Butch Wlaschin Director, Office of Asset Management Federal Highway Administration AASHTO Highway Subcommittee on Construction 2009 Summer Meeting Chicago,

Similar presentations


Presentation on theme: "Butch Wlaschin Director, Office of Asset Management Federal Highway Administration AASHTO Highway Subcommittee on Construction 2009 Summer Meeting Chicago,"— Presentation transcript:

1 Butch Wlaschin Director, Office of Asset Management Federal Highway Administration AASHTO Highway Subcommittee on Construction 2009 Summer Meeting Chicago, IL FHWA UPDATE

2 U.S. Department of Transportation Federal Highway Administration 2 Recent Losses to the FHWA Family Jim Sorenson Vince Barone

3 U.S. Department of Transportation Federal Highway Administration 3 Presentation Overview New Administration Update on Recovery Act and Reauthorization Construction Program Evaluations Domestic and International Scans Other FHWA Programs & Initiatives

4 U.S. Department of Transportation Federal Highway Administration 4 New Administration Victor Mendez, ADOT – Former AASHTO President Greg Nadeau, Maine DOT – Director of Policy New Public Affairs New Chief Counsel

5 U.S. Department of Transportation Federal Highway Administration 5 Reauthorization House very active – $500B – 6 year bill Senate more inclined to get an 18 month extension with no changes Both have passed and sent to WH $7B stop gap provision WH – Administration proposal looking for an 18 month extension with program changes

6 U.S. Department of Transportation Federal Highway Administration 6 Recovery Act Update 64% money obligated As of May 31, FHWA reported 4,798 full time equivalent jobs 400% Increase from March and April $35/hour average pay

7 U.S. Department of Transportation Federal Highway Administration 7 Recovery Act Update 2,406 projects under construction Roughly 2/3 of ARRA funds spent on maintenance and preservation projects. David Winter will fill you in next

8 U.S. Department of Transportation Federal Highway Administration 8 Recovery Act Competitive Procedures S. 1554 All contracts must be awarded through competitive procedures Exceptions must be reported to the Recovery and Accountability and Transparency Board and posted on their web site (example public agency force account approval under 23 CFR 635.204)

9 U.S. Department of Transportation Federal Highway Administration 9 Recovery Act Buy America Provisions Due to the Applicability of Title 23 Requirements in Title XII, there will be no changes in our BA implementation for ARRA projects

10 U.S. Department of Transportation Federal Highway Administration 10 Recovery Act Buy America Provisions FHWA’s BA statutory provisions in 23 USC 313 and our regulatory policies in 23 CFR 635.410 apply. Notifications of waivers will be posted on the FHWA Buy America Waiver web site and published in the Federal Register.

11 U.S. Department of Transportation Federal Highway Administration 11 Recovery Act Davis Bacon Requirements Davis Bacon will apply to all ARRA projects (the existing exclusion for local roads and rural minor collectors will not apply).

12 U.S. Department of Transportation Federal Highway Administration 12 Recovery Act Davis Bacon Requirements This is the result of the “Notwithstanding any other provision of law and in a manner consistent with other provisions of this Act…” language in Section 1606.

13 U.S. Department of Transportation Federal Highway Administration 13 Key Risk Areas Local Public Agency (LPA) Oversight PS&E Quality Contract Administration Indian Reservation Roads Program Quality Assurance DBE Program Eligibility/Improper Payments Achievement of Program Goals Recovery Act Risk Management Plan

14 U.S. Department of Transportation Federal Highway Administration 14 Not Business as Usual Division Office Oversight National Oversight Communication and Education Sharing Risk with Partners Measures and Monitoring Reassessment and Feedback Recovery Act Risk Management Plan

15 U.S. Department of Transportation Federal Highway Administration 15 Construction Program Evaluations Steering group established in July 2008 to lead planning efforts Draft Evaluation Guide developed for 6 focus areas –Staffing, Pre-Construction, Contract Admin., Quality, Safety and Process Improvement An Update -

16 U.S. Department of Transportation Federal Highway Administration 16 Construction Program Evaluations Future Actions –Develop SOP’s, establish evaluation teams, training and identify pilot State(s) to evaluate CPE’s vs. ARRA National Reviews –How do they differ from one another? An Update -

17 U.S. Department of Transportation Federal Highway Administration 17 Sept 2009: Final Evaluation Guide Fall 2009: SOP’s and finalized format Fall 2009: Establish Evaluation Teams Winter 2010: Conduct Team Training Winter 2010: Identify CPE Pilot States Spring 2010: Conduct 1 st Pilot Evaluations Summer 2010: Assessment of evaluation effort (first pilot efforts) Construction Program Evaluations Updated Timeline -

18 U.S. Department of Transportation Federal Highway Administration 18 2009 Domestic Scan of Accelerated Construction Practices AASHTO/ FHWA team conducted the scan in March 2009 with stops in FL, AL, TX, UT and CA Purpose – To identify construction operational and management practices that support accelerated construction and project delivery Scope – Evaluated practices in construction acceleration for emergency situations and a DOT program and planned project Full scan report to be published in December 2009

19 U.S. Department of Transportation Federal Highway Administration 19 2008 International Right-of-Way and Utilities Scan Purpose – Identify practices to better integrate right-of- way and utility activities into the project development and delivery processes Key findings – “Alliance Contracting” approach; non- adversarial right-of-way acquisition; improved working relationship with utility industry at all levels. Final report available at: http://international.fhwa.dot.gov/pubs/pl09011/ http://international.fhwa.dot.gov/pubs/pl09011/

20 U.S. Department of Transportation Federal Highway Administration 20 Work Zone Safety and Mobility Rule Status All 52 States have fully met initial compliance requirements –Approved WZ policy, definition for significant projects, procedures for TMPs, training plan Agencies should be implementing their WZ policy and procedures on all Federal-aid highway projects going to bid after October 12, 2007 unless a project exception was obtained At the project level, observe and provide feedback on TMPs for process improvement

21 U.S. Department of Transportation Federal Highway Administration 21 Temporary Traffic Control Devices Rule Status The Final Rule on Temporary Traffic Control Devices was developed in response to section 1110 of SAFETEA- LU - Decrease WZ fatalities and injuries - Build on WZ Safety and Mobility Rule - December 4, 2008 compliance date

22 U.S. Department of Transportation Federal Highway Administration 22 Temporary Traffic Control Devices Rule Status (cont.) 37 States currently in compliance 15 States still in process of achieving full compliance – majority of these are close

23 U.S. Department of Transportation Federal Highway Administration 23 Work Zone Rule Implementation Support FHWA continues to provide support for implementation –Process Review Toolbox – Now available at http://ops.fhwa.dot.gov/wz/prtoolbox/pr_toolbox.htm http://ops.fhwa.dot.gov/wz/prtoolbox/pr_toolbox.htm –Implementation Examples – Regularly adding new examples to our website www.fhwa.dot.gov/workzones www.fhwa.dot.gov/workzones –WZ Analysis Guides – New leaflet, a guide for decision-makers, and a guide for analysts now available at http://ops.fhwa.dot.gov/wz/traffic_analysis/index.htm http://ops.fhwa.dot.gov/wz/traffic_analysis/index.htm

24 U.S. Department of Transportation Federal Highway Administration 24 Work Zone Rule Implementation Support (cont.) –WZ ITS Assessment Report and White Paper on Managing WZ Impacts with Technology – Now available at http://ops.fhwa.dot.gov/wz/its/index.htmhttp://ops.fhwa.dot.gov/wz/its/index.htm –Training - http://ops.fhwa.dot.gov/wz/outreach/outreach.htm http://ops.fhwa.dot.gov/wz/outreach/outreach.htm NHI Advanced WZ Management and Design - available FHWA Law Enforcement in WZs – available WZ Safety Grants courses - available

25 U.S. Department of Transportation Federal Highway Administration 25 Other Resources WZ Peer-to-Peer Program (http://ops.fhwa.dot.gov/wz/p2p/index.htm)http://ops.fhwa.dot.gov/wz/p2p/index.htm Office of Operations WZ website (http://ops.fhwa.dot.gov/wz/index.asp)http://ops.fhwa.dot.gov/wz/index.asp

26 U.S. Department of Transportation Federal Highway Administration 26 Value Engineering Program Regulatory update anticipated 2009-2010 Continued outreach and guidance Promotion of successful practices Defining success with VE Program Value Engineering Change Proposals FHWA’s VE Accomplishment Reports are available at: http://www.fhwa.dot.gov/ve/vereport.cfm

27 U.S. Department of Transportation Federal Highway Administration 27 Training Opportunities National Highway Institute –www.nhi.fhwa.dot.govwww.nhi.fhwa.dot.gov Transportation Curriculum Coordination Council (TCCC) –http://www.nhi.fhwa.dot.gov/tccc/http://www.nhi.fhwa.dot.gov/tccc/ National Transportation Training Resources database –www.nttr.dot.govwww.nttr.dot.gov

28 U.S. Department of Transportation Federal Highway Administration 28 New Training Courses in 2009 Inspection of Bridge Rehabilitation Projects Risk-based Cost Estimating for Major Projects (scheduled to be available in FY 2008) Maintenance Leadership Academy Environmental Factors in Construction & Maintenance Operations

29 U.S. Department of Transportation Federal Highway Administration 29 New Training Courses in 2009 Advanced Emulsion Technology for Pavement Preservation and Rehabilitation Construction Engineers Academy Free web-based training modules

30 U.S. Department of Transportation Federal Highway Administration 30 Updated Content –Standard specifications –Expanded alternative and emerging specifications –Construction Manuals –Links to standard plans National Highway Specification Website Web Site Improvements -

31 U.S. Department of Transportation Federal Highway Administration 31 National Highway Specification Website Web Site Improvements - Improved Functionality –Administrative procedures –Enhanced search capabilities Web-based training –Administrative procedures –508 compliance www.specs.fhwa.dot.gov

32 U.S. Department of Transportation Federal Highway Administration 32 Additional Topics The use of federal-aid funds can now be used for conferences, NHI training, etc. were PDH’s/CEU’s are given

33 U.S. Department of Transportation Federal Highway Administration 33 Thank You Questions?