EETD Environmental Health and Safety Monthly Metrics July, 2014.

Similar presentations


Presentation on theme: "EETD Environmental Health and Safety Monthly Metrics July, 2014."— Presentation transcript:

1 EETD Environmental Health and Safety Monthly Metrics July, 2014

2 EETD Accidents- 7/14 TypeDateDept.DescriptionSeverityStatus No accidents reported in July Note: Bicycle accident reported in June has been classified as OSHA Recordable with lost work time.

3 EETD Accidents- By Type

4 EETD Accidents- Severity

5 Emergency Incidents- 7/14 DateIncidentAreaStatus No incidents reported in July

6 Ergonomic Assessments- By Month

7 Open EETD Ergonomic Assessments Date Requested Dept.TypeStatus 7/22/14BTUSDiscomfortIn Progress 7/15/14EAEIPreventativeIn Progress 7/15/14EAEIPreventativeIn Progress 7/3/14EAEIDiscomfortActions Pending 6/18/14ESDRDiscomfortActions Pending 6/10/14EAEIDiscomfortActions Pending 4/9/14ESDRDiscomfortActions Pending 3/5/14DIVDiscomfortActions Pending

8 EETD Job Hazard Analysis (JHA)- Pending New Hire vs. Expired Metric Started Sep ‘13

9 Job Hazard Analysis- % Completion

10 EETD Incomplete Training Assignments * Does not include SEC0203 “External Monitoring” Notice

11 Training % Completion Status

12 Incomplete Training by Course Type (Total Incomplete Assignments = 65)

13 Training Assignments Due (Total = 65) Open Assignments by Dept.Open Assignments by Hire Date

14 EETD Training Assignments Due

15 Safety Concerns Submittals- EETD

16 EETD Safety Concerns Status #DateConcernTypeStatus 10143/11/14Utility cover on sidewalk near 56A a trip hazard. Needs to be level with walking surface. Traffic- PedOpen 10345/5/14Surface of B90 4 th floor walkway is uneven where meets exterior stairway. Trip hazard. Building Maint. Open- Work Request #WIM577 10405/23/14Liquid argon dewar venting into pedestrian walkway at B70 fill station area. Environment - Outdoor Open- Add curtains to fill station area 10557/1/14Pot hole in B88 drive.Slip Trip FallOpen- Facilities work request 10657/28/14Trip hazard in Bevetron parking lot walkway. Well with damaged/missing cover. Slip Trip FallCompleted

17 Corrective Action Reports (CATS)- 7/14 CAT #DateDescriptionLeadStatus 96727/29/14Provide improved storage of laser eyewear in 70-157. DOE assessment follow-up item. X. MaoBasically complete. Ready to verify and close. 96737/29/14Provide non-combustible laser barriers in 70-157. DOE assessment follow-up item. X. MaoNew foil material installed and being verified by the LSO. 96757/29/14Seismically secure the laser table near the 70-157 entrance. DOE assessment follow-up item. X. Mao/ R. Scholtz Facilities work request submitted for cost estimate.

18 Activity Hazard Documents (AHD)- 7/14 AHDDescriptionStatusLocationPI 2035Chemical- LithiumCompleted62-246J. Kerr 3939Chemical- Solvent Purification Completed70-269G. Liu 3947Chemical- LithiumNew AHD- Pending draft review 70-293E. Cairns

19 Audits and Inspection Status- 7/14 TypeDateLeadStatus Quarterly SAA Inspections 7/29/14R. ScholtzCompleted

20 Satellite Accumulation Area (SAA) Overall Compliance

21 Satellite Accumulation Area- Issues by Quarter

22 Cumulative SAA Issues (FY Q1 ’12 – Q4 ‘14)

23 Significant Safety Achievements- 7/14 The Chemical Management System (CMS) self-assessment project is almost completed. All data has been collected and the draft report is being prepared. The quarterly Satellite Accumulation Area inspections of EETD lab areas was completed. We had a 99% overall compliance rate. WPC Activity Manager “projects” and “activities’ for EETD operations have been sent out for review. Initial set-up of the system has started in anticipation of the soft roll-out. Chemical inventory lists were sent out to each lab area owner for review and update. The entire EETD inventory was reviewed and obvious corrections made. An EETD Safety Alert was issued regarding proper storage and capping of needles used in the lab areas.

24 Short Term Safety Outlook- 8/14 Submit the completed Chemical Management System (CMS) self-assessment report. Continue the set-up of the Work Planning and Control (WPC) “projects” and “activities” framework for EETD. Continue to assist with start-up of the new FLEXLAB buildings. Complete the flame resistant lab coat corrective action. Address issues identified by the fire marshal in EETD buildings. A large old chemical/sample clean-out is planned in 62-220 and 62-246. Develop FLEXLAB user safety orientation training. Develop area safety lead orientation training.