1 GridPP3 project status Sarah Pearce 14 April 2010 GridPP24 RHUL

2 2 GridPP24, RHUL Since last GridPP meeting LHC has turned on –First collisions in December –“First physics” 30 March –Grid seems to working as expected for all the experiments so far Tier-1 had some ‘settling in’ problems, mostly resolved R89 officially opened 2 nd tranche of T2 hardware grants issued (?) EPSRC review EGI/ROSCOE/CUE/GridTalk proposals submitted and variously accepted or rejected GridPP4 proposal written and submitted 14/4/10

3 3 GridPP24, RHUL Tier-1 Acceptance problems with one tranche of disk delivery. Now resolved - drives replaced with those of a different manufacturer Three triggers for disaster management from R89: Cooling failures in August – remedial work undertaken and work to address Building Management System problems planned Water leak onto tape robot – audit of water sources carried out and rectification Impedance problems with the UPS supply – remedial work ongoing Tier-1 procurements have been carried out. Disk and CPU have been delivered and are undergoing acceptance testing R89 opened on 30 March – same day as LHC event 14/4/10

4 4 GridPP24, RHUL EPSRC review Report explicitly mentions: GridPP’s expertise in large-scale distributed data management and analysis. Our work with start-up companies. The substantial secondary economic benefit arising from the ability to rapidly screen drugs "in-silico”. GridPP resources were used in this way to screen potential agents in the fight against bird-flu and malaria. NGS and GridPP have been highly successful, providing many users with access to more computing power than they could otherwise easily obtain. Looking forward, we recommend that these efforts, including enhanced capacity and function of distributed storage, be sustained and expanded. 14/4/10

5 5 GridPP24, RHUL EGI-Inspire etc. Wide range of project bids submitted to the EC in November: –EGI-Inspire. In negotiation, will go ahead with small changes. UK involved in security, helpdesk, monitoring, regional support (and training) –GridTalk-II. In negotiation, will go ahead. QMUL and IC UK partners: GridBriefings, GridCasts, GridCafe, RTM… May change name? –ROSCOE (SSC including HEP) – not successful. –CUE (Training, outreach) – not successful 14/4/10

6 6 GridPP24, RHUL December performance Tier-1 Efficiency for all 4 LHC experiments over 90% Delivered a record amount of CPU to wLCG Tier-2s ScotGrid 98% availability/ 98% reliability NorthGrid 98%/98% reliability SouthGrid 97%/98% reliability LondonGrid 91%/94% reliability All above 90% threshold 14/4/10

7 7 GridPP24, RHUL UKI CPU contribution CPU April 2010 ? 14/4/10 Since GridPP23 2009 up to GridPP23

8 8 GridPP24, RHUL UKI Tier-1 & Tier-2 contribution 14/4/10 Since GridPP23 GridPP22-GridPP23

9 9 GridPP24, RHUL CPU efficiency September 09 – April10 14/4/10

10 10 GridPP24, RHUL Storage From gstat (and previous talks…) September 2008March 2009September 2009 April 2010 14/4/10

11 11 GridPP24, RHUL Since data taking started 14/4/10

12 12 GridPP24, RHUL Project Map GridPP3 Q4 08 14/4/10

13 13 GridPP24, RHUL ProjectMap Q4 09 14/4/10

14 14 GridPP24, RHUL Project map - statistics MetricsMilestones 14/4/10

15 15 GridPP24, RHUL Experiments - red metrics ATLAS One red metric, due to problems with T1 disk acceptance Job success rate and T1 data availability up LHCb Red metrics similar to last quarter. Low numbers of jobs account for some. RAL downtime from database issues reduced T1 LHCb SAM tests uptime T2 SAM tests low due to issues with EFDA and UCL CMS ‘Good quarter’ Other experiments Efficiency up to 82% in December, with ALICE data Fractions used by other experiments down (7.6% of T1 CPU, compared with 14% in Q3) New users: T2K, Super-B, SuperNemo 14/4/10

16 16 GridPP24, RHUL Grid services Operations 2.1.3 Fraction of KSI2k used (Target 80%, achieved 61%). 2.1.6 Job success rates – no longer use this metric, as SLL test results unreliable Security One red milestone – site security review. Questionnaires sent out in December. Mingchao will report at this meeting Security incident at Oxford: well handled 14/4/10

17 17 GridPP24, RHUL Tier-1 T1 operated well during data taking in Nov/Dec Work on UPS supply problems continuing. Other issues resolved (cooling, water leak) One tranche of disk capacity failed acceptance – now solved MoU commitment for tape not met, due to change in requirements because of LHC schedule Milestones 3.4.21 General ADS Service Ends. Major users have been migrated. Considering next steps. Milestone 3.3.31 R89 document available. A document detailing the trasition to R89 was published in March and is available on request. 14/4/10

18 18 GridPP24, RHUL Tier-2s % of promised disk and CPU available – green for all Tier-2s (metrics 1&2). SAM availability and reliability tests green or orange (so above 90%) for most Tier-2s (metrics 3&4). Metric 5 (SLL ATLAS test) now suspended Other red metrics: Average SLL SE test performance (metric 6) London CPU utilisation (wall clock time & CPU time, metrics 7/8) LondonGrid, SouthGrid Number of management meetings NorthGrid (metric 11) Tier-2 meeting LCG MoU service levels (metric 14) LondonGrid –UCL-central: slow to install kernel update - site taken offline 14/4/10

19 19 GridPP24, RHUL Management and external Project execution – red metrics Quarterly reports target not met (too much focus on GridPP4!) Rest of Map No red metrics 14/4/10

20 20 GridPP24, RHUL Finances - summary 14/4/10

21 21 GridPP24, RHUL Finances: Tier-1 hardware Tier-1 disk purchase FY09 increased in order to address potential shortfall: now allows for half a year buffer in disk £661k moved forward into FY09 from FY10, at the request of STFC Hardware requirements re-profiled, as a result of changes in LHC schedule Likely charge for networking costs pa, due to new arrangement between research councils and JISC 14/4/10

22 22 GridPP24, RHUL Finances: Tier-2s and staff Second tranche of Tier-2 hardware agreed 0.5FTE CMS support post at RAL delayed due to recruitment restrictions. Increased to 1FTE for FY10, to compensate for delay. Bridging funding to retain expertise of some EGEE-funded staff where posts are envisaged to continue in GridPP4. 14/4/10

23 23 GridPP24, RHUL In parallel 14/4/10

24 24 GridPP24, RHUL EGEE moves to EGI 4/2/10

25 25 GridPP24, RHUL And data comes… 4/2/10