Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chapter 8: Introduction

Similar presentations


Presentation on theme: "Chapter 8: Introduction"— Presentation transcript:

1 Chapter 8: Introduction
By MCA-SEM IV

2 Project implementation:
Project implementation focuses on installing or delivery the project major deliverable in the organization.-the information system that was built or purchased. The project team and PM become responsible for ensuring that the IS is responsible for ensuring that the IS is transferred successfully from the development test environment to the operational environment of the sponsor or customer’s organization. This transfer requires a tactical approach and it can be stressful time for all the stakeholders involved. Choosing an appropriate implementation approach can negatively impact the project’s remaining schedule and budget. The project team can take one of three approaches for implementing the information system. These approaches include: Direct cutover parallel phased

3 Project implementation:
Direct cutover: The direct cutover approach as shown below is an approach where the old system is shutdown and the new system is turned on. The general a target or go line date is agreed upon and the new system simply replaces the old This approach can be effective when quick delivery of the new system is critical or when the existing system is so poor that it must be replaced as soon as possible. Direct cutover may also be appropriate when the system is not mission critical i.e. the system failure will not have a major impact on the organization

4 Project implementation: Direct cutover:
Drawback: The pressure of ensuring that everything is right or having a deal with problems and irate users or project stakeholders call create a great deal of stress for the project team.

5 Project implementation: Parallel:
The parallel approach to implementation allows the old and the new systems to run concurrently for a time. At some point the organization switches entirely from the old system to the new. This approach is appropriate when problems or the failure of the system can have a major impact on the organization. E.g.: an organization may be implementing a new accounts receivable package. Before switching over completely to the new system the organization may run both systems concurrently in order to compare the o/p of both systems. This approach provides confidence that the new system is functioning and performing properly before relying on it entirely. The users will probably have to enter data into both systems and even be responsible for comparing the outputs.

6 Project implementation: Parallel:
If expected problems are encountered the target date for switching from the old to the new system may be pushed back.

7 Project implementation: Phased approach
In this approach the system is introduced in modules or in different parts of the organization incrementally as shown in fig. below. Ex: an organization may implement an accounting information system package by first implementing the general ledger components, then accounts payable and accounts receivables, and finally payroll. The phased approach may be appropriate when introducing a s/w system to different areas of the organization. E.g.: when upgrading an operating system, IT dept. may perform the upgrade on a department by department basis according to published schedule. In this case target for each department would be set to allow each department to plan for the upgrade accordingly

8 Project implementation: Phased approach
Phased approach may also allow the project team to learn from its experiences daring initial implementation so that later implementation runs more smoothly. Although phased approach may take more time than direct customer it may be less risky and much more manageable.

9 Comparison of implementation approaches:
Direct cutover Parallel Phased Implementation can be quick Provides backup in case problems are encountered with the implementation of new system. Allows for managed organized approaches for implementing systems modules in different departments. Can be risky if system is not fully tested. Can increase confidence in the new system when o/p systems and new system is compared. Experiences with early implementation can guide and make later implementations go more smoothly Places more pressure on the project team. Takes longer and may cost more than direct customer approach. Places more pressure on the users of the system. Problems encountered during early phases can impact the overall implementation schedule.

10 Project implementation:
Administrative Closure: Although all projects must come to an end, a project can be terminated for any number of reasons. Gray and Larson defined five circumstances for ending the project as below: Normal: A project that ends normally is one that is completed as planned. The project scope is achieved within the cost, quality and schedule objectives. The project is transferred to the project sponsor and the end of the project is marked with celebration, awards, and recognition for a good job done by those involved. This is an ideal situation. Premature: Occasionally, a project team may be pushed to complete a project early even though the system map not includes all of the envisioned features or functionality. Although, there is pressure to finish the project early, the risks of these decisions should be carefully thought through by all the project stakeholders.

11 Project implementation:
Perpetual: Some projects seem to take on a “life of their own” and are known as runway or perpetual projects. These projects never seem to end. Perpetual projects may result from delays or a scope that was never clearly defined or agreed upon. Failed: Sometimes projects are just unsuccessful. In general and IT project fails if insufficient attention is paid to the people, processes or technology.

12 Project implementation:
Changed Priority: In some circumstances, a project may be terminated as a result of a change in priorities. Management may decide to direct resources to higher priority projects. These changes can happen when the original importance or value of the project was misjudged or misrepresented. Ideally, a project is closed or terminated under normal circumstances. The project achieves its desired goals and objectives. Regardless of whether a project ends normally or prematurely, it is important that an orderly set of processes be followed in order to bring it to closure. A good closeout allows the team to wrap up the project in a neat, logical manner.

13 Project implementation: Project Sponsor Acceptance:
The most important requirement for closure under normal circumstances is obtaining the project sponsor’s acceptance of the project. Delivery, installation and implementation of the information system do not necessarily mean that the project sponsor or the client will accept the project’s product. Since acceptance depends heavily on the fulfillment of the project’s scope, the project manager becomes responsible for demonstrating that all project deliverables have been completed according to specifications. Documenting each deliverables and milestones throughout the project provides confidence to the project sponsor that the project has been completed fully.

14 Project implementation: The Final Project Report:
In general, the project manager and team should develop a final report and presentation for the project sponsor and other key stakeholders. The objective of the report and presentation should be to give the project sponsor confidence that the project has been completed as outlined in project plan. By gaining this confidence, the sponsor or client will be more likely to formally accept the project that will allow for a smooth termination of the project. The report may be circulated to key stakeholders before the presentation in order to get feedback and to identify any open or unfinished items that need to be scheduled for completion. Once finalized, the final project report provides a background and history of the project.

15 Project implementation: Final meeting and presentation:
If project manager has been diligent in gaining the confidence of the project sponsor , the final meeting and presentation should be a simple, straightforward affair. The final meeting is useful for: Communicating that the project is over. Transferring the information system from the project team to the organization. Acknowledge contributions. Getting formal sign off.

16 Project implementation: Closing the project:
Once the project is accepted by the sponsor, or customer, a number of administrative closure presents remain. Requirements for administrative closure includes: Verifying that an deliverables are complete. Verifying sponsors/customers formed acceptance of the project. Planning for the release of all project resources. Planning for evaluations and reviews of the project team members and the project itself. Closing of all the project accounts. Planning a celebration to mark the end of a (successful) project.

17 Project implementation: Project evaluation:
Different stakeholders will have different views of success. For the project team members, it may be gaining valuable experience and feeling that their work will have a positive impact on the organization. For the project manager-it may be leading a project that will be profitable to the firm. For client or sponsor: They may view project success in terms of organizational value received after the project implemented. Therefore four types of project evaluations should be conducted: An individual review of each team member’s performance. Post member review-by the project manager and team. An audit-of the project Evaluating project success.

18 Project implementation: Individual Performance Review
The project manager should conduct an individual performance review with each project team member Although the project organization may have its own process & procedure for conducting reviews The project manager should focus on the following points. Begin with the individual evaluating his/her performance. Focus on specific behavior, not the individual. Be consistent and fair. Review should provide a consensus on improving performance. The purpose of conducting a review or evaluation with each project team member is to provide constructive feedback for individuals No one is perfect, for understanding where an individual can improve and how they might give about improving is important.

19 Project implementation: Postmortem Reviews:
Shortly after the final project report and presentation are completed, the PM & project team should conduct a postmortem review of the project. This should be done before the project team is released from the current project. The focus of these reviews should include the following. Review the initial project movement Review the project scope , schedule, budget and quality objectives. Review each of the project deliverables. Review the various project plans and team should review its effectiveness in following area: 1) Project integration management. 2) Project scope management. 3) Project time management 4)Project cost management.5)Project quality management.6)Project human resource management 7)Project communication management.8)Project risk management 9)Project procurement management. 10) Change management. 11) Project implementation. Project management and team should identify what they did right and what they could have done better.

20 Project implementation: Project Audit:
The individual performance and post mortem reviews provide an important view of the internal workings of the project. The general, these reviews are conducted between the project manager and project team. To provide a more objective view of the project, an audit or review by an outside party may be beneficial for uncovering problems, issues or opportunities for improvement. Similar to the postmortem review, the auditor or audit team should focus on how well the project was managed and executed. This may include project plans and different management areas. The audit may involve Project Manager and project team as well as project sponsors and other key project stakeholders.

21 Project implementation: Project Audit:
In addition the third party auditor or audit team should: Have no direct involvement or interest in project Be respected and viewed as impartial and fair. Act in the organization best interest. Have a broad use of project and / or industry experience.

22 Project implementation: Evaluating Project Success:
The Mov or measurable organization value was defined at the beginning of the project. It provides the basis for taking on the project and supports many of the decision points throughout the project life cycle. The different project stakeholders and players may have different views onto whether the project was a success, it is important to assess the value that the project provides the organization. This review may be conducted may several people from both the project sponsor or clients organization and the organization or area responsible for carrying out the project. This review should focus on answering and documenting the following questions: Did the project achieve its Mov? Was the sponsor/customer satisfied? Was the project managed well? Did the project manager and teams are in a professional and ethical manner? What was done right? What can be done better next time?

23 Thanks


Download ppt "Chapter 8: Introduction"

Similar presentations


Ads by Google