CBM Building and Infrastructure

Similar presentations


Presentation on theme: "CBM Building and Infrastructure"— Presentation transcript:

1 CBM Building and Infrastructure
Wolfgang Niebur, GSI CBM Collaboration Meeting, Overview of new (since 2008) old status (before 2007) beamfocus costs

2 Cave+Supply building before 2007 – View in beam direction
access shaft 6 × 6 m access opening 10 × 10 m

3 Cave before 2007 – Top view, surface level
Annex building access shaft 6 X 6 m access opening 10 ×10 m

4 Cave 2008 – Top view, surface level
Annex building access opening 6 ×10 m Roof, compacted earth

5 Cave 2008 – Top view into cave
access opening 6 X 10 m Single wall

6 Cave before 2007 – Top view into cave
access shaft 6 ×6 m Double wall Sandwich filling

7 Cave 2008 – Side view Compacted earth access opening 6 X 10 m
Annex building Compacted earth Shielded area

8 Fair Baseline Technical Report 2006 (FBTR) Version 2
Costs Fair Baseline Technical Report 2006 (FBTR) Version 2 Building Cost FBTR 2006 is Million Euro Cave 11,80 M€ Annex building 0,98 M€ The building cost in our Draft version as of now around 10.5 Million Euro The cost optimizations are the following: 1) The cave floor is in one level 2) The sandwich walling is obsolete 3) 1 slab/floor opening for the crane instead of 2. 4) The new opening dimension is 6m x 10 m.

9 Thank you for your attention.

10 Cave before 2007 – Side view Roof, compacted earth
breakthrough 10 X 10 m

11 X X X X X - + - + + - Beamfocus CBM - Hades CBM-Magnet Cave wall
+ X - Hades-Target CBM-Magnet Cave wall Hades-Magnet Hades-Target CBM-Target - 4000 X X Beam + 6800 - 4700 12000 + 4700 - 4700 Hades-beamtime: beam pipe d 100 X 9400 + X - Hades-Target + + 1600 CBM-beamtime: beam pipe d 100 X 1600 X - Hades-Target W. Niebur


Download ppt "CBM Building and Infrastructure"