 2: Ports, sections flanges and dummy plates Contract 3: RFQ Cavity in copper Contract 4: RF coupling loops Contract 5: RF tuners Contract 6: HIP (High Isostatic Pressing) Contract 7: Helicoflex seals Contract 8: Prototype RF tuner Contract 9: RF test bench equipment Contract 10: RFQ support Contract 11: Finition milling of the entry/exit plates Contract 12: Spares of bolts and nuts Contract 13: Seals for test activities Others contracts: Tools, … CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

6 Tendering documents file
Contract Rules for the call for tender Purchasing procedure deadlines deliverables Technical and financial offer evaluation Statement of work Technical specifications of manufacturing, controlling, cleaning, packing… Deliverables Content of the manufacturing file Drawings 2D representation of the mechanical parts nomenclatures 3D mock-up Catia V5 or Step file others Excel file of the coordinates of points of the modulation CEA Purchasing Department IRFU Engineering team and DO CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

7 Contract follow-up strategy
Regular progress meeting (face to face or by teleconference) Sensitization of the workshops Mechanical behavior specificity of pure copper as raw material Pure copper oxidation properties (degreasing) Cleanliness (work with gloves) Required tolerances for performances Request of collaborative exchanges Sensitization of the workshops RFQ is an RF equipment before being a complex mechanical system Processes qualification is a mandatory step to master RFQ manufacturing Controls at intermediate steps are needed, due to the high value of the parts Transparency and collaborative exchanges are mandatory to deal with technical issues and find solutions Drawings 2D drawings from CEA (functional requirements and needs) 2D manufacturing and control drawings from the manufacturers to be checked by CEA 3D mock-up Catia V5 or Step file from CEA to help the manufacturer for the control CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

8 Chapter 2 CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

9 the 5 main contracts: needed expertise
Contract 1: Copper raw material procurement Contract 2: ports, sections flanges and dummy plates Machining of copper blocks and cylinders Machining / Supply of flanges in SS Cu/SS brazing Machining and copper/copper brazing of the test cavity Contract 3: RFQ Cavity in copper Drilling, machining of vanes Cu/Cu brazing of 5 sections Contract 4: RF coupling loops Machining and brazing of the ceramic window Manufacturing of the water cooling loop TiN coating characterization Contract 5: RF tuners Cu/bellows assembly CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

10 Contract 1: copper raw material
Forging process Isotropic and homogeneous pure copper, with grain size <500µm 3D hot forged copper, at °C 5mm scalping on each facet Thermal treatment Annealing under vacuum (400°C / 1 hour / 10-5 mbar) Slow cooling under vacuum Test plates sampling Test plates sampled from the extremity of each bar 20mm thick Purchased quantity: forged bars and blocks for 5+1 sections, spares for ports Option for 1 more section and additional spares for ports CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

11 Contract 2: ports, section flanges
Contract phasing Step 1: qualification of a SS/Cu brazing process without metallic coating; verification on representative ports, validation after Cu/Cu brazing on the manufactured test cavity Step 2: extension of this process to larger quantities: process industrialization Step 3: manufacturing of the series (for the whole RFQ) Main technical acceptance criteria Satisfactory vacuum leak test of the brazed joint Satisfactory dimensional criteria (geometry, parallelism…) after brazing Manufacturing and control file Shipment of the equipped test cavity Shipment of the ports, sections flanges, and dummy entry/exit plates No Option CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

12 Contract 3: RFQ cavity Contract phasing
Step 1: qualification of deep drilling and precision milling processes on pure copper; verification on representative parts, including a section 1 minor vane modulations scale) Step 2: qualification of a Cu/Cu brazing process on pure copper ; verification on representative parts Step 3: validation of these processes for the manufacturing of the 1st section Step 4: manufacturing and control of the other 4 sections of the RFQ Main technical acceptance criteria Satisfactory vacuum leak test and He pressure test Satisfactory dimensional criteria (geometry, surface quality…) before and after brazing Satisfactory RF tuning test (Bead-pull) Manufacturing and control file Shipment of all the sections Option for one more section CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

13 Contract 4: RF coupling loop
Contract phasing Step 1: qualification of the RF window manufacturing process including Ceramic/Cu brazing; verification and validation on a representative dummy RF window, including a LLRF test Step 2: qualification of the water cooling loop manufacturing process; verification on representative parts which may be the subassembly of the 1st RF coupling loop Step 3: qualification of the TiN coating process by characterization measurement on samples (stoichiometry, thickness, homogeneity) Step 4: manufacturing and control of 3 RF coupling loops Main technical acceptance criteria Satisfactory dimensional criteria (geometry, RF surface quality…) Satisfactory vacuum leak test and pressure test of the concerned parts of the loop Satisfactory LLRF tests of the RF windows Manufacturing and control file Shipment of the 3 RF coupling loops Option for one more RF coupling loop CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

14 Contract 5: RF tuners Contract phasing
Step 1: qualification of the manufacturing processes including bellows/Cu assembly; verification and validation on representative dummy parts and one full prototype Step 2: extension of this process to larger quantities: process industrialization Step 3: manufacturing of the series (for the whole RFQ) Main technical acceptance criteria Satisfactory dimensional criteria (geometry, RF surface quality, adjustment flexibility…) Satisfactory vacuum leak test and pressure test of the concerned parts Satisfactory tests on the prototype Manufacturing and control file Shipment of the 60+5 RF tuners Option for up to 12 more RF tuners CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15

15 Thank you for your attention!
QUESTIONS? Commissariat à l’énergie atomique et aux énergies alternatives Centre de Saclay | Gif-sur-Yvette Cedex T. +33 (0) xx xx | F. +33 (0) Etablissement public à caractère industriel et commercial | RCS Paris B DSM Irfu CEA Saclay/Irfu ESS RFQ CDR2| 8-9 Dec15