Presentation is loading. Please wait.

Presentation is loading. Please wait.

Simulation Based Production Planning, Scheduling, and Control Johannes Krauth Sim-Serv.

Similar presentations


Presentation on theme: "Simulation Based Production Planning, Scheduling, and Control Johannes Krauth Sim-Serv."— Presentation transcript:

1 Simulation Based Production Planning, Scheduling, and Control Johannes Krauth Sim-Serv

2 Overview Planning Steps Methods Applied The Contribution of Simulation Examples The Future

3 Planning Steps Production Programme Planning / Plant or Process Design (time horizon: years) Production Planning (months / weeks) Detailed Scheduling (days / hours) Control

4 Overall Planning Objectives Maximise Capacity Utilisation Minimise Delays Minimise Throughput Times Minimise Work in Progress Note: Conflicting Objectives!!

5 Facility Planning Based on assumed demand Searches “optimal” match of needed and available capacity Planning horizon: years Not an ongoing activity

6 Optimal Match Needed per year: 10,400 h milling ______________ 8,500 h welding … Available per year: 4 machines = 5376 h (1 shift, 80% utilis.); = 10752 h (2 shifts) __________________ 4 workers = 8400 h 5 workers = 10080 h … ?

7 Limitations no interdependencies taken into account based on estimated / experienced degrees of capacity utilisation adequate for strategic, long-term planning, when little information is available

8 Production Planning Based on (expected) customer orders Using fixed throughput times per step (based on experience or assumptions) Accepts / rejects orders and fixes start and end dates

9 Example: Assumed and Real Durations DepartmentEstimated Throughput Time Process Time Lathing20 days1 hour Machining5 days20 hours Surface Treatm.7 days1.5 hours Polishing7 days10 hours Assembly15 days20 hours Total54 days52.5 hours

10 Limitations Capacity assumed available Actual shop floor status not taken into account Waiting times included and therefore fixed Applicable only when long delivery times are acceptable

11 Production Scheduling Planning Horizon: 1 week – 1 day Based on confirmed orders and actually available resources Must take into account technical restrictions Finds exact sequence of operations per work station

12 Production Scheduling Must be “fit for reality”!

13 Contribution of Simulation Detailed models Exact representation of all processes, all needed resources Realistic transition times, based on current shop floor status All kinds of rules and constraints can be taken into account

14 Ways to Use Simulation: MRP /ERP System Simulation Model controls feeds back 1. Offline, from outside

15 Ways to Use Simulation 2. Online, as part of planning toolbox MRP / ERP System: Long Term Planning Module_____________________ Medium Term Planning Module___________________ Scheduling Module: Simulation Model Shop Floor

16 Typical “Leitstand” / APS tool

17 Contribution of Optimisation Can use a large variety of criteria for “optimal” solutions Finds very good schedules quickly Takes away hours of routine work from the planners Allows them to focus on the essentials

18

19 Examples 2 Examples: Simulation helps optimise planning tool and process 4 Examples: Simulation and Optimisation modules as part of planning toolbox

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36 Conclusion from Examples: Broad range of industry sectors Leitstand / APS tools can complement existing MRP / ERP tools or run stand-alone Typical benefits include Higher capacity utilisation Less WiP Less delays, shorter throughput times Payback often within a few months!!

37 Summary Simulation Based Scheduling and Control offers substantial advantages Many approaches available for different special requirements Also useful for SMEs Sim-Serv assists with selection of best suited approach


Download ppt "Simulation Based Production Planning, Scheduling, and Control Johannes Krauth Sim-Serv."

Similar presentations


Ads by Google