Start Up with Electrons Preliminary Schedule. Tasks Polarity Check Transfer Line Store Beam BBA ORM Feedbacks Aperture, Acceptance Filling Schemes and.

Similar presentations


Presentation on theme: "Start Up with Electrons Preliminary Schedule. Tasks Polarity Check Transfer Line Store Beam BBA ORM Feedbacks Aperture, Acceptance Filling Schemes and."— Presentation transcript:

1 Start Up with Electrons Preliminary Schedule

2 Tasks Polarity Check Transfer Line Store Beam BBA ORM Feedbacks Aperture, Acceptance Filling Schemes and Ion Cloud Studies

3 Schedule Mon.14.01Tue. 15.01Wed. 16.01Thu. 17.01Fri. 18.01.Sat. 19.01.Sun. 20.01. Start Maschine Setup E-Weg Feedback BBA ORMAbgleich Kicker Beule 1 mA Beamline Setup Contingency and Test Run Contingency and Test Run Store BeamORM Tunemessung Chroma, Kopplung, Akzeptanz, etc. Ion Cloud 1 mA Run PU4 1 mA Beamline Setup Contingency and Test Run Contingency and Test Run Store Beam

4 Schedule Mon.14.01Tue. 15.01Wed. 16.01Thu. 17.01Fri. 18.01.Sat. 19.01.Sun. 20.01. HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA Test Run 40 Bunches, 80 mA Test Run 40 Bunches, 80 mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA HASYLAB – Beamline Radiation Safety 100mA Test Run 40 Bunches, 80 mA Test Run 40 Bunches, 80 mA Test Run 40 Bunches, 80 mA Test Run 40 Bunches, 80 mA