1 CT DOT 2014 Qualified Inspector Training
General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities

2 Key Terms Grab sample The “Guidelines”
NTU (Nephelometric Turbidity Unit) Structural Measure Engineered Measure Non Engineered Measure Qualified Inspector Locally Exempt Project Locally Approvable Project NPDES / MS4 SWPCP / Plan Normal Working Hours (minimum M – F 8 – 6) Date of filing = the date received by the DEEP *Permit file based on payment Day = the calendar day. If a weekend or legal holiday, deadline is the next business day thereafter

3 Stormwater Permit History
National Pollutant Discharge Elimination System (NPDES) Permit 1972 – US Environmental Protection Agency (EPA) Section 402 of the Clean Water Act Created EPA required to issue NPDES Permits 1990 – US EPA Phase 1 of Stormwater Program CT DEEP Construction General Permit 1992 – General Permit Issued Revisions in 1997, 2002 and 2004 Reissued without modifications in 2007 and 2012 New October 2013

4 Stormwater Permit History
General Permit for the Discharge of Stormwater from Small Municipal Separate Storm Sewer Systems (MS4) Required by EPA through the NPDES Phase II Program via the Clean Water Act Administered and regulated by CT DEEP within the state Requires development and implementation of a Stormwater Management Plan and Program Plan and Program must utilize BMP’s to address six (6) minimum control measures outlined in the general permit

5 Stormwater Permit History
Six Minimum Control Measures Public Education and Outreach Tributary Signage Public Involvement / Participation Public Information Meetings Illicit Discharge Detection and Elimination Storm Sewer System Map Construction Site Runoff Control 2002 CT Guidelines for Soil Erosion and Sediment Control Post Construction Stormwater Management Requirements for Structural and Non-Structural BMPs Pollution Prevention / Good Housekeeping Operation and Maintenance Program

6 C-c-c-c-c-changes! Submission Requirements / Opportunity for Public Comment Certification Requirements New Required Coordination 8 new appendices Stormwater Pollution Control Plan for every registration

7 Submission Requirements
Disturbance of one or more acres regardless of phasing Locally Exempt Projects 60 days for disturbed area between 1 and 20 acres 90 days for More than 20 acres disturbed area Site over 1 acre discharging within 500 feet of a tidal wetland Site over 1 acre discharging to an Impaired Water Body Small Construction (Local Roads / Federal Local Bridge) Local municipal approval for projects between 1 and 5 acres – do not have to register if approved by local commission

8 Submission Requirements
Effective Date of Authorization 60 days / 90 days from date of public notice Notice to Proceed (NTP) contingent upon no public comment(s) If public comment(s), NTP will be delayed Availability of Registration and Plan On the 15th day of each month Electronic Filing Under development

9 Submission Requirements
The registration must be electronically submitted with: Registration form ( Additional forms and information regarding consistency Electronic copy of the SWPCP or a web address where the plan can be downloaded Should NOT include Material not pertaining to stormwater management or erosion & sedimentation control Discharges within a Public water supply watershed or Aquifer Area require that a copy of the registration and plan be provided to the water company

10 Certification Requirements
The registrant and any other individuals responsible for preparing the registration and signing the certification shall have completely reviewed at a minimum; the general permit and All information provided in the Registration Form The project site, based on a site inspection The Stormwater Pollution Control Plan (SWPCP)

11 New Required Coordination Included Into The SWPCP:
Endangered and Threatened Species Aquifer Protection Areas Coastal Management Act Historic Preservation Review Wild and Scenic Rivers Act New Discharges to Impaired Water Body New outfall Same location but Increase in pipe size Same pipe but increase in Q

12 Registrations New Requirements

13 Stormwater Pollution Control Plan (SWPCP)
……….What’s in there?

14 SWPCP – Big Picture The Plan consists of site plan drawings and a narrative in conformance with CT DEEP Stormwater and Dewatering Wastewaters from Construction Activities General Permit 2004 Stormwater Quality Manual / 2002 Guidelines And shall be designed to minimize: Pollution caused by soil erosion & sedimentation during construction AND Stormwater pollution caused by use of the site post construction

15 What’s in the SWPCP ? Plan will include:
Site Plan / Site Specific Drawings Site Description Construction Sequencing Stormwater Control Measures Low Impact Development Inspections (Qualified Inspector, Routine Inspections) Inspection Reporting Keeping Plans Current Monitoring Requirements / Stormwater Monitoring Report Record Keeping Requirements Contractor Identification & Certification Termination Requirements

16 Site Plan Site specific drawings indicating:
Drainage patterns and approximate slopes after major grading activities Areas of soil disturbance Location of structural / non-structural controls Location of stabilization practices / landscaping Monitored outfalls Surface waters – impaired and high quality Wetlands – inland and tidal Location where stormwater will discharge to surface water (during and post construction

17 Site Description Narrative including: Nature of construction activity
Estimate of total area of the site and total area of expected soil disturbance Estimate of the average runoff coefficient of the site post construction Name of the immediate receiving water(s) and ultimate receiving water(s) Extent of wetland acreage

18 Construction Sequencing
Expected sequence of major construction activities on the site Estimated timetable for all construction activities Limits of disturbance for each phase Unless specifically designed by the engineer the site shall be phased to avoid disturbance between 2 to 5 acres and greater than 5 acres at any one time Disturbance of 2 to 5 acres per discharge point requires a temporary sediment trap with capacity to handle 134 c.y. per acre disturbed Disturbance of greater than 5 acres per discharge point requires a temporary sediment basin with capacity to handle 134 c.y. per acre disturbed Disturbance for an Impaired Water Body is different

19 Stormwater Control Measures
Purpose Minimize = reduce or eliminate to the extent achievable using control measures that are technologically available and economically practicable and achievable in light of best industry practice Typical Control Measures Temporary Stabilization Permanent Stabilization Structural Stabilization Designed in accordance with: “Guidelines” (2002 E & S Guidelines) 2004 Stormwater Quality Manual or CT DOT Qualified Products List Special Provisions CT DOT Form 816, as amended Engineered System

20 Stormwater Control Measures
Soil Stabilization and Protection Chapter 5 of the Guidelines Narrative and Drawings of Temporary & Permanent soil stabilization practices for managing disturbed areas and stockpiles, including a schedule for implementing the practices Temporary Stabilization Haybales Silt Fence Erosion Control Blanket Stone Slope Protection Seeding Permanent Stabilization Riprap slope Outlet Protection Surface Roughening Seeding / Landscape Planting

21 Stormwater Control Measures
Inactive Areas Where construction activities have permanently ceased or when final grades are reached in ANY PORTION of the site Implement stabilization and protection within 7 days Areas that will remain disturbed but INACTIVE for 30 days will receive temporary seeding or soil protection within 7 days or in accordance with the Guidelines CT DOT Form 816, Section 1.10 Environmental Compliance

22 Beyond the Seeding Season
Areas that will remain disturbed shall receive long term, non-vegetative stabilization and protection to protect the site through winter. In all cases, measures shall be implemented as soon as possible Hay Mulch / Erosion Control Matting

23 Stormwater Control Measures
When project encounters steep slopes, expect the following to be incorporated by the engineer: Any slope steeper than 3:1 (horizontal : vertical) that exceeds 15 feet vertically is required to have A reverse slope bench - or - Engineered slope stabilization structures - or - Detailed soil mechanics analysis Designed by a licensed CT PE With experience in geotechnical engineering or soil mechanics Reference 2002 E & S guidelines

24 Stormwater Control Measures
Structural Measures Permanent Sediment Basin Outlet Protection CBs / Manholes HDS Unless authorized by a regulatory permit (Inland Wetland / OLISP), all of these measures will be UPLAND

25 Stormwater Control Measures
Structural Measures Discharge from sites with an area of disturbance between 2 to 5 acres requires a temporary sedimentation TRAP to handle 134 c.y. per acre disturbed Non-Engineered Discharge from sites with area of disturbance over 5 acres requires a temporary sedimentation BASIN to handle 134 c.y. per acre disturbed Engineered …until final stabilization of the contributing area as defined in the “Notice of Termination” Capacity to contain 134 cubic yards of storage per acre of runoff

26 Stormwater Control Measures
Structural Measures The requirements for sediment traps and basins does not apply to flows from off site that are either Undisturbed Have undergone final stabilization Where such flows are diverted around the trap or basin

27 Stormwater Control Measures
Maintenance of Measures Plan shall include narrative of procedures to maintain E & S measures, including vegetation in good and effective operating condition All in accordance with the Guidelines, or more frequently as necessary to “protect waters of the state” from pollution.

28 Stormwater Control Measures
Dewatering wastewaters Basins should always be in non-regulated (upland) areas (not in wetlands or floodway) Measures to prevent scour or erosion when discharging to surface waters is necessary May not contain suspended solids in amounts that would cause pollution Discharge shall NOT contain: a visible oil sheen, floating solids or foaming in the receiving water.

29 Stormwater Control Measures
Post Construction Stormwater Management SWPCP Must include plans and narrative describing: Measures that will be installed to control pollution POST construction In conformance with the 2004 Stormwater Quality Manual and / or CT DOT qualified products list Must be placed in UPLANDS unless permitted Long Term Maintenance of such structures

30 Stormwater Control Measures
Other Control Measures Waste Disposal Litter, debris, building materials, hardened concrete waste Concrete Washout Areas Offsite vehicle tracking Generation of Dust All structures must be cleaned of construction sediment Sed Fence Removal upon stabilization Chemical & Petroleum storage

31 Stormwater Control Measures
Other Control Measures Concrete Washout Areas Conducted outside of any buffers and at least 50 feet from any stream, wetland or sensitive resource Conducted in an entirely self-contained system Designated washout areas are to be clearly flagged All washwater is to be directed into a container or pit designed that no overflows can occur during a rain Hardened concrete is considered “Waste Disposal” and is to be removed from the project and disposed of at an approved facility

32 BREAK

33 Low Impact Development (LID)

34 What is LID? Low Impact Development: Site design strategy that maintains, mimics or replicates pre-development hydrology through the use of site design principles and small scale treatment practices distributed throughout a site to manage runoff volume and water quality at the source. LID meant for new roadway development/new facilities or when specific project conditions warrant LID applications Typically LID requirements are not meant for linear type of transportation projects Examples: Permeable Pavement / Vegetative Swales / Infiltration Techniques / Stormwater Ponds

35 Typical LID Stormwater Practices
LID measures that can reduce the impact of development and address stormwater quality issues on site Infiltrating Filtering Retaining stormwater “Divide and conquer” Conserving vegetation and soils Minimizing impervious surface Maintenance Education

36 Inspections

37 Inspectors Certification by the CT DOT “Qualified Inspector”
An individual possessing either A PE or certification by a professional organization recognized by the commissioner related to agronomy, civil engineering, landscape architecture, soil science AND two years of demonstrable and focused experience in erosion & sedimentation control plan reading, installation, inspection and / or report writing for construction projects in accordance with the guidelines – or – 5 years of the same experience described above– or – Certification by the CT DOT

38 Inspections All projects must be inspected initially (within 30 days) for Plan implementation and then weekly for routine inspections Plan implementation Within first days following start of construction activity, qualified construction inspector (YOU) must be contacted to inspect the site Site shall be inspected: At least once and no more than three times during the first 90 days to confirm compliance and proper initial implementation of all control measures for the initial phase of construction.

39 Routine Inspections – “The What”
Maintain a rain gauge on-site At least once a week AND within 24 hours of the end of a storm that generates a discharge a Qualified Inspector shall inspect: Disturbed areas not finally stabilized All E & S measures All structural control measures Soil stockpile areas Concrete Washout areas Construction entrances / exits …for evidence of or potential for pollutants entering drainage system and impacts to receiving waters…..

40 Storm Inspections – “The When”
For storms that end on a weekend, holiday or other time after which normal working hours will not commence within 24 hours, an inspection is required Within 24 hours for storms that equal or exceed 0.5 inches For storms less than 0.5 inch; Inspection shall occur immediately upon start of subsequent normal working hours Where sites have been temporarily or finally stabilized; Inspection shall be once a month for three months

41 Inspection Reporting

42 Inspection Reporting Upon inspection, Qualified Inspector shall determine if it is necessary to install, maintain or repair controls / and / or practices to improve the quality of stormwater discharge Construction Site Environmental Inspection Report (CSEIR) shall be prepared and retained as part of the Plan summarizing: Scope of inspection Names, dates, weather conditions, precipitation amount Major observations relating to E & S controls Description of discharges from the site Any water quality monitoring performed Report must be signed by permittee or authorized representative

43 In Compliance / Out of Compliance
Report shall state that project is either in or out of compliance with the Plan and permit OUT of Compliance Include summary of remedial actions required to be in compliance Non-engineered corrective actions shall be implemented on site within 24 hours and incorporated into a revised Plan within 3 calendar days of the date of inspection unless another schedule is specified in the guidelines Engineered corrective actions shall be implemented on site within 7 days and incorporated into a revised Plan within 10 days of the date of inspection…..

44 Out of Compliance While corrective actions are being developed and have not yet been fully implemented; interim measures shall be implemented to minimize the potential for the discharge of pollutants from the site Inspectors from CT DEEP may inspect the site for compliance with this General Permit at ANY TIME construction activities are ongoing and upon completion of construction activities to verify the final stabilization of the site and / or the installation of post-construction stormwater management measures CT DEEP can issue Field directives / violations on site

45 Out of Compliance CTDEEP may notify the permittee at ANY TIME that the Plan site does not meet one or more minimum requirements of the general permit Within 7 days of such notice (or as specified in the notice), the permittee shall make the required change to the Plan and perform all actions as required by such revised Plan. Within 15 days of such notice (or as specified), the permittee shall submit a written certification that the requested changes have been made and implemented along with required supporting documentation requested.

46 Keeping Plans Current

47 Keeping Plans Current The Plan shall be amended if / when:
The actions fail to prevent pollution or otherwise comply with the general permit Whenever there is a change in contractors or subcontractors Change in design, sequence of construction, operation or maintenance at the site which has the potential for discharge of pollutants and which has not otherwise been addressed.

48 Keeping Plans Current In no event shall failure to complete, maintain or update a Plan relieve a permitee of responsibility to implement any actions required to protect waters of the state and to comply with all conditions of the permit.

49 BREAK

50 Stormwater Monitoring Report (SMR) for Turbidity

51 Monitoring Requirements

52 40 CFR Part 136 Turbidity ONLY ……(Phew!)

53 Normal Working Hours For the purposes of Monitoring, working hours are considered to be, at a minimum, Monday through Friday, between the hours of 8:00 am and 6:00 pm, unless additional working hours are specified by the permittee. If different… you can make a change, i.e. “Keeping Plans Current”

54 Monitoring Requirements
Sampling shall be conducted at least once every month when there is a discharge of stormwater from the site (for CT DOT = 0.1 inch) while construction activity is ongoing, until final stabilization of the drainage area associated with each outfall is achieved. Samples are required to be taken during normal working hours, which must be identified in the Plan.

55 Monitoring Requirements
If sampling is discontinued due to the end of normal working hours, sampling must resume the following morning or the morning of the next working day following a weekend or Holiday, as long as the discharge continues No stormwater discharge during month = no sampling BUT still must submit the SMR to DEEP regardless

56 Safety Considerations
Sampling may be temporarily suspended when such conditions exist that may reasonably pose a threat to the safety of the person taking the sample including: High winds Lightening Impinging wave or tidal activity Intense rainfall Sampling resumes once unsafe condition is no longer present

57 Sample Collection All samples must be collected from discharges resulting from a storm event that occurs at least 24 hours after any previous storm event generating a discharge Any sample containing snow or ice must note such on the SMR Sampling of snow or ice melt in absence of a storm event is not a valid sample

58 Monitoring Report Form – SMR’s

59 Monitoring Report Form

60 Storm Event Field Samples
Must be grab samples taken at least 3 separate times during a storm event and must be representative of the flow and characteristics of the discharge(s) May be taken manually or by an in-situ turbidity probe or other automatic sampling device equipped to take individual turbidity readings First sample must be taken within the first hour of the stormwater discharge from the site When storm begins outside of normal working hours, first sample must be taken at the start of normal working hours (if manual sampling)

61 Sampling Locations All point discharges of stormwater from disturbed areas (except as may be modified for linear projects) Two or more outfalls of substantially identical runoff may sample just one Similar exposed soils, slope, type of control used Report that the results also apply to the substantially identical discharge No more than 5 substantially identical outfalls may be identified for one representative discharge – EXCEPT -

62 Sampling Locations For Linear Projects up to 10 substantially identical outfalls may be identified for one representative discharge If the project continues for more than one year, the permittee must rotate the location of where the sample is taken twice a year (different representative discharge point every six (6) months) All locations must be clearly marked in the field with a flag, stake or other visible marker and on the plans by Station.

63 Turbidity Values Stormwater discharge value for each sampling point must be determined by taking the average of the turbidity values of all samples taken at that sampling point during a given storm

64 Stormwater Monitoring Reports
Stormwater sampling results must be entered on the SMR and submitted via DEEP within 30 days If there is no discharge during the given month, submit the form with “No discharge” in place of the monitoring results to DEEP

65 Stormwater Monitoring Reports
If additional sampling is completed more frequently than what is required, results must be included in additional SMR’s for that month If sampling protocols are modified due to limitations of normal working hours or unsafe conditions, a description / reason must be included with the SMR. Be sure to reference representative / substantially identical discharge points (names & locations)

66 NetDMR SMR’s must be submitted electronically (by the District Environmental Coordinator) to the DEEP no later than the 30th day of the month Registration is required prior to login

67 Record Keeping Requirements

68 Record Keeping / Retention
Permitee must retain an updated copy of the Plan at the construction site from the date construction is initiated until the date construction is completed Permittee shall retain for 5 years: Copy of the Plan All required reports Records of all data Inspection records (5 years after date of inspection)

69 Duty to Report Upon learning of a violation of a condition of the general permit, permittee shall immediately take all responsible action to: determine the cause of such violation, correct and mitigate the results of such violation, prevent further such violation and Report in writing the violation and corrective action to the commissioner within 5 days of learning of such violation

70 Contractor Certification
Can be submitted after permit is approved

71 Termination Requirements

72 Notice of Termination At the completion of construction, a Notice of Termination (NOT) must be filed. A project is considered complete; After all post construction measures are installed, cleaned and functioning AND Site has been stabilized for at least 3 months following the cessation of construction activities A site is considered stable when there is no active erosion or sedimentation present and no disturbed areas remain… for all phases !

73 Final Stabilization Inspection
For all sites, once the site has been stabilized for at least three months, the registrant shall have the site inspected by a qualified inspector to confirm final stabilization Compliance must be noted on the Notice of Termination Form Termination Forms -

74 Links

75

76 http://www. ct. gov/deep/cwp/view. asp

77 http://www. ct. gov/deep/cwp/view. asp

78 http ://www.ct.gov/dot/lib/dot/documents/dresearch/conndot_qpl.pdf