1 Route 364 (Page Ave. Extension) The Missouri Department of Transportation

2 Route 364 history Project started in 1997, opened in 2003 Phase 1 from Route 270 to Jung Station Road, St. Charles – Completed Phase 2 from Jung Station Road to Mid Rivers Mall Drive – In progress Phase 3 from Mid Rivers Mall Drive to Route 40 (near Route N) – Planned Regional Priority for East-West Gateway Council of Governments, St. Charles County

3 What’s going on now? Constructing Phase 2 between Jung Station Road and east of Jungermann Road: $19.7 million Crews have built new north and south outer roads (one-way) Built two-way bypass to construct Harvester Road bridge Bridge completed later this fall Originally scheduled to open winter-spring 2010

4 What’s going on now? Green = current construction

5 What’s on the horizon? Economic stimulus project completes Route 364 from Jungermann to west of Central School Road: about $44 million Work starts in October – completed by 2012 Crews will construct outer roads, then Route 364 Traffic flow may postpone reopening of Route 364 by Harvester Road

6 What’s on the horizon? Yellow = under contract

7 What’s in the future? MoDOT and St. Charles County are working on an agreement to finish Phase 2 between Central School Road and Mid Rivers Mall Drive. MoDOT is expecting to start preliminary bridge or outer road work near Mid Rivers Mall Drive in 2010 Currently, it will cost about $40 million to complete the rest of Phase 2.

8 What’s in the future? Light Green = proposed Red = Phase 3

9 Overall view of Phase 2 of Rte 364

10 What about Phase 3? Phase 3 runs between Mid Rivers Mall Drive and Route 40/Route N No money is available for Phase 3 yet Estimated costs to complete Phase 3: $140 million Legislature has authorized MoDOT to use design-build on Route 364 project – if used, must start design-build by 2013 May consider construction in two financially manageable segments – Mid Rivers to K, K to Route 40

11 What’s in the future?

12 Route 364 (Page Avenue Extension) The Missouri Department of Transportation


Download ppt "Route 364 (Page Ave. Extension) The Missouri Department of Transportation."

Similar presentations


Ads by Google