1 Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015

2 Global Settlement Review Insurance Claims Process – 3 years of negotiations and building assessments during multiple earthquakes Global Settlement completed 22 Dec 2013 Funds received 31 March 2014

3 The Past Year CPT Recovery Team appointed by July 2014 Schedule of Works completed by Oct 2014 Adopted by the Church Property Trustees in Nov 2014 Communicated to Parishes in Dec 2014 –Jan 2015

4 Recovery Programme Progress 230 projects in Recovery Programme 108 projects completed to date: 29 Vicarages 1 New Build (St Saviour’s at Holy Trinity, Lyttelton) 53 Churches 25 Halls and other buildings 7 projects currently under construction 35 projects in the planning phase

5 Schedule Overview Christchurch 12% of projects are in the Christchurch Archdeaconry 26% of projects completed 5 total loss (new build) projects to be completed with 3 in the planning phase St Mary’s Church, Merivale St Mary’s Vicarage, Merivale St Luke’s Church (combined with Durham Street Methodist) 1 total loss project under construction St John’s Latimer Square Commercial Building 4 major works projects (over $200,000) to be completed with 2 in the planning phase: St Barnabas Church, Fendalton St Michael’s Old Stone Building 3 repair projects (under $200,000)to be completed by late 2016 5 minor repair projects (under $50,000) to be completed by early 2017

6 Schedule Overview Christchurch By Dec 2015, 41% of projects are scheduled to be completed All projects are scheduled to completed by Dec 2018


Download ppt "Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015."