Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of.

Similar presentations


Presentation on theme: "Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of."— Presentation transcript:

1 Calculating Risk of Cost Using Monte Carlo Simulation with Fuzzy Parameters in Civil Engineering Michał Bętkowski Andrzej Pownuk Silesian University of Technology, Poland

2 2/56 Risk of cost overruns We can define risk as possibility of occurrence of loss. There is always the difference between the planned costs and real costs.

3 3/56 Direct costs (DC) Indirect costs (IC) Direct costs are expenses that are directly linked to the project For example: materials, labour, equipment etc. Other costs. For example: management costs, cost of insurance etc. Calculating of cost

4 4/56 Estimating of direct cost (DC) The project can be decomposed into elements

5 5/56 Direct cost (DC) DC = Cost 1 + Cost 2+ Cost 3 Cost 1Cost 2Cost 3 MaterialsLabourEquipment

6 6/56 Methods of calculating of directional cost Deterministic Probabilistic

7 7/56 Deterministic methods of calculating costs - appearance of task is deterministic - cost of each task is deterministic

8 8/56 Calculating Risk in deterministic methods Risk in deterministic methods is taken into account as additional constant component of cost. (It is possible to express the risk in percent)

9 9/56 Typical problems with deterministic methods of calculating of costs Unknown characteristics of costs (labour, whether), - Alternative tasks, - Additional tasks.

10 10/56 Probabilistic methods Alternative tasks Additional task Changeable costs of tasks

11 11/56 Alternative tasks hamburger ColaBeer Begin End

12 12/56 Additional task hamburger ColaBeer chips End Begin

13 13/56 Changeable costs of tasks Old car is cheaper than the new one

14 14/56 Probabilistic definition of risk - real cost (random variable) - fixed cost

15 15/56 Probabilistic definition of risk Probability density function Cumulative distribution function Risk of cost

16 16/56 Beta Pert distribution

17 17/56 Beta Pert distribution

18 18/56 Beta Pert distribution

19 19/56 Alternative tasks Cost 1 Cost 2Cost 3 Total cost = Cost 1 + Cost 2 or Total cost = Cost 1 + Cost 3

20 20/56 Existing software - Pert Master, - Risk, - MS Project Etc.

21 21/56 Advantages of probabilistic methods - Express realistic character of the realization of the process. - Using probabilistic methods it is possible describe random parameters (unpredictable weather, material cost, inaccurate materials estimates)

22 22/56 Limitation of pure probabilistic methods - unique character of many civil engineering project - different conditions of the realization (weather, geological conditions, geographical region etc.) Because of that we do not know reliable statistical data

23 23/56 Main problem It is very difficult to obtain exact values of probabilistic characteristics of the structure For example: m, σ etc.

24 24/56 Basic assumption According to many experiments parameters of the system can be characterized by typical probability distribution of cost (if we know the data): - Normal distribution - Beta-Pert distribution - Lognormal distribution etc.

25 25/56 However we do not know the parameters Probability density function of costs

26 26/56 What we know? We know deterministic values of costs from the catalogue We have expert knowledge about particular cost (i.e. what happened usually) Sometimes we have some experimental data

27 27/56 Information from experts Lower bound Upper bound Most probable cost

28 28/56 If we have many experts then we can get more information Lower bound Upper bound Most probable cost

29 29/56 Fuzzy numbers (clouds) We can also ask experts about confidence intervals for different probability levels (alpha-cuts, degree of membership)

30 30/56 Confidence intervals

31 31/56 Calculation of fuzzy numbers using the data

32 32/56 Advantages of fuzzy sets description (clouds) In order to define the worst case (intervals) we do not need many information Confidence intervals can be defined for set valued data (random sets)

33 33/56 Dependency problem It is not a good idea to convert interval probability density function to interval cumulative distribution function (overestimation problem)

34 34/56 Dependency problem P-box method consider all possible probability distribution i.e. some of them do not corresponds to any parameters a, b

35 35/56 Dependency problem Envelop does not correspond to any combination of parameters

36 36/56 Probability density function with fuzzy parameters

37 37/56 Application of extension principle

38 38/56 - Risk for particular cost - Cumulative distribution function - vector of uncertain parameters

39 39/56 Modified extension principle (clouds)

40 40/56 Discretization of α-cuts

41 41/56 Monte Carlo simulations

42 42/56 Advantages of Monte Carlo method - it is possible to get full description of probability density function of the results - the method is able to take into account any type of uncertainty and dependency

43 43/56 Graph description of the system

44 44/56 Numerical results

45 45/56 Numerical results

46 46/56 Numerical results

47 47/56 Numerical results

48 48/56 Computer implementation of the algorithm Algorithm was implemented in C++ language. GSL library was also applied.

49 49/56 Numerical data for node 0

50 50/56 Description of the node Node NumberOfNode 0, NumberOfChildren 2, Children 1 3, Probability 0.415, IntervalProbability 0.088, xMinMin 198.766, xMinMax 206.016, xMidMin 215.688, xMidMax 219.313, xMaxMin 231.391, xMaxMax 238.641, ProbabilityGrids 3 NumberOfGrid 3 End

51 51/56 Types of nodes - Normal distribution (with uncertain parameters) - Beta Pert distribution (with uncertain parameters) - constant value - intervals (not implemented) - fuzzy numbers (not implemented)

52 52/56 Sum of fuzzy number and probability density function Using presented algorithm it is possible to calculate sum of probability density function and fuzzy number (clouds). In calculation one can apply: - min-max extension principle (classical solution - controversial) - new extension principle (recommended, has clear interpretation based on clouds)

53 53/56 Results: Classic extension principle: - fuzzy probability New extension principle: - fuzzy probability - fuzzy number (confidence intervals, clouds)

54 54/56 One more remark about dependency problem Due to nonlinearity alpha cat method is not always good method of transformation of confidence intervals. Because of that we have to check some additional conditions before using this method.

55 55/56 Additional information necessary for computation Results Xmin 820, Xmax 1120, NumberOfSimulations 10000, NumberOfClasses 20, NumberOfGrids 3, DistributionType 2 End

56 56/56 Conclusions Presented method allows estimating the direct cost risk of civil engineering projects in the case when there are no credible data. In presented algorithm the costs can be deterministic, probabilistic, fuzzy number. It is also possible to take into account the cost which is modeled by probability density function with fuzzy parameters. The method shows the relation between the assumed maximal direct costs, the risk of overrun and the uncertainty of the statistical data.