CD FY08 Tactical Plan Status FY08 Tactical Plan Status Report for Network Infrastructure Upgrades Rick Finnegan April 22, 2008.

Similar presentations


Presentation on theme: "CD FY08 Tactical Plan Status FY08 Tactical Plan Status Report for Network Infrastructure Upgrades Rick Finnegan April 22, 2008."— Presentation transcript:

1 CD FY08 Tactical Plan Status FY08 Tactical Plan Status Report for Network Infrastructure Upgrades Rick Finnegan April 22, 2008

2 CD FY08 Tactical Plan Status FY08 Tactical Plan for Network Infrastructure Upgrades Relevant Strategic Plan: –Core Networking Strategic Plan FY2008 v1 Tactical Plan Leader – Rick Finnegan Organizational Unit home –LSC-CNCS-NET Tactical Plan Goals –Maintain network infrastructure capacity well ahead of current use and projected near term requirements –Network infrastructure should be maintained at the forward end of established network technology –Reliability of network infrastructure and services should be maximized –Wireless network support should be fully integrated in the general network infrastructure –The network architecture should provide for varying levels of access needs for attached systems

3 CD FY08 Tactical Plan Status Tactical Plan Activities Summary Activity* Project or Service FTE Allocated FTE Used M&S Costs Allocated for period M&S Costs Committed for period Status^ G/Y/R UpgradesPrj.45.20$131,500$66,200 Green Upgrades/Customer Prj1.05.40 Green Upgrades/CorePrj.20.14 Green Upgrades/WirelessPrj.15.19 Green Upgrades/FirewallPrj.30.05 Green Upgrades/WISMPrj.20.175 Green Upgrades/DNS-DHCP Prj.25.11 Green

4 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Customer Projects related to Customers Deliverables 1.These are planned upgrades to customer networks 2.When – throughout the year 3.Acceptance criteria is the customers accepting and planning for the upgrades 4.Recipients are Network Customers Key Milestones 1.Switch and routers to be upgraded 2.Individual upgrades planned throughout the year 3.Impact is low if the date is not met Issues and Risks (specific to this activity, includes budget impact) 1.Issues are that customers may have to endure minor outages 2.Risks are the network gear will be end of life or outages may occur

5 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Core Projects related to Core Networks Deliverables 1.These are planned upgrades to core networks 2.When – throughout the year 3.Acceptance criteria is the successful completion of the upgrades 4.Recipients are all networking Customers Key Milestones 1.Switch and routers to be upgraded 2.When planned throughout the year 3.Impact is low if the date is not met Issues and Risks (specific to this activity, includes budget impact) 1.Issues are that customers may have to endure minor outages 2.Risks are the network gear will be end of life

6 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Wireless Brief Description – Installation of additional access points Deliverables 1.Planned installs of new Access Points for additional coverage in Fixed Target, DO & CDF 2.Actual progress is on schedule 3.Acceptance criteria is the users testing the new Access Points 4.Recipients are the customers using the new Access Points Key Milestones 1.What is it – implementing new access points 2.When – The plan is 15 of 30 for the first half of the year, actual is 14 3.Impact is low and is felt by users needing additional coverage Metrics (see the next page for a chart of progress) Issues and Risks 1.Risks are that customers will continue to have no coverage until new planned Access Points are installed

7 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Wireless Metrics for new access points to improve coverage. Issues & Risks 1.The risks are that if the new access points are not install we will continue to have areas with not enough coverage.

8 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Firewall Brief Description – Rolling out the yellow zone to new subnets Deliverables 1.What is it – moving user subnets to the yellow zone 2.When – The plan is based on soliciting volunteers 3.Acceptance criteria is users being put behind the transition tool and accepting traffic flows 4.Recipient is Customer subnets Key Milestones 1.What is it – number of subnets converted to the yellow zone 2.When – plan is dependent on soliciting new customers 3.Impact is low – this is a security concern and not a functional requirement 1.URL – Project Plan http://netweb/projects/firewall.htmlhttp://netweb/projects/firewall.html Metrics – none at this time, the project is on hold Issues and Risks (specific to this activity, includes budget impact) 1.The Risks are that we are not getting groups/subnets to volunteer to move to the yellow zone. This has put the progress of the project on hold.

9 CD FY08 Tactical Plan Status Project Activity: Network Upgrades WISM Brief Description - wireless access point upgrades to Wism Deliverables 1.Planned upgrades of Access Points from IOS to WISM 2.Actual progress is ahead of schedule 3.Acceptance criteria is the users testing the converted Access Points 4.Recipient is the customers using the Access Points Key Milestones 1.What is it – the number of access points converted 2.When – planned vs actual 260 for the year, 240 are done at this point 3.Impact is medium – Customers of unconverted access points are still functioning but they do no support the WISM blocking 1.URL – Project Plan http://netweb/projects/wism.htmlhttp://netweb/projects/wism.html Metrics (see the next page for a chart of progress) Issues and Risks 1.Issues are that customers may not be willing to take minor outages, this is the case currently with the Accelerator Division

10 CD FY08 Tactical Plan Status Project Activity: Network Upgrades Wireless Metrics for upgrades of access points from IOS to WiSM Issues & Risks 1.Devices remaining to be converted are from the Accelerator Division. The timing is dependant on AD, there are no risks.

11 CD FY08 Tactical Plan Status Project Activity: Network Upgrades DNS-DHCP Brief Description – Upgrading DNS/DHCP software Deliverables 1.What is it – Upgrading DHCP/DNS to Linux and the latest software also converting all systems to standard builds to be taken over by central server management. 2.When – planned vs actual – the current progress is slightly ahead of the plan 3.Acceptance criteria is testing DHCP and DNS from selected areas of the lab 4.Recipients are all Customers at the lab. Key Milestones 1.What is it – The number of servers converted compared to the total, 13. 2.When – planned vs actual – The plan is to have half the servers converted 3.Impact is high because the current software we are running is unsupported 1.URL – Project Plan http://netweb/projects/dns.htmlhttp://netweb/projects/dns.html Metrics (see the next page for a chart of progress)

12 CD FY08 Tactical Plan Status Project Activity: DNS/DHCP Upgrade Metrics for DNS/DHCP Upgrade. Issues & Risks 1.The risks are that the current software is so old that we can not receive support from the vendor.

13 CD FY08 Tactical Plan Status Tactical Plan Issues and Risks Action Items –We need to stay focused on project upgrades even though we have a reduction in FTE’s. Issues and Risks (includes overall budget impact) –Reduction in staff could cause delays in projects. –Fewer resources could cause delays in projects. –There are no serious consequences for CD and stakeholders 1.Fewer resources working on projects due to operational activities 1.Estimated probability of occurring is medium. 2.Estimated impact is that some projects could get pushed in to next year. 3.Fall-back or Contingency plan is to add resources to key projects from other parts of the networking team.

14 CD FY08 Tactical Plan Status Tactical Plan Status Summary Status Summary –FTE’s for Operations are slightly below the targets. This will be fixed with the new hire (CP6). –A reduction in staff for the first 6 months has adversely affected the number of hours spent on projects. –Fewer resources results in a higher percentage of time spent on operations resulting in less availability for projects.


Download ppt "CD FY08 Tactical Plan Status FY08 Tactical Plan Status Report for Network Infrastructure Upgrades Rick Finnegan April 22, 2008."