CAMINADA HEADLAND BEACH / DUNE RESTORATION Governor’s Advisory Commission on Coastal Protection, Restoration and Conservation Meeting October 5, 2011.

Similar presentations


Presentation on theme: "CAMINADA HEADLAND BEACH / DUNE RESTORATION Governor’s Advisory Commission on Coastal Protection, Restoration and Conservation Meeting October 5, 2011."— Presentation transcript:

1 CAMINADA HEADLAND BEACH / DUNE RESTORATION Governor’s Advisory Commission on Coastal Protection, Restoration and Conservation Meeting October 5, 2011

2 Project Overview Fill Template Options Conveyance Corridor Options Project Schedule Outline

3 PROJECT GOALS Address severe erosion of Headland (historical rate average of 45 ft per year) Protect and sustain unique coastal habitats, Chenier Ridges, essential for migratory birds Reduce wave energy & saltwater intrusion into back barrier environments Provide sediment source to sustain barrier breaches east and west of the Headland

4 PROJECT LOCATION MAP

5 CAMINADA HEADLAND BBBS RECOMMENDED PLAN

6 CAMINADA HEADLAND FOOTPRINT OPTIONS 1-3

7 CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH ONLY

8 CAMINADA HEADLAND TYPICAL DESIGN TEMPLATES BEACH AND DUNE

9 CONCEPTUAL CONVEYANCE CORRIDORS

10 CONCEPTUAL BELLE PASS PUMP-OUT AREA

11 CONCEPTUAL PASS FOURCHON PUMP-OUT AREA

12 CONCEPTUAL OFFSHORE RE-HANDLING / PUMP-OUT AREA

13 DESIGN SCHEDULE Data Collection May 2011 – October 2011 Preliminary Design May 2011 – December 2011 Permitting September 2011 – April 2012 Final Design January 2012– April 2012

14 Questions?


Download ppt "CAMINADA HEADLAND BEACH / DUNE RESTORATION Governor’s Advisory Commission on Coastal Protection, Restoration and Conservation Meeting October 5, 2011."

Similar presentations