November 7, 2012.  Projects Recently Completed  Portal, ND  Projects in Feasibility & Design  Milltown, ME  Derby Line, VT  Madawaska, ME  Project.

Similar presentations


Presentation on theme: "November 7, 2012.  Projects Recently Completed  Portal, ND  Projects in Feasibility & Design  Milltown, ME  Derby Line, VT  Madawaska, ME  Project."— Presentation transcript:

1 November 7, 2012

2  Projects Recently Completed  Portal, ND  Projects in Feasibility & Design  Milltown, ME  Derby Line, VT  Madawaska, ME  Project Under Construction  Van Buren, Maine  Other projects  Alexandria Bay, NY  Fort Kent, ME

3  Portal, North Dakota  Construction Start  06/2008  Construction Completion  10/2012

4

5

6  Milltown, ME  Design started July 2012  Construction Start Spring 2013  Madawaska, Maine  Focus on upgrading of main inspection building  Construction start planned for 2014

7  Derby Line, Vermont  Focusing on commercial processing  Construction Start planned in 2014

8  Van Buren, Maine  Construction Start  06/2011  Estimated Construction Completion  7/2013  Project is six months ahead of schedule

9

10

11  Alexandria Bay, New York  Re-design a likely scenario  Project remains a CBP priority  Could be constructed in two phases

12  Fort Kent, ME  GSA will make modifications to the lanes & canopies to accommodate the alignment of the new bridge from St. Clair, NB.  Completion by October 2013

13  Some funding relief in the future?  No program for FY 2013  A small FY2014 program possible  A continued emphasis on small cost, quick fixes.  Public Private Partnerships

14 Ralph Scalise U.S. General Services Administration 617-565-5821 Ralph.scalise@gsa.gov