1 TBWG Plenary STATUS OF GSA NORTHERN BORDER PROJECTS Bill Wells Land Ports of Entry SME October 27, 2010

2 Discussion Overview Projects Recently Complete Jackman, ME Warroad, MN Blaine, WA (Peace Arch) Investment Since 2006 Project Under Construction – Portal, ND Construction starts planned in 2011/2012 Derby Line, VT Madawaska, ME Van Buren, ME Alexandria Bay, NY Program-Project Investment Outlook

3 Recently Completed Projects Jackman, Maine Estimated Total Project Cost $30.5 M Construction Award 1/2008 Construction Completed 09/2010 Gold LEED Certification

4

5 Recently Completed Projects cont. Warroad, Minnesota  Estimated Total Project Cost $45. 4 M  Construction Start 06/2008  Construction Completed 2/2010  LEED Gold Certification

6

7 Recently Completed Projects Cont. Peace Arch, (Blaine) Washington Estimated Total Project Cost $100.5 M Construction Start 08/2007 Estimated Construction Completion 12/2010 LEED Gold Certification

8

9 Projects Completed Since 2006 Calais, ME Jackman, ME Champlain, NY Massena, NY Sault Saint Marie, MI Detroit, MI Warroad MN Peace Arch, WA Capital Investment: $438M

10 Ongoing Construction Projects Portal, North Dakota Estimated Total Project Cost $39.7 M Disconnect in design, which delayed original construction completion Construction Start 06/2008 Re-rewarded construction contract after redesign Estimated Construction Completion 6/2012

11

12 2011/2012 Construction Starts Derby Line, Vermont Estimated Total Project Cost $43.5 M Construction Start 02/2011 Estimated Construction Completion 08/2013

13 Derby Line Notes: PROJECT ON HOLD. The design awarded to Orcutt Associates 1/15/09. The project on hold at CBP request CBP is opting for a de-scoped project GSA moving forward to study optimizing existing site Goal to maximize throughput at this port Construction award is planned for 9/2011

14 2011/2012 Construction Starts Cont. Madawaska, Maine Estimated Total Project Cost $69.7 M Construction Start TBD Estimated Construction Completion TBD

15 Madawaska Notes: GSA is looking into the viability of the elevated roadway connecting the existing bridge to the planned new LPOE. GSA with MDOT have had very preliminary talks of a new bridge at the existing port location as an alternative to the current elevated roadway proposal. Pending.

16 2011/2012 Construction Starts Cont. Van Buren, Maine Estimated Total Project Cost $42.0 M Construction Start 06/2011 Estimated Construction Completion 11/2013

17 Van Buren Notes: Concepts approved by Commissioner on March 18, 2010. The design/build construction contract was awarded on June 29, 2010 to J&J contractors Robert Siegel Architects

18 2011/2012 Construction Starts Cont. Alexandria Bay, New York Estimated Total Project Cost $175 M Possible Construction Start 2012 Estimated Construction Completion 6/2014

19

20 Near Future Program Richford, VT Ferry Point, ME Milltown, ME Coburn Gore, ME International Falls, MN Dunseith, ND

21 Future Program Considerations: $6 Billion program need Future projects could be re-scoped, and/or re-prioritized. Much leaner program than envisioned Tough decisions on priorities Scaled down projects Decades to modernize

22 Thank You U.S. General Services Administration 1800 F Street Washington, DC 20405 202-501-1858 (Ph. WDC) 202-281-8373 (mobile) bill.wells@gsa.gov


Download ppt "TBWG Plenary STATUS OF GSA NORTHERN BORDER PROJECTS Bill Wells Land Ports of Entry SME October 27, 2010."

Similar presentations


Ads by Google