Presentation is loading. Please wait.

Presentation is loading. Please wait.

Safety Officier Planning & quantity Survey Quality Assurance Eng. Accounting & Cost control Building erection Mechanical equipment Reheating furnace Piping.

Similar presentations


Presentation on theme: "Safety Officier Planning & quantity Survey Quality Assurance Eng. Accounting & Cost control Building erection Mechanical equipment Reheating furnace Piping."— Presentation transcript:

1 Safety Officier Planning & quantity Survey Quality Assurance Eng. Accounting & Cost control Building erection Mechanical equipment Reheating furnace Piping and aux. Systems HV / LV power distribution & Automation system Mechanical Electrical Piping Director, Projects Sales Manager Export Finance & L/C Manager Legal Dept. Manager Procurement Manager Quality Manager Client Project Manager & Project Management Staff P.M. DMH P.E. Rolling process P.E. Mech. Equipment eng. P.E. Hydraulics Lubrication P.E. Piping Utilities P.E. Instrumentation P.M. DCC P.E. Combustion process P.E. L.V. Distribution P.E. Automation P.M. DE P.C. WTP process P.E. Civil & structural des. P.E. Interconnecting piping P.E. Instrumentation P.E. HVAC P.E. Firefighting system P.E. Compressed air system P.C. Workshop laboratory eq. P.C. Cranes P.M. DA Process Coordinator P.E. Substation, HV - LV power distrib. P.E. Interconnecting cabling P.C. Automation system level 1 P.C. Automation system level 2 P.M. DCM P.E. Meltshop process P.E. Mech. Equipment engin. P.E. Hydraulics lubrication P.E. Piping utilities P.E. Instrumentation Site Technical Office Field Engineers Civil and infrastructure construction Supervisor Erection SupervisorsStartup and commissioning Team Material Man Client Site manager & Staff P.C. Spare partsP.C. Packing & Shipping P.C. TrainingP.C. Operation, maintenance & safety manuals P.C. Expediting / testing (E LE) P.C. Quality Control P.C. Manufacturing & expediting P.C. Procurement cc Danieli Construction & Commissioning (UMAC) P.M. Construct Erection & Commiss. Site Manager Deputy Site Manager Danieli Engineering (DE) Project Manager Project Planning & Control Contract Administr. Automation Aux. Systems Turn-key project Key-Personnel Organisation chart

2 SCHEDULE (LEV. III) WORK BREAKDOWN PRICE BREAKDOWN JOB POSITION (TPC/JET) INSPECTION TEST SCHEDULE (ITS) CASH FLOW (PART 2)(PART 3) RESPONSIBILITY CONTRACT & FINANCING TOOLS REQUIREMENTS MASTER PLANT LIST TECHNICAL SPECIFICATIONCONTRACT SCHEDULEPAYMENT METHOD/FORMALITIES PICS (PROJECT INTEGRATED CONTROL SYSTEM) General Management Flow Chart (part 1)

3 OUTSIDE (E/LE)INSIDE (I) (PART 3) ENGINEERING (DOCUMENT MANAGEMENT SYSTEM - DMS) TECHN. DOCUMENTS JOB POSITION (TPC / JET) from part 1 MATERIAL REQUIR. PROCUREMENT PURCHASE & ORDERS MANUFACTURING General management Flow Chart (part 2)

4 INSPECTION & TESTING (NOI/IRE/LOC/QCTM) OUTSIDE (E)INSIDE (I/LE) INSPECTION TEST SCHEDULE (ITS) (FROM PART 1) CERTIFICATIONS (IRE) SHIPPING & INVOICING CERTIFICATION (IRP) PACKING LIST INSPECTION PLANNING NOTICE OF SURVEILLANCE (NOS) PACKING COMMISSIONING JOB POSITION (TPC/JET) (FROM PART 1) RELEASE CERTIFICATE (RC) PRICE BREAKDOWN (FROM PART 1) MANUFACTURING (FROM PART 2) INSPECTION PLANNING NOTICE OF INSPECTION (NOI) CONSTRUCTION & ERECTION WORKS SITE PROGRESS MANAGEMENT (SPM) General management Flow Chart (part 3)

5 Master Plant List (esempio)

6 Estratto Livello 3: Plant Unit 31 (Typical)

7 Programmazione di Livello 3 (Typical)

8 Programmazione di Livello 4 (Typical)

9 Cut-off date: Progress (Typical)

10 planned progress % NDJMFAMJJASONDJMFAMJJASONDJMFA Valide per tutte le discipline e attività Curve pianificate di avanzamento (typical)


Download ppt "Safety Officier Planning & quantity Survey Quality Assurance Eng. Accounting & Cost control Building erection Mechanical equipment Reheating furnace Piping."

Similar presentations


Ads by Google