EUG 01/02/2011 News from Electronic Modules design, manufacturing and assembly Betty Magnin TE-MPE-EM 1.

Similar presentations


Presentation on theme: "EUG 01/02/2011 News from Electronic Modules design, manufacturing and assembly Betty Magnin TE-MPE-EM 1."— Presentation transcript:

1 EUG 01/02/2011 News from Electronic Modules design, manufacturing and assembly Betty Magnin TE-MPE-EM 1

2 EUG 01/02/2011 Activity similar to 2009 1230 job requests throughout the whole section, including 260 designs (new or modifications) 710 in-house MPGD and PCB manufacturing 500 in-house assembly and repair 55 external PCB manufacturing orders 80 external assembly orders 2 TE-MPE-EM some figures for 2010

3 EUG 01/02/2011 3 TE-MPE-EM News New structure since July 2010: Move to TE-MPE, Fabio Formenti SL Design office: capacity increased by 2 since September 2010 Subcontracting: New suppliers in poorly balanced countries (DK, UK and GR) Building 107: Merge all activities from B102, B1 and B301 in a single and modern building, suited for surface finishing and PCB manufacturing. Project launched in Spring, MS in September, IT in December The study shall start in April 2011 for a finished building before the end of 2013.

4 EUG 01/02/2011 4 Building 107- project DG stated that this project is a priority for CERN Need more space for new detector developments and for new larger machines Total floor Area of the building: 3200m2 Renewed cooling and ventilation systems Safety for environnement and personnel Access control, alarms (fire and gas detection) Opportunity for EM to be grouped in one building

5 EUG 01/02/2011 5 Investment of total 785 KChf in 2010-2011 to be able to manufacture large MPGD components (RD51) –Large developing machine (DR) –Large copper etching machine (DR) –Large stripping machine (DR) –Large laminator (ordered) –Large dryer (ordered) –Large oven (ordered) –Large exposure machine(OK) –Continuous Kapton etching machine(ordered) –Electro-chemical copper etching line(study) All machines will be ordered by mid 2011 PCB manufacturing workshop

6 EUG 01/02/2010 6 General project layout TE-MPE-EM in Building 867

7 EUG 01/02/2010 7 The electronic repair workshop General purpose repair area TE-MPE-EM staff Diagnostic and repair area All declared users

8 EUG 01/02/2011 Building 867, pending actions: Collaboration with SC, RP, EL, CV, IT,… Training for staff (RPE, work in controlled areas) Order equipments for the general purpose repair area Optimize a final layout with the declared users A 260kCHF budget has been defined for this project 8 The workshop should be in operation by 2011/Q1 or Q2