Presentation is loading. Please wait.

Presentation is loading. Please wait.

Nathan Davis Steven Reid Kristen Ulmer Graduate Assistant: Nathan Dye.

Similar presentations


Presentation on theme: "Nathan Davis Steven Reid Kristen Ulmer Graduate Assistant: Nathan Dye."— Presentation transcript:

1 Nathan Davis Steven Reid Kristen Ulmer Graduate Assistant: Nathan Dye

2 N Design a stormwater drainage system for the city of Bluffdale Assess current infrastructure Assess current drainage needs for a 100 year 24 hour storm Design of new infrastructure using EPA SWMM Prepare a cost estimate

3 Map of Existing Inlets and Pipe Locations

4 3 Drains in Neighborhood 1 drain has no pipe exit 2 drains empty into trench  9 Drains on Northern Street Pipes over to Bangeter Highway system

5 STEPS  Create drainage basins for each inlet  Find the depth of the 100 year 24 hour storm  Calculate flow lines and accumulations  Calculate curve number using soil type and land use data  Export information into HEC- HMS Map of Drainage Basins

6 HEC-HMS Model HEC-HMS Output

7 Node Average Depth (ft) Maximum Depth (ft) 10.130.7 20.180.82 30.21.04 40.21.04 50.110.47 60.080.43 Outfall0.66 Link Max Flow (CFS) Max Depth (ft) 12.570.28 23.250.46 36.230.55 470.69 53.190.32 67.980.66 Flow Volume vs. Time in Fullest Pipe Depth of Water in Pipe vs. Time Depth of Water and Inlets Depth and Flow in Pipes

8 1 2 3 4 6 5 1b 6b 5a 2b 2a 1a 4a 3 4b 5b 6a Final Design Existing.................. Proposed……………. Pipe Labels…………… Inlet Label……………

9 Pipe IDSurface UpstreamSurface DownstreamInvert UpstreamInvert DownstreamLengthGradePipe Diameter 1445344474449.54443.5307.32.0%1.5 2444744464443.54440.5612.10.5%1.5 3445044464446.54440.5304.42.0%1.5 4444644444440.54438238.91.0%1.5 54444 44384437152.40.7%1.5 644444437 443620.05.0%1.5 Total Length1635.0 Inlet IDSurface Elevation Invert ElevationDepth of Pipe 1a44534449.53.5 1b445344503 2a44474443.53.5 2b444744443 344504446.53.5 4a44464440.55.5 4b444644415 5a444444386 5b44444438.55.5 6a444444377 6b44444437.56.5 Cross PipesUpstream InvertDownstream InvertGrade 144504449.52.1% 244444443.52.1% 444414440.52.1% 54438.544382.1% 64437.544372.1% Pipe elevation and length information Inlet elevation and box depths Cross Pipe depths

10 ITEMQUANTITYUNIT UNIT COST ITEM COST Mobilization1LS $ 8,000.00 Furnish and Install 18-inch RCP Pipe1635LF $ 52.00 $ 85,020.00 Furnish and Install 15-inch RCP Pipe152LF $ 40.00 $ 6,080.00 Manhole6EA $ 2,550.00 $ 15,300.00 Inlet8EA $ 2,200.00 $ 17,600.00 Roadway Patching596SY $ 20.00 $ 11,913.33 Remove Surface Materials (asphalt)1787LF $ 9.00 $ 16,083.00 Construction Cost: $ 159,996.33 Construction Contengencies (20%): $ 31,999.27 Engineering Design and Construction Management (15%): $ 23,999.45 Total Cost: $ 215,995.05 Total Cost (Rounded): $ 216,000.00


Download ppt "Nathan Davis Steven Reid Kristen Ulmer Graduate Assistant: Nathan Dye."

Similar presentations


Ads by Google