LESSONS LEARNT ON THE BASIS OF ACCIDENT ENQUIRY REPORT OF CRS ( LEVEL CROSSINGS )

Similar presentations


Presentation on theme: "LESSONS LEARNT ON THE BASIS OF ACCIDENT ENQUIRY REPORT OF CRS ( LEVEL CROSSINGS )"— Presentation transcript:

1 LESSONS LEARNT ON THE BASIS OF ACCIDENT ENQUIRY REPORT OF CRS ( LEVEL CROSSINGS )

2 LEVEL CROSSING GATE ACCIDENTS CONSTITUTE 16% OF TOTAL ACCIDENTS ON INDIAN RAILWAYS, BUT ACCOUNT FOR 46% FATALITIES. CRS CONDUCTED ENQUIRY AND SUBMITTED HIS REPORTS ON LC COLLISION/DASHINGS HAPPENED IN VARIOUS RLYS. COULD LAY HANDS ON 17 NOS OF MANNED AND ONE U/M LC COLLISION/ DASHING REPORTS 65 PERSONS KILLED, 49 SERIOUSLY INJURED AND 79 SIMPLE INJURIES. THE CAUSE OF ACIDENT, RECOMMENDATIONS AND RESPONSIBILITY FOR 17 REPORTS ARE ANALYSED IN DETAIL, CORRECTIVE ACTIONS TO BE TAKEN ARE DISCUSSED. INTRODUCTION

3 CAUSE OF COLLISIONNUMBER CASUALITIES K GI SI FAILURE OF RAILWAY. STAFF10 38 23 35 FAILURE OF OTHER THAN RAILWAY STAFF 04 24 12 32 FAILURE OF RLY STAFF + OTHER THAN RAILWAY STAFF 03 03 14 12 TOTAL17 65 49 79 ANALYSIS OF COLLISIONS IN MANNED LEVEL CROSSINGS

4 COLLISIONS DUE TO FAILURE OF RAILWAY STAFF CAUSE OF COLLSION NO CAUSALITIES K GI SI GATEMAN EXCHANGED PN BEFORE CLOSING THE GATE O3 06 16 23 GATE KEPT KEPT OPENED TO ROAD TRAFFIC AGAINST NORMAL POSITION OF CLOSED 02 04 04 11 PN NOT EXCHANGED BY STATION STAFF 02 09 01 - OPENED GATE WITHOUT OBSERVING TRAIN 02 18 01 01 GATEMAN AND ASM BOTH FAILED TO EXCHANGE PN TOTAL 01 10 01 01 - 28 23 35

5 COLLSIONS DUE TO OTHER THAN RAILWAY STAFF CAUSE OF COLLSIONNUMBER CASUALITIES K GI SI ROAD VEHICLE DRIVER CRASHING THE LC GATE 02 10 08 27 LIFTING BARRIER FAILED AND ROAD DRIVER OVERSHOOTED CHAINED GATE 01 03 01 05 ROAD DRIVER CROSSING TRACK ADJACENT TO THE CLOSED LC GATE 01 11 03 - TOTAL04 24 12 32

6 COLLISIONS DUE TO RAILWAY STAFF AND OTHER THAN RAILWAY STAFF CAUSE OF COLLISIONNO CASUALITIES K GI SI GATE KEPT OPENED AGAINST NORMAL POSITION, WHILE CLOSING GATE, ROAD DRIVER OVERSHOOTED 01 - 03 02 TRAIN DRIVER NOT ADHERED CAUTION ORDER, ROAD DRIVER OVERSHOOTED CHAINED GATE 01 02 07 04 OPENING GATE BY FORCE TOTAL 01 03 01 04 06 03 14 12

7 SUMMARY 60% OF ACCIDENTS AT MANNED LC IS ON ACCOUNT OF RAILWAY STAFF FAILURE 24% 0F ACCIDENTS ARE ON ACCOUNT OF OTHER THAN RAILWAY STAFF FAILURE 16% OF ACCIDENTS ARE ON ACCOUNT OF COMBINED FAILURE OF RAILWAY STAFF AND OTHER THAN RAILWAY STAFF ULTIMATELY IT CAN BE CONCLUDED THAT 76% OF ACCIDENTS ON ACCOUNT OF RAILWAY STAFF FAILURE DIRECTLY OR INDIRECTLY

8 SHORT TERM MEASURES TO PREVENT ACCIDENTS IN MANNED LC IMMEDIATE COUNSELLING OF STAFF TO ADHERE WORKING INSTRUCTIONS, CONSTITUTION OF SUPERVISORS TASK FORCE TO CERTIFY CORRECTNESS OF GATE WORKING INSTRUCTION WITH STN. INCREASE SURPRISE INSPECTION TO ENSURE THAT STAFF FAITHFULLY FOLLOW WORKING INSTRUCTIONS, EXCHANGE OF PN, NORMAL POSITION OF GATE, PLANTING BANNER FLAG, DIVISIONAL LEVEL ONE WEEK TRAINING FOR GATEMAN / GANGAMN AND ISSUE OF CERTIFICATE ONLY BY THEM, CROSS CHECKING BY SUPERVISORY STAFF THE PN EXCHANGE FOR TRAINS FOR ATLEAST ONE DAY IN A MONTH. CONTD…..

9 SHORT TERM MEASURES TO PREVENT ACCIDENTS AT MANNED LCS PLANT BANNER FALG AT 5M AWAY FROM GATE WHEN GATE IS KEPT OPENED FOR TRAFFIC IN NON INTERLOCKED GATE, THIS TO BE INCLUDED AS A TOOL IN LC TOOL LIST COUNSELLING STATION STAFF NOT TO OBTAIN PN FROM GATEKEEPERS SOONER THAN ABSOLUTELY REQUIRED TAKE ACTION ON INSPECTING OFFICIALS WHO HAVE NOT COMPLETED THEIR SHEDULE OF INSPECTION PERIODICAL PUBLICITY COMPAIGNS TO BE LAUNCHED AGAINST LC ACCIDENTS BY RAILWAYS AND NOT TO HARASE GATEMAN FILL UP VACACIES OF GATEMAN WITH GANGMAN IMMEEDIATELY CONTD

10 INTERIM MEASURES TO PREVENT ACCIDENTS IN MANNED LCS UPGRADATION OF LCS IMMEDIATELY IN ACCORDANCE WITH BOARD LETTER, REVISE PROFORMA FOR LC INSPECTION AND RECORDINGS, CONNECT LC WITH ELECTRICITY, IF NOT, ATLEAST WITH SOLAR ENERGY, ERRECT ELECTRICALY LIT ROAD WARNING BOARDS ON STATE / NATIONAL HIGHWAYS BY RAILWAYS, TRAIN ACUATED WARNING DEVICES IN MANNED NON INTERLOCKED LCS PROVISION OF FLASHING LIGHTS, AUDIO WARNING BUZZER, TELEPHONE WITH DTMT CALLING SYSTEM TO BE PROVIDED, PROVIDE ROAD DIVIDERS ON LC APPROACHES TO PREVENT JAMMING OF ROAD VECHICLES CONTD

11 INTERIM MEASURES TO PREVENT ACCIDENTS IN MANNED LCS CONTD….. PROVIDE STEEL CHANNEL BARRIERS ON VOLNURABLE GATES PROVIDE SECOND LIFTING BARRIER WHEREVER CRASHING HAPPENED, RAIL-BUS COLLISION WARNING BOARDS ON ACCIDENT PRONE LCS TO BE PROVIDED, MINIMUM EDUCATIONAL QUALIFICATION OF GATEMAN TO BE 10+2 AND HIGHER GRADE IN GROUP “C “, SUPPLY WALL CLOCK TO LCS TO NOTE CORRECT TIMINGS STATE GOVERNMENT TO PROVIDE STRONGER BARRIER AND WARNING BOARDS WHEREVER LCS ARE DIVERTED, IMPLICITLY IMPLEMENT ROAD WIDTH, GRADIENT ON LC AND ITS APPROACHES, WARNING BOARDS ETC AS PER CHAPTER IX OF IRPWM,

12 REVIEW OF POLICY DECISIONS BY BOARD RAILWAY BOARD MAY REVIEW THE POLICY DECISION ON THE COST SHARING MECHANISM OF CONSTRUCTION OF ROB / RUB ETC. TO ELIMINATE LCS ON NATIONAL HIGHWAYS/STATE HIGHWAYS IN A TIME BOUND PROGRAME RAILWAY BAORD MAY REVIEW THE TVUS CRITERIA IN ORDER TO PROVIDE AT LEAST MANNED INTERLOCKED LCS ON DISTRICT ROADS AND BUSY ROAD LCS

13


Download ppt "LESSONS LEARNT ON THE BASIS OF ACCIDENT ENQUIRY REPORT OF CRS ( LEVEL CROSSINGS )"