ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.

Similar presentations


Presentation on theme: "ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler."— Presentation transcript:

1 ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler FNAL, A.Enomoto KEK, J.Osborne CERN ILC-GDE Beijing March 2010

2 ILC RDR Baseline Layouts for Interaction Region

3 400t 400 ton gantry crane is the cost driver large steel columns down to floor level would be needed Lot of lost space RDR Baseline for IR cavern

4 Possible layout for ILC Interaction Region for Deep Tunnel Solution using CMS concept SLAC Workshop : A.Herve (CMS) and CERN team A.Gaddi, H.Gerwig study 2007

5 Proposed new cross section for ILC Interaction Region

6 Vertical shaft Communication tunnel vertical communication shaft accelerator tunnel -20,0 Proposed Dubna typical cross section Beam tunnel 20m below surface

7 Surface building ≈ 130m long, 20m high, 40m wide Sub-surface experimental hall ≈ 90m long, 30m deep, 35m wide Proposed Dubna Solution

8 Permanent central propping needed due to large span via concrete slab This type of excavation is typically done using ‘diaphragm wall’ technique

9 Central Ventilation building feeding both areas Control room for each detector Detector in garage position

10 Detector on Beam line

11 Surface building access

12 ILC Project general view ILC 3d models developed at CERN using CATIA

13 14.Oct. 2009 CLIC_09 Workshop H.Gerwig/ A. Gaddi/ N.Siegrist Tunnel part Thin endcaps Is this ‘tunnel part’ more stable than cavern ? “Tunnel is at least ~ 10 times more stable than detector” (A. Seryi, CLIC08)

14 2004

15 2005 Stability of CMS platforms could be checked ?

16 CFS Questions Is ‘CMS’ installation concept adopted for both detectors ? Who are CFS points of contact BDS/MDI and Detectors ? Can CLIC and ILC experimental hall layouts be identical at this stage ? Costing required for CLIC CDR & ILC TDP for all technical infrastructure Dedicated CFS workshop in 2010 to gather required information ? (1/2 June KEK ?)