Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Defense Acquisition Management System 2009 Implementing DoDI 5000

Similar presentations


Presentation on theme: "The Defense Acquisition Management System 2009 Implementing DoDI 5000"— Presentation transcript:

1 The Defense Acquisition Management System 2009 Implementing DoDI 5000
May 6, 2009 John Gorrell Deputy Director, Current Acquisition 090506_CBDAIF_DODI _MDD_Gorrell

2 The Defense Acquisition Management System
DoDI (December 2008) New Policy Directed by Congress New or Revised Regulatory Policy Statutory & Regulatory Information & Milestone Requirements The Defense Acquisition Management System - Milestones, Phases and Key Activities 090506_CBDAIF_DODI _MDD_Gorrell

3 Changes to Phases A C B IOC FOC Pre-Systems Acquisition
User Needs Technology Opportunities & Resources A C B IOC FOC Materiel Solution Analysis Technology Development Engineering and Manufacturing Development Production & Deployment Operations & Support CDD CPD Materiel Development Decision Post PDR Assessment Post CDR Assessment FRP Decision Review AoA PDR PDR CDR ICD or Pre-Systems Acquisition Systems Acquisition Sustainment Materiel Solution Analysis (MSA). Major change: AoA no longer “refines” materiel solution(s) identified in the ICD. ICD will no longer contain prioritized materiel solutions. Technology Development. Major change: The TDS and associated funding must provide for two or more competing teams producing prototypes of the system and/or key system elements prior to, or through, Milestone B. PDR conducted for candidate designs and PDR report provided to MDA at Milestone B. Guided by the ICD, draft CDD, the TDS and systems engineering planning. (Note, does not mention draft CDD; however, revised 3170 will make this clear). Engineering & Manufacturing Development. Major changes: Establishment of the product baseline for all configuration items prior to P-CDR Assessment. Requires that selected production-representative article be demonstrated in their intended environment and that manufacturing processes have been effectively demonstrated prior to MS C. Names and some activities of two major efforts changed: covered later. Old (2003) New (2008) Change from 2003 Concept Refinement (CR) Materiel Solution Analysis More robust AoA Technology Development (TD) Technology Development (TD) Competitive prototyping Systems Development & Demonstration (SDD) Engineering & Manufacturing Development (EMD) More robust system engineering 090506_CBDAIF_DODI _MDD_Gorrell

4 Changes to Decision Points
User Needs Technology Opportunities & Resources A C B IOC FOC Materiel Solution Analysis Technology Development Engineering and Manufacturing Development Production & Deployment Operations & Support ICD CDD CPD Materiel Development Decision Post PDR Assessment Post CDR Assessment FRP Decision Review AoA PDR PDR CDR or Sustainment Pre-Systems Acquisition MDD: the formal entry into the acquisition process; mandatory for all programs. -At the MDD, the Joint Staff presents JROC recommendations; the Component presents the ICD with a preliminary CONOPS, description of capability needed, operational risks, and basis for why a non-materiel solution(s) will not fill the need (or completely fill the need). --The MDA approves the guidance for conduct of the AoA (for ACAT I programs, OSD/PA&E provides); determines the phase of entry into the process; and designates the lead Component. --The lead Component prepares the AoA study plan after approval of the study guidance at the MDD. Post PDR Assessment: Required only if PDR comes after Milestone B. More on PDRs later. Post CDR Assessment: -MDA conducts based on a post-CDR report from the PM. -Post CDR Report provides assessment of design maturity, a summary of the issues and actions PM intends to take to resolve the issues, assessment of risk of meeting exit criteria for EMDD phase, potential issues that could result in an APB breach. -MDA reviews the PM’s report and decides if program is ready/not ready to proceed in EMD and issue an ADM. Systems Acquisition Old (2003) New (2008) Change from 2003 Concept Decision (CD) Materiel Development Decision (MDD) MDD required prior to entering the process at any point N/A Post-PDR Assessment MDA’s assessment of PM’s PDR Report (if PDR after MS B) Design Readiness Review DRR Post-CDR Assessment MDA’s assessment of PM’s CDR Report 090506_CBDAIF_DODI _MDD_Gorrell

5 Evolutionary Acquisition
From two processes… To one process… Incremental Development: End-state is known; requirements met over time in several increments Spiral Development: End-state is not known; requirements for increments dependent upon technology maturation and user feedback. Capability delivered in increments, recognizing up front need for future capability improvements Each increment: depends on mature technology is a militarily useful and supportable operational capability Successive Technology Development Phases may be needed to mature technology for multiple increments No spirals! -EA now just one process as shown. No “spirals”. Term spiral development no longer used as an EA strategy term. “Spirals” are out. “Spiral Development” is an engineering term that will continue to be used for software development. However, using it as a “strategy” term caused problems “Increments” are in. -Each increment is a militarily-useful and supportable operational capability that can be developed, produced, deployed, and sustained. -Each increment will have its own set of threshold and objective values set by the user. -Block upgrades, pre-planned product improvement, and similar efforts that provide a significant increase in operational capability and meet an acquisition category threshold specified in this document shall be managed as separate increments. . 090506_CBDAIF_DODI _MDD_Gorrell

6 Prototyping and Competition
“The TDS and associated funding shall provide for two or more competing teams producing prototypes of the system and/or key system elements prior to, or through, Milestone B. Prototype systems or appropriate component-level prototyping shall be employed to reduce technical risk, validate designs and cost estimates, evaluate manufacturing processes, and refine requirements ” IOC B A FOC CDD CPD ICD Materiel Solution Analysis Technology Development Production & Deployment Operations & Support Engineering and Manufacturing Development FRP Decision Review Materiel Development Post CDR Assessment Post PDR PDR CDR AoA Pre-Systems Acquisition Systems Acquisition Sustainment C or 090506_CBDAIF_DODI _MDD_Gorrell

7 Material Development Decision
John Gorrell Deputy Director, Current Acquisition 090506_CBDAIF_DODI _MDD_Gorrell

8 The Defense Acquisition Management System 2008
Technology Opportunities & Resources User Needs A B C Operations & Support Strategic Guidance Joint Concepts Capabilities - Based Assessment ICD Materiel Solution Analysis Technology Development CDD MDD Engineering & Manuf Development CPD Production & Deployment O&S FCB Incremental Development OSD/JCS COCOM Acquisition Process For some, this chart better illustrates that programs may enter the process at points further to the right than the MSA phase. The change from 2003 is that now an MDD is required to determine what the appropriate entry point will be. This chart also shows the JCIDS process at the front end. The policy for JCIDS is under revision, with a revised CJCSI G due out soon. CJCSM C will be cancelled and replaced with a “manual” posted on the J8 website on the SIPRNET. Non-SIPRNET access is not known at this time. MDD is Formal Entry into Defense Acquisition Management System MDD Required Regardless of DAMS Entry Point “Following the Materiel Development Decision (MDD), the MDA may authorize entry into the acquisition management system at any point consistent with phase-specific entrance criteria and statutory requirements.” 090506_CBDAIF_DODI _MDD_Gorrell

9 Challenges Transitions from Tech Base to Acquisition Program Funding
6.2/6.3 transitions to 6.3/6.4 Requirements Maturation From MDD to Material Solution Analysis through Technology Development Phase Contracting Dual Prototyping Limits to Recompete in Later Phases 090506_CBDAIF_DODI _MDD_Gorrell

10 So What? Implications to Industry
DUAL PROTOTYPE – Technology Development Phase Early Technology Commitment in the Technology Development Phase Early Industry Resource Commitments to Compete in Technology Development Phase Industry Must Understand Requirements Early to Get in Front of the Government Process Shifts more Risk to Industry 090506_CBDAIF_DODI _MDD_Gorrell

11 Backup Slides 090506_CBDAIF_DODI _MDD_Gorrell

12 Material Development Decision (MDD)
JRO – Presents the ICD Preliminary concept of operations Description of needed capability Operational risk(s) Basis for determining the a “non-material” approach will not sufficiently mitigate the capability gap PAIO – Proposes Study Guidance for the AoA MDA – Approve the AoA Study guidance Determines the acquisition phase of entry Identifies the Milestone Reviews Designates the Lead DoD Component or Principal Staff Assistant Documents the decision(s) by ADM The AoA is not performed by the PM 090506_CBDAIF_DODI _MDD_Gorrell

13 Post MDD Material Solution Analysis Phase
Lead DoD Component Proposes an AoA Study Plan AoA assesses the preliminary material solutions Identifies key technologies Prepares and estimate of Life Cycle Costs Study Plan coordinated with the MDA; approved by the PAIO prior to start of the AoA Final AoA to be provided 60 days in advance of the Milestone Review PAIO (in this case) evaluates the AoA and provides assessment to the Lead Component/Principal Staff and to the MDA Illuminates capability advantages/disadvantages Considers joint operational plans Examination of sufficient feasible alternatives Discuss key assumptions, variability and sensitivity to changes in calculated costs, technology risk maturity (TRL), training Material Solution Analysis Phase Ends When the AoA is Completed 090506_CBDAIF_DODI _MDD_Gorrell

14 Milestone Review (MS) JPM develops for presentation at MS A
Strategy for executing MS A to MS B to include Dual (or more) Prototyping Technology Development Strategy (draft approved as part of MS review) Systems Engineering Plan (Compare/contrast FDA fulfilled requirements to programmatic) Test and Evaluation Strategy Lifecycle concept Tech Development Test Plan T & E Resourcing Strategy 090506_CBDAIF_DODI _MDD_Gorrell

15 Technology Development Phase
“Entrance into this phase depends on the completion of the AoA, a proposed materiel solution, and full funding for planned Technology Development Phase activity. At Milestone A, the MDA shall review the proposed materiel solution and the draft Technology Development Strategy (TDS). The Technology Development Phase begins when the MDA has approved a materiel solution and the TDS, and has documented the decision in an ADM. Technology development for an MDAP shall not proceed without Milestone A approval. For business area capabilities, commercially available solutions shall be preferred. A favorable Milestone A decision DOES NOT mean that a new acquisition program has been initiated.” IOC B A FOC CDD CPD ICD Materiel Solution Analysis Technology Development Production & Deployment Operations & Support Engineering and Manufacturing Development FRP Decision Review Materiel Development Post CDR Assessment Post PDR PDR CDR AoA Pre-Systems Acquisition Systems Acquisition Sustainment C or 090506_CBDAIF_DODI _MDD_Gorrell

16 PDR & CDR Milestone A Milestone B FOC Sustain Stockpile IOC Milestone C LRIP (Low Rate Initial Production ) Full Rate Production IPR (Initial Program Review) (Initial Operating Capability) Transitions to Advanced Development (Medical) Transitions to Advanced Development (Non-Medical) DoD 5000 Documentation ICD TDS SEP AoA CDD SAMP APB etc. CPD DoD Materiel Solution Analysis Technology Development Engineering and Manufacturing Development Production & Deployment Operations & Support Pre-Clinical / Clinical Development Clinical Development Regulatory Submission Post Licensure Research / Discovery Proof of concept animal studies Dose range, schedule & safety in animals Phase 1 Human Trials (safety) Animal Efficacy Trials Phase 2 Human Trials (safety/dose/schedule) BLA / NDA Submission Pivotal animal efficacy studies Phase 3 Human trials (expanded safety) Licensure FDA Review Initial assay development Clinical assay development Post marketing surveillance Biologic License Agreement / New Drug Application (Investigational New Drug) Indication(s) for use Route(s) of administration Manufacturing process (initial) Lab scale production Process development & pilot lot production Manufacturing scale up Validation & Demo Lots Consistency Lots Warm Base Manufacturing IND Submission - Product Commitment Emergency Use Authorization may be considered FDA PDR CDR PDR after initial successful human trials (Phase I Safety) The flexibility of the DoD 5000 Acquisition Program facilitates integration of DoD Acquisition and FDA regulatory requirements. All medical products must be FDA approved. Key performance parameter is licensure. KPPs must be done in order for our programs to proceed to the procurement phase. DoD has an acquisition system that requires a system-engineering like framework for each program. There are specific documentation and review required whether you are building a plane or a vaccine. The medical product development approach is tailored to integrate the much more rigid FDA process CDR after Validation & Demo lots produced successfully 090506_CBDAIF_DODI _MDD_Gorrell

17 Comparison 2003 vs. 2008 Focus of major changes
User Needs & Technology Opportunities Defense Acquisition Management Framework- 2003 A B Program Initiation C IOC FOC Concept Refinement Technology Development System Development & Demonstration Production & Deployment Operations & Support Design Readiness Review FRP Decision Review Concept Decision User Needs Defense Acquisition Management System The major differences between the 2003 and 2008 versions of the DoDI are: -The Materiel Development Decision (MDD) replaces the Concept Decision (CD). A MDD is required regardless of where the program intends to enter the acquisition process. NOTE: The arrows from User Needs/Technology Opportunities now point to the MDD at the extreme left: THIS DOES NOT MEAN THAT EVERY PROGRAM MUST ENTER AT THE MATERIEL SOLUTION ANALYSIS PHASE. This is illustrated better on chart 5. -The Materiel Solution Analysis Phase (MSA) replaces the Concept Refinement (CR) Phase. MSA is not “refinement” of the preferred solution(s) identified in the ICD. The JCIDS process no longer includes an Analysis of Materiel and Non-Materiel Alternatives. Non-materiel solutions will be handled IAW JCIDS; however, all analysis of alternative materiel solutions will be accomplished by the AoA during MSA. The MDA will approve the materiel solution at Milestone A. -Technology Development: This phase now includes a mandatory requirement for competitive prototyping of the system or key-system elements. A Preliminary Design Review (PDR) may be conducted for the candidate designs, and a PDR report will be provided to the MDA with recommended requirements trades. (The final CDD should contain trade-offs determined during the TD phase). -Engineering & Manufacturing Development (EMD) replaces System Development and Demonstration (SDD). There is more emphasis on systems engineering and technical reviews. The two major efforts have been renamed. The PM must provide a PDR report, and must provide a Critical Design Review (CDR) report to the MDA (more on this later). A Post-CDR Assessment replaces the Design Readiness Review. The MDA will determine if the results of the CDR warrant continuing EMD to Milestone C. SE is much more robust throughout all phases, with mandatory technical reviews. Technology Opportunities & Resources A B Program Initiation C IOC FOC Materiel Solution Analysis Technology Development Engineering and Manufacturing Development Production & Deployment Operations & Support Materiel Development Decision Post PDR Assessment Post-CDR Assessment FRP Decision Review PDR PDR or 090506_CBDAIF_DODI _MDD_Gorrell


Download ppt "The Defense Acquisition Management System 2009 Implementing DoDI 5000"

Similar presentations


Ads by Google