Presentation is loading. Please wait.

Presentation is loading. Please wait.

Mock State Aid Project County Highway Accountant’s Conference 2015.

Similar presentations


Presentation on theme: "Mock State Aid Project County Highway Accountant’s Conference 2015."— Presentation transcript:

1 Mock State Aid Project County Highway Accountant’s Conference 2015

2  Obtain SAP # from District State Aid Engineer (DSAE)  Submit plan to DSAE for review and approval  After approval setup project in your Contract Management system along with Engineer’s Estimate  After project has been let, enter the bid amounts into your Contract Management system  Contract is awarded to the most responsible contractor who may or may not be the lowest bidder Steps Leading up to 1 st Pay Request

3  Separate pay request for each SAP #  Remember to include tied to Project numbers on line below  Submit after the award of contract  May request  95% of state aid eligible construction items  95% of Right of Way appraisal costs or 100% of actual purchase price with proof of payment  100% of Engineering costs up to a cap of 25% of the state aid eligible construction costs Exceptions: Projects funded by State Bonds, such as bridge bonds, LRIP, special legislative bonds etc., are paid as a reimbursement only. (If tied to a DCP Project, Bond Funds will be paid with the DCP Payment Request Form.) First Partial State Aid Pay Request

4  State Aid Payment Request: Signed by County Engineer or Assistant Engineer  Bid Award Information submitted by electronic file to SALT. See attachment for details.  Distribution of Costs: A spreadsheet showing the split between state-aid eligible items, storm sewer items, and non-participating items. Also, split between SAP’s if there is more than one. If project contains only one SAP and is 100% state-aid eligible, no spreadsheet is needed.  Right of Way Documentation: Submit a Right of Way Certificate showing actual expenditures. This must First Partial State Aid Pay Request Checklist

5  ROW cont..: Include the parcel number, price paid, person/business paid, and proof of payment (copy of checks, electronic transfer number etc.). Legal costs, title fees and other administrative costs may be lumped together and shown on one line – retain the documentation for audit purposes.  Engineering Costs: No back up documentation is required. Engineer’s signature certifies that the amount requested does not exceed the actual cost. Engineering costs cannot exceed 25% of state aid eligible items. Combine preliminary & construction engineering.  Force Account (FA) Costs: must have an executed FA on file. Payment is 95% of the Schedule of Costs shown on the FA. First Partial State Aid Pay Request Checklist (continued)

6  State Aid Payment Request: same as Initial Request  Copy of Payment Voucher to Contractor: Shows to date quantities and amounts actually paid out to contractor  Distribution of Costs: same as Initial Request  Right of Way: same as Initial Request  Supplemental Agreements/Work and Change Orders: Include all Supplemental Agreements, Work Orders and Change Orders  Engineering Costs: same as Initial Request  Force Account Costs: same as Initial Request Subsequent Partial State Aid Pay Request - Checklist

7  State Aid Payment Request: same as Initial Request except make sure Final is checked and the total project costs are equal to the total paid to the contractor  Copy of Final Payment Voucher to Contractor: Shows final quantities and amounts actually paid out to contractor  Distribution of Costs: same as Initial Request  Right of Way: same as Initial Request  Supplemental Agreements/Work and Change Orders: Include all Supplemental Agreements, Work Orders and Change Orders  Engineering Costs: same as Initial Request  Force Account Costs: Include documentation of force labor costs or an invoice from an external source like utilities or railroad. Final State Aid Pay Request Checklist

8  Projects using state bonds such as Bridge or special legislative programs like Local Road Improvement Program and Flood Bonds  State bond funds are “reimbursement” only funds unlike state aid funds which may be paid out before the project is started. Bond funds can only be paid up to the actual expenditure of participating costs as shown on a partial or final contractor payment voucher.  These projects need all the same documentation shown on previous checklists in addition to:  Abstract of Bids on Bridge Bond funded projects sent in early so Bridge Bond grant amount can be determined by State Aid Finance. Bridge items should be highlighted.  Bond Agreement with County Resolution: The resolution states the exact amount of the bond granted to the project and states that the local agency will return any bonds funds not used on the project and fund any excess costs Special Bond Funds Pay Request Checklist

9 For DCP projects, the state bonds are requested with the Federal DCP pay request. Do not use the SAPR (State Aid Pay Request) form for the construction bond funds. The only bond funds that may be requested, for the DCP projects on the SAPR, are engineering costs if they were approved in the bonding agreement. Special Bond Funds Pay Request DCP Notes

10 Recognize receivable from State Aid and reduce the allotment Accounting Entries – for amount of State Aid Construction Obligation ONLY - $452,019.38 Debit: (asset) State Aid – Receivable Credit: (asset) State Aid – Allotment NOTE: This is only for the State Aid Construction Obligation shown on the SAPR SAPR – Contract Receivable

11 Accounting Entries – for 95% of State Aid Construction Obligation ONLY - $429,418.41 Debit: (asset) Cash Credit: (asset) State Aid – Receivable NOTE: Be sure to break up the entry of your receipt by what you are being paid for (Contract Construction, Engineering, Utility Relocation and/or Right of Way) SAPR – 95% State Aid Contract Receipt

12 Accounting Entries – for the amount of Engineering, Utility Relocation or Right of Way, if any - $100,000.00 Debit: (asset) Cash Credit: (asset) State Aid – Allotment NOTE: Be sure to break up the entry of your receipt by what you are being paid for (Contract Construction, Engineering, Utility Relocation and/or Right of Way) SAPR – Engineering, Utility Relocation and Right of Way Receipt

13 Accounting Entries – for the amount of Engineering, Utility Relocation or Right of Way, if any - $100,000.00 Debt: (asset) State Aid – Deferred Revenue Credit: (asset) State Aid Construction – Revenue SAPR – Recognize Revenue for Eng, Utility Relocation and Right of Way

14 Partial Payment made to Contractor Amount of Work Certified ($ amt of work performed) $200,000 Less: Any Retainage ($ withheld as an insurance factor) $10,000 Equals: Cash paid to Contractor $190,000 Accounting Entries – recognize expenses as work is certified - $200,000 Debit: (exp) Construction Expenses Credit: (liability) Contracts Payable Work Begins on the Project Recognize Expenses

15 Partial Payment made to Contractor Amount of Work Certified ($ amt of work performed) $200,000 Less: Any Retainage ($ withheld as an insurance factor) $10,000 Equals: Cash paid to Contractor $190,000 Accounting Entries – recognize earned revenue as work is certified - $200,000 Debit: (liability) State Aid – Deferred Revenue Credit: (revenue) State Aid Construction - Revenue Work Begins on the Project (cont.) Recognize Earned Revenue

16 Partial Payment made to Contractor Amount of Work Certified ($ amt of work performed) $200,000 Less: Any Retainage ($ withheld as an insurance factor) $10,000 Equals: Cash paid to Contractor $190,000 Accounting Entries – for amount of contractor disbursement - $190,000 Debit: (liability) Contracts Payable Credit: (asset) Cash Work Begins on the Project (cont.) Disbursement to Contractor

17 Four different situations can occur. These are: 1)Project is completed exactly as estimated 2)Project overruns original estimate 3)Project Underruns original estimate without a State Aid overpayment 4)Project Underruns original estimate with a State Aid overpayment Examples of all these scenarios may be found in our Accounting Manual – Chapter 3 Regular and Municipal Construction Accounts. Project is Finalized

18 State Aid has encumbered too much and will only reimburse the portion of the encumbered amount that covers the actual project costs. Remember that the amount over the estimate will reduce your receivable & increase your allotment. Accounting Entry - Recognize the underrun – $9,087.23 ($442,932.15 final obligated amt - $452,019.38 original obligated amt) Debit: (asset) State Aid – Allotment Credit: (asset) State Aid – Receivable Accounting Entry – Record State Aid Receipt - $13,513.74 Debit: (asset) Cash Credit: (asset) State Aid - Receivable Project Underruns Original Estimate without an Overpayment

19 There are two methods of accounting for these. We are using the one with optional entries because this method is useful to track the balance of the Bond Grant. The State Auditor’s Office may recommend these accounts be adjusted to zero at year end and re- established in the new-year. Project is Awarded & SAPR sent in Accounting Entry – record bond grant amount - $570,312.75 Debit: (asset) Bond Grant Credit: (liability) Bond Grand – Deferred Revenue State Bond Grant

20 Accounting Entry – Recognize expense for work certified & record payable - $553,847.18 Debit: (const exp) State Bond – Expense Credit: (liability) Contracts Payable Accounting Entry – Record disbursement to contractor - $526,154.82 Debit: (liability) Contracts Payable Credit: (asset) Cash There will be numerous payments. This is only for the one attached to the Initial State Aid Pay Request. State Bond Grant – Work Begins on Project

21 Accounting Entry – Record state bond receivable for work certified - $553,847.18 Debit: (asset) State Bond – Receivable Credit: (asset) State Bond Grant Accounting Entry – Record state bond revenue for work certified - $553,847.18 Debit: (liability) State Bond – Deferred Revenue Credit: (revenue) State Bond – Revenue There will be numerous payments. This is only for the one attached to the Initial State Aid Pay Request. SAPR - State Bond Grant

22 Accounting Entry – Record receipt of state bond funds - $526,154.82 Debit: (asset) Cash Credit: (asset) State Bond – Receivable NOTE: Revenue for these funds would be booked at the time it becomes certain and determinable, when work is certified. SAPR - State Bond Grant (cont..)

23 CAUTION: State bond revenue can only be recognized up to the grant amount. In cases where the bond eligible items overrun the grant amount they become county expense and no revenue can be recognized. In special cases it may be possible to request and receive additional grant funds through an amendment to the bond agreement. This is rarely done Accounting Entry – record bond grant amendment amount - $21,459.75 Debit: (asset) Bond Grant – Receivable Credit: (liability) Bond Grand – Deferred Revenue State Bond Grant (cont..) Amendment to Bond Agreement

24 There are three main situations which can occur relating to the bond funds. These are: 1)Project is completed exactly as estimated 2)Project overruns the original estimate 3)Project underruns the original estimate Examples of all these scenarios may be found in our Accounting Manual – Chapter 5 Special Construction Accounts. State Bond Grant is Finalized

25 Accounting Entry – Recognize additional state bond revenue up to work certified - $37,925.32 Debit: (liability) State Bond – Deferred Revenue Credit: (revenue) State Bond – Revenue Accounting Entry – Recognize expense greater than bond grant - $37,925.32 Debit: (expense) – Construction Expense Credit: (liability) – Contracts Payable State Bond Grant is Finalized (cont..)

26 Accounting Entry – Record disbursement to contractor - $65,617.68 Debit: (liability) Contracts Payable Credit: (asset) Cash Accounting Entry – Record receipt of state bond funds - $65,617.68 Debit: (asset) Cash Credit: (asset) State Bond - Receivable State Bond Grant is Finalized (cont..)

27 John Fox 651-366-4854 www.john.e.fox@state.mn.uswww.john.e.fox@state.mn.us Cindy Degener 651-366-4850 www.cindy.degener@state.mn.uswww.cindy.degener@state.mn.us Sandra Martinez 651-366-4880 www.sandra.martinez@state.mn.uswww.sandra.martinez@state.mn.us Candy Harding 651-366-4891 www.candice.harding@state.mn.uswww.candice.harding@state.mn.us Questions on filling out SAPR Who to Call

28


Download ppt "Mock State Aid Project County Highway Accountant’s Conference 2015."

Similar presentations


Ads by Google