University of Peradeniya1. Name of the Project: Construction of Chemical Engineering Building Stage II Faculty of Engineering. (CW/CON/2012/935) Contractor:State.

Similar presentations


Presentation on theme: "University of Peradeniya1. Name of the Project: Construction of Chemical Engineering Building Stage II Faculty of Engineering. (CW/CON/2012/935) Contractor:State."— Presentation transcript:

1 University of Peradeniya1

2 Name of the Project: Construction of Chemical Engineering Building Stage II Faculty of Engineering. (CW/CON/2012/935) Contractor:State Engineering Corp Date of Award the Contract: 2014-06-27 Total Cost of the Project : Rs. 85,489,600.00 (With VAT) Expected Date of Completion: 2015-07-10 Financial Progress: Date of Mobilization Advance: 2014-10-16 (Rs. 36,110,981.42 ) 42% University of Peradeniya 55% Physical Progress: 2

3 Name of the Project: Construction of Building for the Department of Management Studies – Stage II Faculty of Arts. (CW/CON/2011/892) Contractor:ASB Construction (Pvt) Ltd Date of Award the Contract: 2014-06-27 Total Cost of the ProjectRs. 92,936,317.06 (With VAT) Expected Date of Completion: 2015-07-14 Financial Progress:Date of Mobilization Advance: 2014-10-02 Physical Progress: 60% (Rs. 37,145,241.14) 40% University of Peradeniya3

4 Name of the Project:Proposed Extension to the Surgical Ward Faculty of Medicine (CW/CON/2013/964) Contractor:State Engineering Corp. Date of Award the Contract: 2014-07-11 Total Cost of the Project : Rs. 80,937,642.03 (With VAT) Expected Date of Completion: 2016-07-24 Financial Progress:Date of Mobilization Advance: 2014-10-16 Physical Progress: 25%  Four Storied Buiding (Rs. 21.068.603.16) 26% University of Peradeniya4

5 Name of the Project:Master Plan Development of the Faculty of Agriculture – Phase I (CW/CON/2007/755) Contractor:Sathuta Builders (Pvt) Ltd Date of Award the Contract: 2014-07-11 Total Cost of the Project: Rs. 892,956,226.20 (With VAT) Expected Date of Completion: 2017-02-28 Financial Progress: Date of Mobilization Advance: 2015-04-10 Physical Progress: 30% (Rs. 255,285,039.60) 29% University of Peradeniya5

6 Name of the Project: Proposed Five Storied Building Complex for the Faculty of Dental Science. (CW/CON/2011/898) Contractor:Trio Construction Date of Award the Contract: 2014-07-25 Total Cost of the Project : Rs. 207,338,895.60 (With VAT) Expected Date of Completion: 2016-02-19 Financial Progress: Date of Mobilization Advance: 2014-10-07 Physical Progress: 20% (Rs. 49,204,065.64 ) 24% University of Peradeniya6

7 Name of the Project:Construction of Building for the Faculty of AHS (CW/CON/2007/743) Contractor:Waterman (Pvt) Ltd Date of Award the Contract: 2011-11-28 Total Cost of the Project: Rs. 43,214,599.16 (With VAT) Expected Date of Completion: 2013-06-14 Extension Granted : 2015 April Financial Progress: Date of Mobilization Advance: 2012-04-02 Physical Progress:60%  Terminated the Contract.  Action has been taken to call Tenders to complete the balance work of the Basement (Rs. 22,090,721.01) 51% University of Peradeniya7

8 Name of the Project: Construction of New Building for the Department of Statistics and Computer Science Faculty of Science (CW/CON/2011/891) Contractor:Central Suppliers (Pvt) Ltd Date of Award the Contract: 2014-06-27 Total Cost of the Project : Rs. 174,966,400.00 (With VAT) Expected Date of Completion: 2015-12-26 Financial Progress: Project Delay due to site change Physical Progress:  Original location had to be changed due to unforeseen underground high tension power cables. New site preparation completed.NBRO has substantially approved the site. Preparation of Structural design is in progress. University of Peradeniya8

9 Name of the Project: Expansion of the Student Hostel at Sarasaviuyana. (CW/CON/2009/843) Contractor:ASB Construction Date of Award the Contract: 2013-10-15 Total Cost of Project : Rs. 77,739,160.97 (With VAT) Expected Date of Completion: 2014-10-27 Financial Progress: Date of Mobilization Advance: 2013-11-15 Physical Progress: 93% (Rs. 53,577,643.31 ) 68% University of Peradeniya9

10 Name of the Project: Proposed Building for the Clinical Research & Service Laboratory Faculty of Medicine – Stage I (CW/CON/2010/883) Contractor:SEC Date of Award the Contract: 2013-05-13 Total Cost of the Project: Rs. 38,778,142.03 (With VAT) Expected Date of Completion: 2014-03-07 Financial Progress: Date of Mobilization Advance: 2013-07-02 Physical Progress: 100% Rs. 24,024,963.36 62% University of Peradeniya10

11 Name of the Project: Construction of Para Clinical Building (Stage II) (CW/CON/2011/910) Contractor:SEC Date of Award the Contract: 2013 -05-30 Total Cost of the Project : Rs. 608,874,537.92 (With VAT) Expected Date of Completion: 2015 July 14 Financial Progress: Date of Mobilization Advance: 2014-10-02 Physical Progress: 45% (Rs. 183,784,948.07) 30% University of Peradeniya11

12 Name of the Project:Para Clinical Building Stage I - Faculty of Medicine (CW/CON/2005/662) Contractor:SEC Date of Commencement: 2005-08-11 Total Cost of the Project: Rs. 280,000,000.00 (With VAT) Expected Date of Completion: 2008-08-30 Extention Granted : 2013 April 30 Financial Progress: Rs. 219,736,900.90 78% Date of Mobilization Advance: 2005-10-10 Physical Progress: 100% University of Peradeniya12


Download ppt "University of Peradeniya1. Name of the Project: Construction of Chemical Engineering Building Stage II Faculty of Engineering. (CW/CON/2012/935) Contractor:State."