Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Delivery Method Selection Guidance ACEC/WSDOT Annual Meeting June 11, 2015 Jeff Carpenter Director, WSDOT Construction Division.

Similar presentations


Presentation on theme: "Project Delivery Method Selection Guidance ACEC/WSDOT Annual Meeting June 11, 2015 Jeff Carpenter Director, WSDOT Construction Division."— Presentation transcript:

1 Project Delivery Method Selection Guidance ACEC/WSDOT Annual Meeting June 11, 2015 Jeff Carpenter Director, WSDOT Construction Division

2 Acronyms/Definitions PDMSG – Project Delivery Method Selection Guidance PDM – Project Delivery Method Alternative Project Delivery Method – a delivery method other than Design-Bid-Build Probable Project Delivery Method - a temporary determination at project scoping that is used for project planning until it can be validated/updated by the Engineering Project Office assigned to the project. Final Project Delivery Method - is the PDM determination submitted for approval to use as the contracting method for the project early in the project design process.

3 PDMSG Team Purpose Develop formal guidance to aid WSDOT staff in the selection of project delivery methods based on a project’s attributes, opportunities and risks that will result in the most cost effective and best value project delivery in alignment with Reform VII.

4 PDMSG Task Goals 1.Establish a systematic approach that can be consistently applied throughout WSDOT, 2.Establish how and when a project should be assessed, 3.Develop the PDMS Process to be scalable for all projects, 4.Design the PDMSG Process to provide the documentation for delivery method approval, 5.Clearly identify all levels of approval or endorsement in the process.

5 PDMSG Background Current Selection Process –Design-Bid-Build is automatic unless an Alternative Delivery Method is pursued –Design-Build approval is required from WSDOT Chief Engineer –General Contractor/Construction Manager approval is required through CPARB

6 PDMSG Background New Selection Process –All projects will be evaluated for the optimal Project Delivery Method (PDM), –The PDMSG evaluates three methods, Design-Bid-Build, Design-Build, General Contractor/Construction Manager, –The selected PDM will be endorsed and/or approved through the Regions and HQ.

7 PDMSG Outline Project Delivery Selection Matrix from University of Colorado, Boulder and CDOT was used as a foundation - data and some forms retained WSDOT PDMSG was tailored to WSDOT Policy and Values All projects are evaluated in two steps The Probable PDM is determined during Scoping of the project The Final PDM is determined by the Design PEO by validating, updating or revising the Probable PDM

8 PDMSG Outline A Selection Checklist is used to quickly screen out projects that are obvious Design-Bid-Build or have a easily determined PDM, A Selection Matrix (if needed as a second step) is used to determine the Probable PDM and validate/revise it to determine the Final PDM, The work to determine the Probable PDM and the Final PDM are scalable to the size and complexity of the projects, The timing and requirements for different levels of work are integrated with the existing project development process.

9 Determining Probable PDM Project SizeRequired Process Project less than $10 MillionComplete Part 1 of Selection Checklist Projects less than $25 Million or if Part 1 of Checklist does not determine a Probable PDM Complete Part 1 and 2 of Selection Checklist Projects greater than or equal to $25 Million or if Part 2 of the Checklist does not determine a Probable PDM Complete Selection Matrix

10 Determining Final PDM Project SizeRequired Process Project less than $10 Million Validate/Revise Part 1 of Selection Checklist Projects less than $25 Million or if Validation/Revision of Part 1 of Checklist does not determine a Final PDM Validate/Revise or Complete Part 1 and 2 of Selection Checklist Projects greater than or equal to $25 Million or if Validation/Revision of Part 2 of the Checklist does not determine a Final PDM Validate/Revise or Complete Selection Matrix Projects greater than or equal to $100 Million or if Validation/Revision of the Selection Matrix does not determine a Final PDM Complete Selection Matrix Workshop

11 PDMSG Timing

12 Probable PDM Process

13 Probable PDM Endorsement

14 Final PDM Determination - Validation/Revision Process

15 Final PDM Determination – Selection Workshop Process

16 Final PDM Approval

17 PDMSG Status “White Paper” on other DOT/Agency project delivery selection guidance Completed PDMSG Team Formed – HQ Construction, HQ Design, Program Management, OR and NWR Draft PDMSG Documents Developed – Selection Checklist – Selection Matrix – Processes including flowcharts – Endorsement/Approval Processes – Preliminary User Guidance and Tools

18 PDMSG Next Steps Expand guidance document Review PDMSG with WSDOT/AGC/ACEC DB Committee Test “Beta” guidance, tools and processes with an independent WSDOT group Refine document from test group input Review PDMSG through Executive Create user friendly platform for delivery to users Develop Training and Implementation Plan Implement

19 Questions? Jeff Carpenter Director, Construction Division CARPENJ@wsdot.wa.gov 360.705.7821 (x7821)


Download ppt "Project Delivery Method Selection Guidance ACEC/WSDOT Annual Meeting June 11, 2015 Jeff Carpenter Director, WSDOT Construction Division."

Similar presentations


Ads by Google