1 Role of Account Management at ERCOT Nodal Training Project Debrief for TPTF September 12, 2006 Market Education

2 September 12, 2006 TPTF Nodal Training Debrief Agenda I.Readiness Discussion II.Course Availability and Schedule III.Nodal Training Communications IV.Standard Course Development Process V.Project Planning and Budgeting Assumptions VI.Suggestions for Restructuring the Course Curriculum VII.LMS Update VIII.Nodal 101 Course Update VII.LMP 201 Update VIII.Work in Progress

3 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Readiness Discussion Market Education

4 September 12, 2006 TPTF Nodal Training Debrief Discussion Materials have all been distributed –Summarized TAC comments –Market Readiness Requirements Validate comments and discuss

5 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Course Availability and Schedule Market Education

6 September 12, 2006 TPTF Nodal Training Debrief TPTF Curriculum – Proposed Availability Schedule Available dates are based on current information, staffing and plan assumptions.

7 September 12, 2006 TPTF Nodal Training Debrief ERCOT Requested Supported Courses and Capabilities

8 September 12, 2006 TPTF Nodal Training Debrief Scheduling Assumptions The available dates are based on the current EDS delivery schedule and phasing (prior to Sept, 2006) and the Curriculum descriptions regarding Training Readiness. ERCOT Team refers to ERCOT staff and contractors who are developing an application. Vendor assumes that the vendor developing the software is contracted to create and deliver the courses (including tests) in approved format. Individual course delivery schedules are not currently scheduled other than for 101 The Basics (Typically delivery schedules are finalized 30 days before date available, rooms are preliminarily assigned at the beginning of course development). WebEx productions are currently not scheduled. All courses (other than LMP 201 which replaced LMP 101) will be hosted on LMS.

9 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Nodal Training Communication Market Education

10 September 12, 2006 TPTF Nodal Training Debrief Proposed Nodal Training Site http://nodal.ercot.com/training/index.html

11 September 12, 2006 TPTF Nodal Training Debrief Proposed Course Pages

12 September 12, 2006 TPTF Nodal Training Debrief Communication Plan For course updates and other nodal training information there are several ways is which information will be communicated. Nodal training website Nodal project news letter Word of mouth E-mail exploder lists – actual lists to be determined During course delivery TPTF presentations

13 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Course Development Process Market Education

14 September 12, 2006 TPTF Nodal Training Debrief 8 Hour Course Development Cycle – One Day Course 4 Days 12 Days 24 Days 5 Days 12 Days 54 Days TPTF subgroup review of abstract and outline Publish Course TPTF subgroup review of preliminary module BetaTPTF workshop Interactive Visual Training Map Schedule Course Design Course Develop Preliminary Module Develop Course Structure F.A.Q. Document Develop Quick Guides Compose WebEx Materials Migrate Materials to Web-Based Training Deliver Courses

15 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Current Nodal Training Budget and Plan Assumptions Market Education

16 September 12, 2006 TPTF Nodal Training Debrief Nodal Training Planning and Budgeting Assumptions The training plan does not include the current ERCOT payments for WebEx sessions. ERCOT departments are allowed to use WebEx sessions without specifying the actual charge in budgets. WebEx sessions will not exceed 125 students per class session. The training plan assumes the use of the current LMS with the purchase of Lectora to provide a testing platform. Any required self-study presenters are provided from resources already allocated to the project. For budgeting purposes we have used the lowest estimated cost ($6 per booklet) for production of the course booklets. This is not the current preferred ERCOT vendor for printing - Document Engine – which has estimated three times this much. Printing is black & white only. Based on the Curriculum seven courses need to be transcribed for narration for web-based. The number of students trained per active course per month by face to face is estimated at 50. There are no charges included for ERCOT provided facility, software & supplies or for internally printed material.

17 September 12, 2006 TPTF Nodal Training Debrief Nodal Training Planning and Budgeting Assumptions The level of effort is based on market-focused courses identified by the Market Participants in the “Curriculum" document, and those identified by the IRT group as required for ERCOT Readiness. Any additional training at ERCOT would be the responsibility of the particular department, though it is suggested that the standard formats and process being used by the Nodal Training Project may be of value. The market-focused course schedule and scope is to support the requirements dictated by the TPTF as documented in the Curriculum documents. Scaling of development effort is based on the course creation section of the process.

18 September 12, 2006 TPTF Nodal Training Debrief Nodal Training Planning and Budgeting Assumptions PJM training is not being purchased. Contractor travel expenses are included in vendor rates. Other than LMP 201, all courses are presented by ERCOT staff or Training contractors. The LMS contract is good for two years there is no guarantee of the same price from the vendor – OnLine Training – for the 3rd year. The cost of software licenses includes est. 10% sales tax. All scenario based training is one day. Nodal Program Office will provide a mechanism to monitor budget & time. Training external to Texas can be provided at time and material reimbursement. The cost of course delivery through 2009 is included in the Nodal Training budget with the assumption of using internal ERCOT resources. No assumption is made as to the provision of these resources. Approximately 14,000 hours have been budgeted using these internal resources at $65 hour. Should these resources not be available cost of contractors for training delivery could be as high as $165 an hour (including expenses). The current assumption is that each course, once available, will be presented once a month through market opening.

19 September 12, 2006 TPTF Nodal Training Debrief Nodal Training Planning and Budgeting Assumptions The Annual ERCOT Operations Training Seminar will include at least 2 Hours of nodal material in the 2007 Seminar. The Seminar Working Group is expected to include more in the Seminar to be held in the fall of 2008; how much is yet to be determined. Since the 2009 Seminar is to be held in the fall of 2009, post Nodal implementation, operational implementation issues will be considered by the Seminar Working Group. Nodal Training will provide support and material to the Seminar as required. The current Early Delivery System (EDS) development timelines must consider all available options to prepare target populations for Nodal implementation. The Extended Training – System Dynamics course is budgeted for development but not delivery as delivery (according to the Curriculum) occurs after 1/1/09. The Nodal Training Budget does not include any activity or expenses after 1/1/09.

20 September 12, 2006 TPTF Nodal Training Debrief Training Travel Discussion Training external to Texas can be provided at time and material reimbursement. Training has currently budgeted for in-Texas training at four separate locations (North, South, East and West) at an ERCOT approved facility. –Market Participant support & travel is not included. –Budget assumes course travel for three people per month in Texas, with two nights out (three days) at one of the four locations. –Out-of-Austin facilities are assumed free and include projection and sound capability supporting an audience from 25-50 people. Laptop is purchased for training use in out-of-Austin facilities, includes tax, support, and warranty.

21 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Suggestions for Reorganization of Nodal Training Curriculum for Budget Reduction Market Education

22 September 12, 2006 TPTF Nodal Training Debrief Nodal Training Budgeting Background Can the scope be reduced Can we simplify the process Can the scale be reduced Can we reorganize the schedule Must maintain the quality and content Perspective Nodal 101 Training in production Development of five day Basic Training Course outline/abstract for QSEs Familiarity with other components of the Nodal Project

23 September 12, 2006 TPTF Nodal Training Debrief Courses with no suggestions for curriculum changes NOIE QSE Operations Basic Training Program Extended Training System Operations ERCOT LMP 201 Market Settlements 301 CRRs, PCRRs etc Support for Annual System Operations Seminar

24 September 12, 2006 TPTF Nodal Training Debrief Reduction of Face to Face Course Delivery Rationale: The provision of Web-Based Training with electronic testing capability could provide the necessary coverage. Nodal Training will host a once-a-month question and answer conference-call for questions. In addition several of the course durations could be reduced. Courses ImpactedSavings ERCOT Nodal 101 After 2006$ 75,000 Transition to Nodal Markets$250,000 Reduce to 4 hours (from 16 hours) as content is largely project information that might be provided in updates to TPTF and circulated on a regular basis. Course content still includes a description of the plans, major components and anticipated interaction points of the Market. Transmission 101$300,000 Reduce to 10 hours (from 20 hours) as content is very specific to TSPs and DSPs and they are already required to attend the Basic Training QSE course per the Readiness discussions.

25 September 12, 2006 TPTF Nodal Training Debrief Consolidation of Generation Courses Rationale: There are currently four courses that are generation focused for a total duration of 48 hours of classroom time. Based on the fact that this material will build on the Basic Training QSE course generation specific material could be provided over 16 hours of training (vastly reducing development and delivery time) with one possible format as follows: Day 1, Morning Generation 101 Day 1, AfternoonGeneration 101, test 101 Day 1, AfternoonGeneration 201 Day 2, MorningGeneration 201, test 201 Day 2, AfternoonGeneration 301, test 301 Day 2, AfternoonWind Generation, test wind generation Courses ImpactedSavings Generation 101,201,301$910,000 Wind Generation 101$290,000

26 September 12, 2006 TPTF Nodal Training Debrief Reduction of Course Duration Rationale: Based on the current anticipated depth of material being created for the 5 Day Basic Training Program, the following courses could have their duration reduced. Courses ImpactedSavings Load Service Entity 201$142,000 (Reduce from 20 to 16 hours) Network Model Management $ 76,000 (Reduce from 16 to 8 hours)

27 September 12, 2006 TPTF Nodal Training Debrief Removal of courses from Nodal Training Plan and Budget Rationale: This course can be scheduled for production and delivery after the 1/1/2009 date used for the Texas Nodal Training budget and plan. Course ImpactedSavings Scenario-Based Training$737,000 Rationale: This course will be provided by the ERCOT Software Development Team in the form of presentations. Course ImpactedSavings MIS 101$292,000

28 September 12, 2006 TPTF Nodal Training Debrief Additional Potential Savings Item ImpactedSavings Remove WebEx$ 78,000 Remove Off-site Texas Training $ 90,000 Remove support for vendor supplied training$100,000 Drop Interactive Visual Training (Quality Impact)$100,000 Drop Process Maps (Quality Impact) $429,000 Drop Quick Guides (Quality Impact) $273,000 Drop FAQ (Quality Impact) $ 55,000

29 September 12, 2006 TPTF Nodal Training Debrief Budget Saving Summary ItemsSavings Curriculum Restructuring$3,072,000 No off-site Texas training$ 90,000 Drop WebEx$ 78,000 Drop Vendor Training Support$ 100,000 Reduce Training Quality $ 857,000

30 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT LMS Update Market Education

31 September 12, 2006 TPTF Nodal Training Debrief Tracking and reporting on Nodal Market Readiness Automation of as many processes as possible Support for distance learning MPs need to be able to manage their own students Mapping Market Protocols to learning objectives Support for NERC Certification and CEH Flexible and secure system Business Drivers

32 September 12, 2006 TPTF Nodal Training Debrief Technology Functional Requirement Categories User Accounts Publishing & Scheduling Student Enrollment Attendance & Tracking Reporting Certification Protocol Mapping Prospective software WBT Manager (LMS), hosted by external vendor Lectora courseware and exam creation tools, hosted by external vendor Requisite Pro for protocol mapping

33 September 12, 2006 TPTF Nodal Training Debrief LMS Readiness Schedule 9/15 – Complete Requirements / UI Design 9/22 – Licensing & Software Procurement (dependency) 10/20 – Requirements, UI, & Template Design Approval (dependency) 10/20 – LMS Configuration Completed 11/10 – UI & Templates Completed 11/22 – System Testing & Data Migration Completed 12/22 – Flight Testing Completed 12/26 – Go Live

34 September 12, 2006 TPTF Nodal Training Debrief Proposed Features Reporting: Reporting access provided at the overall system and business domain (MP) levels. Report generation on student performance: –By student –By Market Participant and Market Participant Division –By Market Segment (QSE, LSE, etc.) For the market at large with a wide range of additional reports Publishing & Scheduling: Organization of content by course and module Class schedule, instructor, and facility management tools Support for launching self-directed, electronic deliverables (courseware, exams, and other course aids) Publicly accessible via the Internet

35 September 12, 2006 TPTF Nodal Training Debrief Proposed Features User Account: MP-centric student hierarchy Local MP administrator support at both the company and division level Mandatory student account creation Self-service, managed, and bulk creation of accounts Self-service and managed account maintenance Self-service support for transition between Market Participants Certification: Tracking of certification programs to facilitate NERC requirements Support for organizing curricula to meet certification program needs Application of training time towards student Continuing Educational Hours (CEH)

36 September 12, 2006 TPTF Nodal Training Debrief Proposed Features Student Enrollment: Access to all course curricula via a global course catalog Self-service and managed student class enrollment Alerts to facilitate communication between Training and students Attendance and Tracking Features: Manual attendance management for class sessions Automatic attendance management for self-service, distance learning Tracking of all AICC- or SCORM-compliant electronic courseware Exam data gathering, by question and learning objective Optional support for pre-requisite constraints on certain curricula Optional support for “testing out” of certain curricula

37 September 12, 2006 TPTF Nodal Training Debrief Proposed Features Protocol Mapping : Mapping of Market Protocols and derived Nodal system application features to applicable learning objectives

38 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Nodal 101 Update Market Education

39 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Evaluation Results Four MP classes held (150 attendees, 90 surveys completed – 60%) July 26 – 37 attendees, 20 surveys completed July 27 – 33 attendees, 21 surveys completed Aug 8 – 35 attendees, 26 surveys completed Aug 23 – 45 attendees, 23 surveys completed Survey asked attendees: Name (optional) Participant Type –QSE, LSE/REP, TDSP, Generation, PUCT, Other Role –Accounting/Settlements, Power Operations, Engineering, Management, Consultant, Other Nodal Market Knowledge –Beginner, Intermediate, Advanced

40 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Surveys by Type

41 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Surveys by Role

42 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Prior Nodal Knowledge

43 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Topic Importance Topics Market Overview LMP Adjustment Period and Real- Time Operations Day-Ahead Operations Congestion Revenue Rights Settlements Participants asked to rate each topic using the following scale: No Opinion (0 – Not Counted) Very Unimportant (1) Unimportant (2) Important (3) Very Important (4) All topics received ratings between 3.02 and 3.44

44 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Content/Presentation Ratings Adapted to reflect generic NERC survey Met learning objectives Prerequisites were appropriate Materials were accurate and relevant Instructional method was appropriate Time allotted was appropriate Instructor(s) were effective Facilities and/or tech equipment were appropriate Materials issued before/during training were appropriate A/V used were effective Recommend course to others Participants asked to rate each item using the following scale: No Opinion (0 – Not Counted) Strongly Disagree (1) Disagree (2) Agree (3) Strongly Agree (4) All categories received ratings between 3.16 and 3.48 except Time Allotted - 2.86 (Large amount of new material)

45 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Test Procedures Attendees were told that they need to take the test, this is now documented on the web site and in the course materials. –150 attendees –87 took test (58% of those who attended) –69 passed (79% of those who took the test) ERCOT Attendees –26 attendees –10 (38%) took test and all passed Test was open book/notes Multiple choice questions –Some questions removed as a result of 7/26 and 7/27 classes Passing score = 70% “Test out” option to be in place Q4 2006 when LMS is operational

46 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Intro Slide on Testing Market Participant – An Entity that engages in any activity that is in whole or in part the subject of the Nodal Protocols, regardless of whether that Entity has signed an Agreement with ERCOT. Market Participants are required as part of the Nodal Transition Plan to demonstrate Market Readiness. –Training is considered one component of Market Readiness. –As such each Market Participant, as defined above, will be expected to take the test for a given course. –ERCOT will maintain such information and report to the Market as required on the status of Training Readiness.

47 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – Test Performance, all Attendees

48 September 12, 2006 TPTF Nodal Training Debrief ERCOT Nodal 101: The Basics – 2006 Face to Face Schedule September 21, 2006 in Austin October 11, 2006in Taylor October 25, 2006 in Austin November 7, 2006 in Austin November 29, 2006 in Taylor

49 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT LMP 201 Update Market Education

50 September 12, 2006 TPTF Nodal Training Debrief Summary of comments Very strong content that was broader than LMP, include a lot of basic supply and demand theory. Had some material that was commentary on other markets that could be removed. Material delivered as if in a university – Professor Baldick presents the information without facilitating the learning of the information. Professor Baldick is highly knowledgeable about the subject matter. Professor Baldick has certain opinions that are not necessarily those of ERCOT and is not afraid to voice them. Audience did not perceive this as a 200 level course. Material was in Professor Baldick’s own format. Recommendation from an audience member was that the course should be mandatory.

51 September 12, 2006 TPTF Nodal Training Debrief Decisions required for LMP 201 Should this course be included in the “Nodal Training” Curriculum in standard format with or without test as a replacement for LMP 101? –Professor Baldick owns the material completely. Should this course be mandatory and a prerequisite to Nodal Basics 101? Should this course be called “The Economics of LMP”?

52 Market Education Nodal Education: (Course Title) (Presenter Name) (Presenter Title) ERCOT July 17, 2006 Role of Account Management at ERCOT Work in Progress Market Education

53 September 12, 2006 TPTF Nodal Training Debrief Accomplishments and On-going Work Recent Accomplishments Finalization of ERCOT Nodal 101 Development including quick guides Transition of delivery of Nodal 101 to Wholesale Client Services Completion of initial budget and plans Beta Run of LMP 201 Training development standards Completion of Protocol Mapping On-going Work Finalization of LMP 201 Development of 5-Day Basics Training Program –Release of abstract and outline to TPTF Sub-Group 9/15/2006 Development of Interactive Visual Process Map has commenced Completion of LMS requirements validation Development of Transition to Nodal Testing –Release of abstract and outline to TPTF Sub-Group 10/14/2006