COMMA: Coordinating the Migration of Multi-tier Applications Jie Zheng, T. S. Eugene Ng, Zhaolei Liu Rice University Kunwadee Sripanidkulchai NECTEC, Thailand.

Similar presentations


Presentation on theme: "COMMA: Coordinating the Migration of Multi-tier Applications Jie Zheng, T. S. Eugene Ng, Zhaolei Liu Rice University Kunwadee Sripanidkulchai NECTEC, Thailand."— Presentation transcript:

1 COMMA: Coordinating the Migration of Multi-tier Applications Jie Zheng, T. S. Eugene Ng, Zhaolei Liu Rice University Kunwadee Sripanidkulchai NECTEC, Thailand VEE’14

2 Motivation Live migration can migrate single VM efficiently. Existing solutions on migrating VMs in a multi-tier application can cause serious performance degradation.

3 Multi-tier Application

4 Split-components Problem

5 Existing Solutions

6 Problem Formulation Given a set of n VMs in a multi-tier application. Minimize the performance degradation, or impact. ◦ TM[i,j]: communication traffic rates between VMs prior to the start of migration.

7 COMMA “COordinating the Migration of Multi-tier Applications” ◦ The first migration coordination system for multiple VMs. ◦ Centralized architecture. ◦ A two-stage scheduling.

8 Two-stage Scheduling First stage: migrates static content. Second stage : migrate dynamically generated content.

9 First Stage Migrate VMs in parallel and finish all VMs’ data migration at the same time. ◦ The amount of migrated data is fixed. Adjusts each VM’s migration speed according to its virtual disk size

10 Second Stage Migrate dynamically generated content. ◦ After the first stage, a set of dirty blocks are recorded. ◦ The minimum migration speed of a VM must be greater than its block dirty rate. VMs are divided into groups.

11 Inter-group Scheduling To minimize the impact. Brute-force ◦ O(2 n *n!)

12 Inter-group Scheduling(Cont.) To minimize the impact. Heuristic ◦ Repeatedly take the largest rate element (rate, VM i, VM j ) from the list L, check if VM i and VM j are already in the group set S.  Merge group or insert new groups. ◦ Find the permutation of groups in S with minimal impact ◦ O(n!)

13 Intra-group Scheduling Starting the VMs’ migration at the same time is not an efficient use of available migration bandwidth.

14 Intra-group Scheduling(Cont.) Estimate the migration time of each VM. ◦ Assume the minimal required speed for each VM is equal to the VM’s maximal dirty rate “Finish migration at the same time” ◦ Set different start time to each VM. Extra available bandwidth will be allocated to the VMs to minimize the total migration time of the group.

15 Evaluation-Setting Six physical machines. Kernel-based Virtual Machine(KVM) Multi-tier application: RUBiS ◦ Includes web server, application server, database server. Performance metric: average response time of the request from clients per second.

16 Migrate 3VMs with different strategies. Evaluation-Performance

17 Evaluation-Impact Migrate 4 VMs from at most three physical machines to the other three.

18 Evaluation-EC2 Migrate 2 SPECweb2005 VMs from a university campus network to EC2 instances.

19 Conclusion Propose COMMA, the first coordinated live VM migration system for multi-tier applications. ◦ Based on a two-stage scheduling algorithm to coordinate the migration of VMs. ◦ The goal is to minimize the migration’s impact on inter-component communications.