Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Change Management FOR University Medical Group Saint Louis University Click this icon for Audio.

Similar presentations


Presentation on theme: "1 Change Management FOR University Medical Group Saint Louis University Click this icon for Audio."— Presentation transcript:

1

2 1 Change Management FOR University Medical Group Saint Louis University Click this icon for Audio

3 2Agenda Change Management DefinedChange Management Defined Process OverviewProcess Overview MonitoringMonitoring Q & AQ & A

4 3 Change Management - Process of executing and documenting changes that ensures a highly available, consistent, and stable computing environment. Ensure standardization across all sites and departments, as well as ensures that all necessary parties are contacted, informed and approve each change request. Each requested change is recorded and properly tracked to completion. All changes are controlled to provide reasonable assurance that significant changes are authorized and appropriately tested before being moved to production.Definitions

5 4Definitions Functional Manager (FM) – Responsible for the technical operation of the system or application Business Process Owner (BPO) – End user of the system or it’s non- technical manager. Key Controls (CM #) - Denotes the key process controls within Change Management identified and approved by the University. Change Control Board (CCB) – Formal group of FM, BPO and other key stakeholders responsible for approving, scheduling or rejecting high or urgent changes Change Control Manger (CCM) – Responsible for facilitating the process. Is the first point of contact for each Change and can assist throughout the process. Change Management Team (CMT) – Formal group of FM, systems application managers and other technical personnel responsible for managing the Change Remedy Management System (Remedy) – Request tracking system used to record and document the Change for the CM process

6 5CONTROLS CM1 A formalized documented system for tracking and reporting CM2 A formalized documented system for approval CM3 Changes meeting Project criteria must go to Project Office or Senior Management for Approval/Management CM4 Change Request must have all required documentation CM5 Change Request must have an Assessment Analysis CM6 Change Request must have Testing Environment CM7 Change Requests must have Testing documentation CM8 Change Requests must have Production Approval CM9 Change Request must have Production documentation CM10 Change Request must have documentation of users and process owner approval CM11 Version Control must be documented and maintained CM12 Scheduled Service Reviews of Changes made to the Applications

7 6 Business Case Impact & Risk Analysis Change Build Form Back Out Plan Test Plan & Checklist Communication Plan Implementation Plan Acceptance Form Closure FormForms See CM Desk Top Procedures for more information

8 7 Process Overview For Change Management

9 8 For a more detailed outline see the CM Desktop Procedures Life Cycle

10 9 IT Functional Manager: 1. Creates a Change Request in Remedy 2. Inputs Requestor Log-in information 3. Selects Functional Group to manage Change Step One: Initiate Request CM Control #1

11 10 FM will give brief description of the change request in these fields. FM will input the SLUNET ID of the requestor: additional information will auto-populate. Initiating Change Request in Remedy FM will select his group here

12 11 Functional Manager: 1.Submit the Change Request to CCM for review: Selects “CCB” in the Service field Submits the Business Case Form with the Requestor 2.Performs initial risk assessment Completes Risk Matrix Completes CCB Review 3.Determines if this is an emergency Selects the proper Priority code: “Urgent” Step Two: Manage Change Review CM CONTROL # 2 and 3

13 12 Risk Management Tools For Functional Manager After selecting “CCB” in the Service field for review: tabs for performing risk and impact analysis' will appear.

14 13 Risk Management Tools For Functional Manager The Risk of the Change will automatically be determined after the FM completes these few questions: simply press the “Calculate Risk” button. (The Risk Classification will also auto-populate in the Assessment tab.) Note the hyperlink “View Required Documentation” RISK MATRIX

15 14 Risk Management Tools For Functional Manager Change Classification -- Required Forms Request Phase Highlighted Documentation listed below is required for Medium and High Risk changes: 1.0 Initiate 1.1 Remedy Change Request (always required) 2.0 Change Review 2.1 Business Case 3.0 Change Assessment 3.1 Communications Plan 3.2 Training Plan (as needed) 3.3 Support Plan (as needed) 3.4 Risk and Impact Analysis 3.5 Change Build Form 3.6 Backout Plan 4.0 Testing 4.1 Test Plan 5.0 Approve / Implement 5.1 Acceptance Form 5.2 Implementation Plan 6.0 Change Closure 6.1 Close-Out / Sign Off 2.1 Business Case 3.1 Communications Plan 3.4 Risk and Impact Analysis 3.5 Change Build Form 3.6 Backout Plan 4.1 Test Plan 5.1 Acceptance Form 5.2 Implementation Plan 6.1 Close-Out / Sign Off Sample of Required Forms for Medium and High Changes “View Required Documentation”

16 15 Risk Management Tools For Functional Manager Risk Classifications Four classifications of Risk: Low Medium High Urgent Managed by one or more of four entities Change Control Board Change Control Manager Departmental Functional Manger ITS Project Office All Risk Assessments Reviewed by Change Control Manager

17 16 A Change will be assigned to the Functional Manager if: For Example: –If the change requires immediate (emergency) attention –If the change requires no “down time” –If the change has no interrupt to service Low/Medium Risk Changes Reference: Change Management Risk and Impact Matrix for further details

18 17 A Change will be assigned to the CCB if : For Example: –If the change has multiple system dependencies –If the change does not require immediate attention –If the change requires “downtime” –If the change has interruption to services High Risk Changes Reference: Change Management Risk and Impact Matrix for further details

19 18 A Change will be assigned to the Project Office if: The budget of the project is over $25,000 of non-labor expenses It involves staff from 3 or more ITS departments one or more of the following: It involves more than 300hrs ITS effort A work schedule that is longer than 3 months External labor greater than 100 hrs The project schedule is highly constrained An ITS project is a defined, approved, temporary effort to produce a unique product or service in support of the University mission. ITS Project Office - Managed Changes Reference: slu.edu/x11183.xml for further detailsslu.edu/x11183.xml

20 19 Documenting “Emergency” changes FM can override the Risk Matrix, and note circumstance below. In the case of an emergency Change, records must be completed post- implementation. FM will select “Urgent” in the Priority field, and fill out the remaining documentation.

21 20 Risk Management Tools For Functional Manager CCB REVIEW The CCB Review questions are forwarded directly to the CCB and CCM: They will assist all stakeholders in managing Medium to High risk Changes.

22 21 The FM or their designee can attach any documentation on this tab: including confidential material (see right). Attaching Supporting Documentation Labeled “CM Attachments” There is also a Hyperlink to CM documentation. CCB Attachments

23 22 Risk Management Tools For Functional Manager The final task in the initial Risk and Impact analysis is to input a start and end date for the Change under the Assessment tab. (can be adjusted later). Assessment DON’T FORGET TO SAVE YOUR WORK !!!

24 23 Step Three: Change Assessment Functional Manager, CCM or CCB: 1. Reviews and begins approval process 2. Performs a detailed risk assessment Impact & Risk Analysis Form 3. Gathers requirements and plans resources 4. Identifies personnel involved 5. Develops material and documentation Change Build Form Back Out Plan Form CM CONTROL # 4 and 5

25 24 Functional Manger, CCM or CCB: 1.Creates a Test Plan and Test Plan Checklist Identify test cases, scenarios and scripts Specify test environment requirements Identify document standards for testing and production environment Test Plan 2.Completes other forms as required by Functional Manager, CCM or CCB: Communication Plan Training Plan Support Plan CM Control # 6 and 7 Step Four: Testing

26 25 Step Five: Approve & Implement Functional Manager: Creates an Implementation Plan Implementation Form Functional Manager, CCB, CCM and/or Business Process Owner: 1.Reviews all work against requirements and schedule Risk & Impact Analysis Back Out Plan Change Build Form Test Plan & Checklist 2.Communicates and Implement Change Implementation and Communication Forms revisited Acceptance Form (CCB, CCM and BPO approval) CM CONTROL # 8,9 and 10

27 26 Step Six: Change Closure Functional Manager, CCM or CCB: 1.Confirms Version Control with Requester Review all forms for correct documentation 2.Finalize Plans and Validates Closure Form CM CONTROL # 10 and 11

28 27 Change Management Monitoring

29 28 Functional Manager, CCB, CCM and Business Process Owner will review reports for the following areas on pre- determined schedule. 1. Segregation of Duties Analysis 2. Reconciliation of CM logs to configuration logs 3. Documentation supporting implementation of CM CM CONTROL 12Reporting

30 29 For Additional Information CONCLUSION Please contact the Quality Assurance Office: qaoffice@slu.edu


Download ppt "1 Change Management FOR University Medical Group Saint Louis University Click this icon for Audio."

Similar presentations


Ads by Google