Www.wv.doe.gov Phase I Decommissioning Project Update West Valley Demonstration Project Presented by: Bryan Bower, Department of Energy November 14, 2012.

Similar presentations


Presentation on theme: "Www.wv.doe.gov Phase I Decommissioning Project Update West Valley Demonstration Project Presented by: Bryan Bower, Department of Energy November 14, 2012."— Presentation transcript:

1 www.wv.doe.gov Phase I Decommissioning Project Update West Valley Demonstration Project Presented by: Bryan Bower, Department of Energy November 14, 2012

2 Current Activities: Reviewed Concrete Storage Cask fabrication activities at Zion (CHBWV) NAC prepared the project plan (NAC) Design for Storage System - Due December 31, 2012 (NAC) Design for Storage Pad (NAC) – January 30, 2013 Design for transport system (NAC) – Dec 31, 2012 Request For Proposal for decontamination canisters (CHBWV) – December 2012 2 NAC Project using Vertical Storage High Level Waste Canister Relocation and Storage Project

3 Continued pre-demolition activity in the Lower Extraction Aisle and Chemical Operating Aisle for systems disposition Continued asbestos abatement in Cold Lab of the Analytical Aisle Continued characterization of high hazardous areas MPPB Accomplishments Drilling Tell-Tale in LXA/COA Draining Piping in LXA/COA 3

4 Vitrification Facility Accomplishments Completed air gap of Vitrification Off-Gas piping between trench and 01-14 Building, including grout bulkhead Removed components containing hazardous constituents from Vit Facility Aisles (e.g., circuit boards, lamps, batteries) – formerly used for treatment Vit Off-Gas Pipe Air Gap in Trench Haz. Component Removal in Vit 4

5 01-14 Building Accomplishments Completed electrical and mechanical isolations and air gap to facility Completed removal of shielded pipe chase Shut down facility blowers and stack monitoring Completed Off-Gas and main plenum filter removal Prepared for demolition Shielded Pipe Chase Cutting Shieled Pipe Chase Air Gap 5

6 01-14 Building: Demolition Phases 6 Original Construction After Step 1 After Step 2

7 Completed demolition of: Maintenance Storage Area Product Storage Area Old Warehouse and Counting Lab Slabs Vehicle Repair Shop Vitrification Test Facility Waste Area Slab Vitrification Construction Fab Shop Slab Waste Tank Farm Test Tower Balance of Site Facilities Accomplishments Vehicle Repair Shop Demo Vit Fab Shop Slab Demo 7 Waste Tank Farm Test Tower

8 Waste Shipping Accomplishments Completed 5 of 12 low level waste (LLW) and 2 of 4 mixed low level waste (MLLW) interim shipping milestones Total volume of legacy waste shipped since contract start: ̶ 44,335 ft 3 versus plan of 41,951 ft 3 of legacy LLW Exceeds FY2012 plan 6 months ahead of schedule ̶ 1,607 ft 3 of legacy MLLW ̶ 120 ft 3 of legacy hazardous and universal waste (Completed) ̶ 814 ft 3 of legacy industrial waste Loading LLW shipment in LSA 4 LSA 4 TRU and LLW container storage 8

9 Waste Shipping Accomplishments Total volume of newly generated (NG) waste shipped since contract start: ̶ 3,696 ft 3 of NG LLW ̶ 110 ft 3 of NG MLLW ̶ 204 ft 3 of NG Hazardous and Universal waste ̶ 10,185 ft 3 of NG Industrial waste Waste Load Out of the Old Warehouse Pad 9

10 Questions? 10


Download ppt "Www.wv.doe.gov Phase I Decommissioning Project Update West Valley Demonstration Project Presented by: Bryan Bower, Department of Energy November 14, 2012."