1 New Data Center at BNL– Status Update HEPIX – CERN May 6, 2008 Tony Chan - BNL

2 Background RACF (RHIC/ATLAS Computing Facility) provides support for RHIC experiments and ATLAS RACF (RHIC/ATLAS Computing Facility) provides support for RHIC experiments and ATLAS Rapid growth in the past few years caused space, power and cooling shortages Rapid growth in the past few years caused space, power and cooling shortages Steep capacity ramp-up for ATLAS cannot be accommodated with current facility resources Steep capacity ramp-up for ATLAS cannot be accommodated with current facility resources Phased increase in facility infrastructure over many years Phased increase in facility infrastructure over many years

3 RACF Current Capacities Nearly 15 PB of tape storage capacity Nearly 15 PB of tape storage capacity Nearly 5 PB of disk storage capacity Nearly 5 PB of disk storage capacity Almost 13 million SI2K in computing capacity Almost 13 million SI2K in computing capacity Approximately 160 racks of equipment on (5000 ft 2 ) 465 m 2 of floor space Approximately 160 racks of equipment on (5000 ft 2 ) 465 m 2 of floor space

4 The Growth of the Linux Farm

5 Total Distributed Storage Capacity

6 Expected Computing Capacity Evolution

7 Expected Storage Capacity Evolution

8 Evolution of Space Usage Capacity of data center Intel dual and quad-core deployed

9 Evolution of Power Usage Existing UPS Capacity

10 What are we doing about it? Short-Term (next 12 months) Short-Term (next 12 months) More efficient use of facility resourcesMore efficient use of facility resources Auxiliary cooling units in existing facilityAuxiliary cooling units in existing facility Renovation of (2000 ft 2 ) 185 m 2 of unused floor and adding 300 KW of power underwayRenovation of (2000 ft 2 ) 185 m 2 of unused floor and adding 300 KW of power underway Enough for ~ 40 additional racksEnough for ~ 40 additional racks Medium-Term (12 to 24 months) Medium-Term (12 to 24 months) New building with (6600 ft 2 ) 622 m 2 and 1.5 MW of powerNew building with (6600 ft 2 ) 622 m 2 and 1.5 MW of power Mission-specific facility (redundant cooling, deep raised floors, etc)Mission-specific facility (redundant cooling, deep raised floors, etc) Enough for ~ 120 rack and 4 robotic silosEnough for ~ 120 rack and 4 robotic silos Long-Term (beyond 24 months) Long-Term (beyond 24 months) New BNL data center with 25000 ft 2 (2300 m 2 ) after 2015New BNL data center with 25000 ft 2 (2300 m 2 ) after 2015

11 Rack-Top Cooling Units

12 Data Center Layout in 2007

13 Data Center Layout by 2009

14 COMPUTER DATA CENTER ADDITION BUILDING 515 BROOKHAVEN NATIONAL LABORATORY UPTON, NEW YORK

15 BROOKHAVEN NATIONAL LABORATORY COMPUTER DATA CENTER ADDITION BUILDING 515

16 New Data Center Layout

17 Building Timeline Finalize new building design – May 2008 Finalize new building design – May 2008 Award contract for new building – June 2008 Award contract for new building – June 2008 Start construction – July 2008 Start construction – July 2008 Renovated floor space occupancy – October 2008 Renovated floor space occupancy – October 2008 New building construction complete – May 2009 New building construction complete – May 2009 New building occupancy – July 2009 New building occupancy – July 2009 New buildings of this size requires at least 2½ years from first proposal to occupancy – this one done in 1½ years New buildings of this size requires at least 2½ years from first proposal to occupancy – this one done in 1½ years New building cost under US $5 million – so far still on schedule and within budget New building cost under US $5 million – so far still on schedule and within budget Reason for optimism – cost to renovate 2000 ft 2 floor space is under budget by 30%! Reason for optimism – cost to renovate 2000 ft 2 floor space is under budget by 30%!

18 Suggested Floor Plan

19 Summary The growth of the RACF in the past few years exposed severe infrastructure problems The growth of the RACF in the past few years exposed severe infrastructure problems Learned some important lessons (maximize use of existing space, better planning, etc) Learned some important lessons (maximize use of existing space, better planning, etc) Renovated space and additional power available in October 2008 – some breathing room Renovated space and additional power available in October 2008 – some breathing room New data center dedicated to RACF will be available in summer 2009 New data center dedicated to RACF will be available in summer 2009 New facility in long-range plan after 2015 New facility in long-range plan after 2015