Harding Elementary School Exterior Repairs & Select Roofing Replacement 11/18/2014.

Similar presentations


Presentation on theme: "Harding Elementary School Exterior Repairs & Select Roofing Replacement 11/18/2014."— Presentation transcript:

1 Harding Elementary School Exterior Repairs & Select Roofing Replacement 11/18/2014

2

3  General ContractorBest Contracting Services, Inc.  Architect of RecordGrossman Design Group  Construction ManagerWillie Robinson

4  Contract Amount $918,600  Notice of Award06/17/14  Notice to Proceed07/21/14  Completion 01/05/15

5  Fabricating & installing Surround Window flashings is 95% complete.  Re-setting of Windows at Building A is 90% compete.  Stucco (scratch & brown coats) at Building A-1 upper parapet walls & west wall of Theatre is complete.  Installation of waterproof membrane and lathing at Building A-1 is 75% complete.  Clean-up, repair and environmental testing of water intrusion areas.

6 Building A-1: South wall at storefront.

7 Building A-1: Theatre West Wall – Stucco brown coasting.

8 Building A: 1 st floor windows re-installed.

9 Building A-1: Stucco brown coat at upper parapet wall.

10 Library Past Water Intrusion Damage _2 10/28/14.

11 Computer Lab Hygienist Clean –Up 10/04/14

12 Library Water Intrusion Repairs_3 11/06/14

13 Building A-1: Theatre West Wall, stucco brown coat.


Download ppt "Harding Elementary School Exterior Repairs & Select Roofing Replacement 11/18/2014."