بسم الله الرحمن الرحيم 2015 1. General Information Total Installed Capacity PLAN 2015 =3155 MAX Load =2296 MW demand– 2015 =11793GWH Number of Customers2014.

Similar presentations


Presentation on theme: "بسم الله الرحمن الرحيم 2015 1. General Information Total Installed Capacity PLAN 2015 =3155 MAX Load =2296 MW demand– 2015 =11793GWH Number of Customers2014."— Presentation transcript:

1 بسم الله الرحمن الرحيم 2015 1

2 General Information Total Installed Capacity PLAN 2015 =3155 MAX Load =2296 MW demand– 2015 =11793GWH Number of Customers2014. =2,250000 Energy Access up to now = 45 % Average Annual Growth = 14 % 2

3 3

4 Location : Second Cataract at DAL area ( Nile River State) (North of Khartoum) Generation Capacity: 8 Units – 642 MW. Preliminary Feasibility Study: Available. Funding: Needed. 4 0

5 Location : South of Mograt Island (Nile River State) (North of Khartoum) Generation Capacity: 8 units with total capacity 320MW. Construction period 5 years. Preliminary Feasibility Study: Available. Funding : Needed. 5 0

6 Location : 120 km north the city of Dongola. Generation Capacity: 360 MW (6X60MW) Kaplan type. Project Status: under promotion Funding : Needed. 6 0

7 Shereik Dam Location : on the 5th Nile cataract. Generation Capacity: 420 MW (6X70MW) Kaplan type. Project Status:under promotion. Funding : Needed. 7 0

8 8

9 Location: Red sea state in eastern Sudan - about 70 Km to the north of Port Sudan Generation Capacity & Configuration : Red Sea Power Plant consisting of 2 independent units with a configuration of 2X300 MW coal steam turbine units600 MW total capacity. Plant fuel type: coal Project contract type : turnkey project or Boot. Project Status : ( under promotion) Fund : Needed 9

10 Red Sea Gas power plant Project Gas turbine 4 units 4x225 MW900 MW total capacity. PROJECT STATES ( UNDER Negotiation ) Fuel type GAS ( natural gas NG ) Fund Needed 10

11 The main objective of these projects is to supply Sudan National Grid with clean, sustainable, eco- friendly energy with low operating cost. 11

12 12

13 Location: Tokar south of Port Sudan, Red Sea State. Generation Capacity: 180MW Status: wind measurement ongoing. Feasibility study : ongoing. Funding : Needed. Red Sea wind farm 13

14 Location: Nyala. Capacity: 20MW. It will be implemented in two phases, 10 MW each. Annual average wind speed: 7.9 m/s. Feasibility study: available Land: Available.Fund : Needed 14

15 Average wind speed 4.2 – 8.1 meter/second at 80 meters above ground level (agl) Areas with highest wind speed: o Red Sea o Northern Sudan (Dongola) o Jabel Marra Mountains in western Sudan 15

16 16

17 Capacity: 10 MW Location: Khartoum Feasibility Study available & Techincal specs avaible. Funding : Needed 17

18 Capacity: 5 MW Location: Nyala Feasibility Study : available. Land available. Funding : Needed 18

19 Capacity: 3 MW Location: Al Fashir Feasibility Study : available Funding : Needed 19

20 Capacity: 2 MW Location: Al Geniena Feasibility Study : available Funding : Needed 20

21 Average daily solar irradiation: 5.8 – 7.2 kWh/m 2 The solar radiation increases in northern and west-northern areas and decreases towards the south 21