LA Metro’s Highway Program May 29, 2014

Similar presentations


Presentation on theme: "LA Metro’s Highway Program May 29, 2014"— Presentation transcript:

1 LA Metro’s Highway Program May 29, 2014
Construction Management Association of America (CMAA) Ben Jong Transportation Program Manager Highway Program 1 1

2 Highway Projects 2

3 State Route 710 North BUDGET SCHEDULE Alternatives Analysis Dec 2012
Total Cost ($ mil.) Current $780 Forecast $2.6 – 5.4B* BUDGET Secured Funds: Measure R - $780M Unsecured Funds: $1.82B – $4.62B *Potential P3 Opportunity Construction Complete Current 2029 Forecast SCHEDULE Alternatives Analysis Dec 2012 Draft EIR/EIS Feb 2015 Public Hearing Spring 2015 Final EIR/EIS Fall 2016 Record of Decision Fall 2016 * Denotes a range of cost for several higher cost alternatives On target Possible problem Major issue

4 State Route 710 North Alternatives Analysis – completed in Dec. 2012
Alternatives: No Build Transportation System Management/Transportation Demand Management (TSM/TDM) Bus Rapid Transit (BRT) Light Rail Transit (LRT) Freeway Tunnel

5 State Route 710 North Build Alternatives
BRT LRT Freeway Tunnel* 5

6 Interstate 710 South EIR/EIS*
Construction Complete Current 2028 Forecast SCHEDULE Draft REIR/REIS Public Hearing Final REIR/REIS Record of Decision Multiple Early Action Study Projects with various schedules Cost Begin Construction Total Cost ($ mil.) Current $395 Forecast $6.75B BUDGET Secured Funds: Measure R - $395M Unsecured Funds: $6.36B – TBD *Potential P3 Opportunity *Some of these funds will be utilized for I-710 Early Action Projects On target Possible problem Major issue

7 I-710 Early Action Projects
BUDGET Current $30.6 Forecast $30.6 Total Cost ($ mil.) SCHEDULE various (see below) BUDGET (000’S) #APPR. PROJECTS COMPLETION Completed $ N/A Ongoing $10, Future $20, TOTAL* $30, *Multiple projects to be programmed with various schedules through 2030 On target Possible problem Major issue

8 High Desert Corridor (Environmental)
Cost Total Cost ($ mil.) Current $65 Forecast BUDGET Funds include: STIP (GF), Measure R, Measure I, and federal earmarks Scope includes Project Approval and Environmental Document (PA/ED) only Environmental Document Complete Current 2015 Forecast SCHEDULE Draft ED Circulation Public Hearing Final ED Record of Decision 2014 Spring 2015 Winter 2015 On target Possible problem Major issue

9 I-5 High Occupancy Vehicle/Toll Lane
Total Cost ($ mil.) Forecast $600 BUDGET Funds include: Measure R, Toll Revenues and SHOPP Construction Complete Forecast 2019 SCHEDULE RFQ RFP Mid 2015 Late 2015 On target Possible problem Major issue

10 I-605 Corridor “Hot Spot” Interchanges
Total Cost ($ mil.) Current $590M* Forecast $3.2 B* BUDGET Secured Funds: Measure R - $590M Unsecured Funds: $ 2.6B Construction Complete Current 2026 Forecast SCHEDULE Multiple projects to be programmed with various schedules through 2030 Completed Feasibility Study Project Study Report Environmental Phase *Denotes current secure funding and not expected to cover Feasibility Study improvement needs. Project costs to be determined post Feasibility Study On target Possible problem Major issue

11 Arroyo Verdugo COG Measure R Operational Improvements Program
BUDGET Current $60.3 Forecast $170 SCHEDULE Total Cost ($ mil.) various (see below) BUDGET (000’S) #APPROVED PROJECTS COMPLETION Completed $ Ongoing $ 33, Future $ 26, TOTAL $60, Measure R provides $170.0 Million over 30 years of which $60.3 Million has been programmed in the Subregion for FYs Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014. On target Possible problem Major issue 11 11 11 11

12 Las Virgenes/Malibu COG Measure R Operational Improvements Program
BUDGET SCHEDULE Current $106.75 Forecast $175 various (see below) Total Cost ($ mil.) #APPROVED PROJECTS BUDGET (000’S) COMPLETION Completed $ N/A Ongoing $ 46, Future $ 59, TOTAL $106, Measure R provides $175.0 M over 30 years, $ Million has been programmed for the Subregion by the Metro Board for FY’s Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014. On target Possible problem Major issue 12 12 12 12

13 South Bay (I-405, I-110, I-105 and SR-91) Ramp and Interchange Operational Improvements Program
BUDGET Current $235.7 SCHEDULE Forecast $906 Total Cost ($ mil.) various (see below) BUDGET (000’S) COMPLETION #APPROVED PROJECTS COG Admin/Development N/A $ 13, Contingency/Reserves N/A $ 15, Completed $ 5, Ongoing $ 135, Future $ 65, TOTAL $ 235, Measure R provides $906.0 Million over 30 years of which $235.7 Million has been programmed in the Subregion for FYs Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014. On target Possible problem Major issue 13 13 13 13

14 Upcoming Procurements A&E Professional Services
(Highway Program Look Ahead Reports) 14

15 Highway Projects in Construction
(Highway Program Look Ahead Reports) 15

16 Questions? Frank Quon, P.E. Executive Officer – Highway Program Los Angeles County Metropolitan Transportation Authority – Metro Ben Jong