Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015.

Similar presentations


Presentation on theme: "Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015."— Presentation transcript:

1 Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015

2 Global Settlement Review Insurance Claims Process – 3 years of negotiations and building assessments during multiple earthquakes Global Settlement completed 22 Dec 2013 Funds received 31 March 2014

3 The Past Year CPT Recovery Team appointed by July 2014 Schedule of Works completed by Oct 2014 Adopted by the Church Property Trustees in Nov 2014 Communicated to Parishes in Dec 2014 –Jan 2015

4 Recovery Programme Progress 230 projects in Recovery Programme 108 projects completed to date: 29 Vicarages 1 New Build (St Saviour’s at Holy Trinity, Lyttelton) 53 Churches 25 Halls and other buildings 7 projects currently under construction 35 projects in the planning phase

5 Schedule Overview South Canterbury 8% of projects are in South Canterbury Archdeaconry 32% of projects completed 2 major works projects (over $200,000) to be completed Currently in the design and/or pricing phase: St Mary’s Church and Hall, Timaru Church of the Holy Innocents, Mt Peel 8 minor repair projects (under $50,000) To be completed progressively from 2016 to late 2017 3 stained glass window repair projects To be completed progressively from 2016 to late 2017

6 Schedule Overview South Canterbury By Dec 2015, 37% of projects are scheduled to be completed All projects are scheduled to completed by Dec 2018


Download ppt "Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015."