Presentation is loading. Please wait.

Presentation is loading. Please wait.

A tutorial on MS Project James Burns. 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start.

Similar presentations


Presentation on theme: "A tutorial on MS Project James Burns. 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start."— Presentation transcript:

1 A tutorial on MS Project James Burns

2 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start & stop dates  Assigning resources  Calculating costs

3 12345678910111213141516 Contract signed Survey designed Target market ID Data collection Develop presentation Analyze results Demographics Presentation

4 03 3 3 6 5 613 15 16

5 14.

6 Network Computation Process Forward Pass – Earliest Times – Early Start (ES) – How soon can the activity start? – Early Finish (EF) – How soon can the activity finish? Backward Pass – Latest Times – Late Start (LS) – How late can the activity start? – Late Finish (LF) – How late can the activity finish? Slack (SL) – How long can the activity be delayed? Critical Path (CP)– The longest path in the network which, when delayed, will delay the project

7 Forward Pass Computation You add activity times along each path in the network (ES + Duration = EF).  You carry the early finish (EF) to the next activity where it becomes its early start (ES), unless  The next succeeding activity is a merge activity. In this case, you select the largest early finish number (EF) of all its immediate predecessor activities.

8 Backward Pass Computation  You subtract activity times along each path starting with the project end activity (LF - Duration = LS).  You carry the late start (LS) to the next preceding activity to establish its late finish (LF), unless  The next preceding activity is a burst activity. In this case, you select the smallest late start number (LS) of all its immediate successor activities to establish its late finish (LF).

9 Determining Slack Slack for an activity is simply the difference between the LS and ES (LS – ES) or between LF and EF (LF – EF). Slack tells us the amount of time an activity can be delayed and yet not delay the project. When the LF = EF for the end project activity, the critical path can be identified as those activities that also have LF = EF or a slack of zero (LF – EF = 0 or LS – ES = 0).

10 Activity-On-node network

11 Critical path method network Description Legend IDEF LF ES SL LS DUR Create Graphics 9E10 11110 1 Edit Paper 11D9 29 0 Draft Paper 9C6 0 639 Research Topic 1B6 0 156 Identify Topic 110 0 0A1 References 9F10 11110 1 Final Draft 11G12 111 0 Group Term Paper

12 Forward Pass Computation Description Legend IDEF LF ES SL LS DUR Create Graphics 9E10 1 Edit Paper 11D9 2 Draft Paper 9C6 3 Research Topic 1B6 5 Identify Topic 1 0A1 References 9F10 1 Final Draft 11G12 1 Group Term Paper Always start at 0 EF = ES+DUR EF = ES+DUR EF = ES+DUR EF = ES+DUR

13 Backward Pass Computation Description Legend IDEF LF ES SL LS DUR Create Graphics 9E10 11110 Edit Paper 11D9 29 Draft Paper 9C6 639 Research Topic 1B6 0 156 Identify Topic 110 0A1 References 9F10 11110 1 Final Draft 11G12 111 Group Term Paper EF=LF LS = LF - DUR LS = LF - DUR LS = LF - DUR LS = LF - DUR

14 Determining Slack Description Legend IDEF LF ES SL LS DUR Create Graphics 9E10 11110 1 Edit Paper 11D9 29 0 Draft Paper 9C6 0 639 Research Topic 1B6 0 156 Identify Topic 110 0 0A1 References 9F10 11110 1 Final Draft 11G12 111 0 Group Term Paper SL = LS – ES or LF - EF SL = LS – ES or LF - EF SL = LS – ES or LF - EF CRITIC AL PATH?

15 Garage Problem Compute the early, late, and slack activity times Determine the planned project duration Identify the critical path What should you do if the Doors activity is going to take two extra days?

16 Garage Problem Description Legend IDEF LF ES SL LS DUR Windows 4 1 Roof 3 4 Electrical 6 3 Erect Frame 2 4 Pour Foundation 3 1 Doors 5 1 Paint 9 2 Rough-in Frame 7 2 Door Opener 8 1 Clean-up 10 1 Project Duration: ______ days Critical Path: _______________

17 Garage Problem Description Legend IDEF LF ES SL LS DUR Windows 748 11110 3 Roof 1137 47 0 Electrical 1067 1 8311 Erect Frame 327 0 347 Pour Foundation 330 0 013 Doors 758 11110 3 Paint 13915 213 0 Rough-in Frame 11713 211 0 Door Opener 10811 13112 2 Clean-up 151016 115 0 Project Duration: ___16___ days Critical Path: __1  2  3  7  9  10__ If activity 5 is going to take two extra days, you probably do not have to do any thing because this activity has three days of slack – no effect on project duration.

18 More Learning Objectives  Recurring tasks  STATISTICS  Zoom out/zoom in  Precedence relationships  Lags between links

19 PM Software in general

20 Popular Project Management Software Packages CA-SuperProject Microsoft Project Project Scheduler SureTrak Project Manager Time Line High-End Project Management Software

21 4 Criteria for Selecting Project Management Software Capacity Documentation and on-line help facilities Ease of use Features available Integration with other systems

22 Additional Criteria Installation requirements Reporting capabilities Security Vendor Support

23 5 Advantages of Using Project Management Software Accuracy Affordability Ease of use Ability to handle complexity Maintainability and modifiability Record keeping Speed What-if analysis

24 6 Concerns about Using Project Management Software Becoming distracted by the software A false sense of security Information overload The learning curve Over-reliance on software

25 Must start with A list of tasks Or A Work Breakdown Structure Always make your first task a PROJECT summary task to which all other tasks are subordinate

26 Bring up MS Project Start in the Gantt View Enter task detail in the entry table to the left Subordinate tasks appropriately Link Tasks as appropriate

27 Project Information Box

28 Can schedule from a start date or backward from a stop date Can choose a particular calendar type—that makes assumptions about when people will be working

29

30 Statistics Box—by clicking Statistics

31 The Gantt View Tasks are entered within the Entry Table in the Gantt View

32 The Main Window of MS Project

33 Entering Tasks in the Gantt View Enter Tasks into the entry table on the GANTT view Entry table is behind the GANTT chart and works just like a spreadsheet Can also enter tasks in the network diagram or the task usage views

34 Tables You can choose a variety of tables to view in conjunction with the Gantt view – Entry, Cost, Schedule, Tracking, Earned value, Usage, Variance, Work, Hyperlink… are just some of the tables you can choose from – Click on View on the Menu bar and then click on Table – To view all the tables, click on More Tables…

35 Columns You can add columns to any table in the Gantt view Click on Insert and then Columns Select the column you want included in the table by clicking on the dropdown arrow associated with the first box and selecting the desired column name Click on OK That column will be included in the table to the left of the point where the selected cell appears

36 Predefined Reports MS Project provides a number of predefined, static reports that can be displayed and printed Click on View and the Reports The categories are Overview, Current Activities, Costs, Assignments, Workload and Custom

37 Task subordination Use indent arrow MS Proj has a WBS understanding and assigns a WBS code even though it does not explicitly exhibit a WBS chart

38 Linking of Tasks Select tasks to be linked Click on the chain-link icon Decide on precedence relationship: FS, SS, FF, SF

39 Setting start & stop dates When you set a date in the entry table of the Gantt view, MS Project treats it as if it were a “hard” constraint – It schedules everything around such “hard” dates

40 Assigning resources Resources have to be created before they can be assigned You can use the “faces” icon in the Gantt view to both create and assign resources – Resources are created once they are named Alternatively, you can create resources in the Resources Sheet view – Simply click on this “view” in the column on the left.

41 Calculating costs Fixed costs – Enter these in the cost table From the VIEW menu item change to the cost table Enter fixed costs Variable costs – Enter resource hourly rates – MS Project will calculate

42 33 Project Management Software Features Budgeting and cost control Calendars Email Graphics Importing/exporting data Handling multiple projects and subprojects Report generation

43 Project Management Software Additional Features Resource management Planning Project monitoring and tracking Scheduling Security Sorting and filtering What-if analysis

44


Download ppt "A tutorial on MS Project James Burns. 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start."

Similar presentations


Ads by Google