Presentation is loading. Please wait.

Presentation is loading. Please wait.

Duquesne University Forbes Expansion

Similar presentations


Presentation on theme: "Duquesne University Forbes Expansion"— Presentation transcript:

1 Duquesne University Forbes Expansion
The Pennsylvania State University Spring Semester 2007 Michael Szott Structural Option Senior Thesis Presentation Duquesne University Forbes Expansion Michael J. Szott Structural Option Duquesne University Multipurpose Facility

2 Presentation Outline Introduction Proposed Analysis
Structural Depth Study Lateral system redesign Gravity system redesign Breadth Studies Acoustics Construction cost comparison Conclusions and Recommendations Michael J. Szott Structural Option Duquesne University Multipurpose Facility

3 Location Michael J. Szott Structural Option
Duquesne University Multipurpose Facility

4 Location Michael J. Szott Structural Option
Duquesne University Multipurpose Facility

5 Project Overview Project Team Duquesne University DRS Architects
Jendoco Construction Atlantic Engineering Services Dodson Engineering Hornfeck Electrical Michael J. Szott Structural Option Duquesne University Multipurpose Facility

6 Project Overview Building Statistics Construction dates
March 2006 – December 2007/January2008 Building occupancy Mixed Use – retail, student fitness, office, entertainment Building size 7 stories – 125,000 sq. ft. Project cost $24 million Michael J. Szott Structural Option Duquesne University Multipurpose Facility

7 Project Overview Existing Structural System Gravity system
Composite steel construction Lateral system Concentrically braced frames Foundations Auger cast piles Grade Beams Michael J. Szott Structural Option Duquesne University Multipurpose Facility

8 Project Overview Typical – Floors 1-3 Michael J. Szott
Structural Option Duquesne University Multipurpose Facility

9 Project Overview Long Span Framing, Floors 4-5 Michael J. Szott
Structural Option Duquesne University Multipurpose Facility

10 Proposed Analysis Lateral Resisting System
More efficient bracing scheme? Gravity System – Vibration Analysis Intermixed activity spaces Long span conditions Interior Acoustical Performance Impact on Construction Cost Michael J. Szott Structural Option Duquesne University Multipurpose Facility

11 Structural Depth: Lateral Redesign
Lateral Bracing Locations Typical Frame Michael J. Szott Structural Option Duquesne University Multipurpose Facility

12 Structural Depth: Lateral Redesign
Three Alternate Bracing Schemes Modified concentric bracing Chevron bracing Alternating diagonals (K-bracing) Michael J. Szott Structural Option Duquesne University Multipurpose Facility

13 Structural Depth: Lateral Redesign
Design Criteria IBC 2003 ASCE 7-02 Applied Loads Dead Live Snow Wind Seismic IBC2003 section : “analysis must be performed except when structures are assigned to Seismic Design Category A” Michael J. Szott Structural Option Duquesne University Multipurpose Facility

14 Structural Depth: Lateral Redesign
Individual Frames: RAM Advanse Optimization Minimal Weight Member check Local Buckling Overall System: RAM Frame Drift check Michael J. Szott Structural Option Duquesne University Multipurpose Facility

15 Structural Depth: Lateral Redesign
Modified – Tension/Compression Chevron Bracing “K” Bracing Existing - Tension Only LC: DL+0.75LL+0.75W Michael J. Szott Structural Option Duquesne University Multipurpose Facility

16 Structural Depth: Lateral Redesign
Existing Frame Design HSS 6x4x1/4 – 8x4x5/8 Columns: W14x53 – 132 Beams: W33x118 Modified Ten. – Comp. HSS 4x3x1/4 – 9x7x1/4 Columns: W14x53 – 211 Beams: W33x118 Chevron Bracing HSS 4x3x1/4 – 10x8x3/8 Columns: W14x53 – 211 Beams: W24x76 “K” Bracing HSS 4x3x1/4 – 12x10x1/2 Columns: W10x45 – W24x131 Beams: W33x118 Michael J. Szott Structural Option Duquesne University Multipurpose Facility

17 Structural Depth: Lateral Redesign
Chevron Bracing Least weight of all systems Smallest frame beams Controlling deflection limits – L/600 or 0.3” Michael J. Szott Structural Option Duquesne University Multipurpose Facility

18 Structural Depth: Lateral Redesign
Bracing Layout HR IR 5th H/400 Existing 5.6 3.3 2.1 3.96 X-Bracing (T/C) 4.6 2.6 1.5 Chevron Bracing 4.8 2.7 K-Bracing 5 2.9 1.6 Overall Building Drift (in.) Drift at High Roof Level Drift at Intermediate Roof Level Drift at 5th Floor Level Pedestrian bridge Michael J. Szott Structural Option Duquesne University Multipurpose Facility

19 Structural Depth: Gravity Redesign
Vibration Design: AISC Design Guide 11 Floor vibrations due to human activity Criteria based on rhythmic activity Aerobics Dining and Dancing Serviceability issue – not strength Design to avoid personal discomfort Michael J. Szott Structural Option Duquesne University Multipurpose Facility

20 Structural Depth: Gravity Redesign
Four Critical Spaces Analyzed 2nd floor Aerobic/Fitness areas 3rd floor gymnasium (typical bays) 4th floor gymnasium (long spans) 5th floor ballroom (long spans) Designed for partially loaded bays Modified constant “k” used Michael J. Szott Structural Option Duquesne University Multipurpose Facility

21 Structural Depth: Gravity Redesign
Acceleration Limits Dancing/Dining g Aerobics only g Gymnasium g-0.15g (i.e. basketball, etc…) Michael J. Szott Structural Option Duquesne University Multipurpose Facility

22 Structural Depth: Gravity Redesign
Michael J. Szott Structural Option Duquesne University Multipurpose Facility

23 Structural Depth: Gravity Redesign
Existing Fitness Framing 20’8” span Beams: 7’ o.c. Girders: W16x31 (21’0”) 31’4” span Beams: 7’ o.c. Girders: W18x35 (21’0”) Michael J. Szott Structural Option Duquesne University Multipurpose Facility

24 Structural Depth: Gravity Redesign
New Fitness Framing 31’4” span Beams: 7’ o.c. Girders: W21x83 (21’0”) Michael J. Szott Structural Option Duquesne University Multipurpose Facility

25 Structural Depth: Gravity Redesign
Michael J. Szott Structural Option Duquesne University Multipurpose Facility

26 Structural Depth: Gravity Redesign
Existing Ballroom Framing 79’6” span Beams: 7’ o.c. Girders: W27x84 (21’0”) Criteria not met Michael J. Szott Structural Option Duquesne University Multipurpose Facility

27 Structural Depth: Gravity Redesign
Ballroom Redesign Departure from Design Guide 11 Partial loading vs. Fully loaded bays Michael J. Szott Structural Option Duquesne University Multipurpose Facility

28 Structural Depth: Gravity Redesign
New Ballroom Framing Conventional Beams: 7’ o.c. Girders: W30x90 (21’0”) Castellated Beams Modified wide flange sections Lighter and more stiff Economical Michael J. Szott Structural Option Duquesne University Multipurpose Facility

29 Structural Depth: Gravity Redesign
Castellated Ballroom Framing 79’6” span Beams: 7’ o.c. Girders: W27x84 (21’0”) Michael J. Szott Structural Option Duquesne University Multipurpose Facility

30 Structural Depth: Gravity Redesign
Overall Effects of New Framing Lighter gravity system Reduced clear height in both gym spaces Improved vibrational performance Cost? Michael J. Szott Structural Option Duquesne University Multipurpose Facility

31 Breadth Study: Construction Cost
Castellated Sections Less material, reduced material cost 2 man hours to convert from wide flange to castellated “…in general, spans longer than 40’ can recoup these costs.” - Billy Milligan, VP of CMC Steel Products Delivery From Hope, AR Distance: miles Cost: $65,500 Michael J. Szott Structural Option Duquesne University Multipurpose Facility

32 Breadth Study: Construction Cost
Material savings, greater than fabrication costs Delivery costs drive more expensive system Michael J. Szott Structural Option Duquesne University Multipurpose Facility

33 Breadth Study: Construction Cost
Lateral Frames Structural tubing more expensive than wide flange sections Fabrication and connection costs Chevrons bracing: least material = least cost Frame beams considerably smaller Michael J. Szott Structural Option Duquesne University Multipurpose Facility

34 Conclusions and Recommendations
A chevron bracing scheme offers a reduction in weight and material Redesigning the lateral system will save on material costs Castellated beams improve floor vibrations and decrease floor weight over long spans Gravity system costs increase slightly Suggested improvements are cost feasible Michael J. Szott Structural Option Duquesne University Multipurpose Facility

35 Questions?? ?? Michael J. Szott Structural Option
Duquesne University Multipurpose Facility


Download ppt "Duquesne University Forbes Expansion"

Similar presentations


Ads by Google