Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr.

Similar presentations


Presentation on theme: "Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr."— Presentation transcript:

1 Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr. Yong-Kyu Jung A.I.R Automated Individual Remote September 27, 2006

2 Deliverable 2006 Due DateDeliverablePrimary Member Status 09/04/2006Summary of ResearchLibby John 09/27/2006PCB #1Matthew Watkins 10/01/2006LON ModuleLarry Wu 10/09/2006Communications Documentation Libby John 11/15/2006PCB #2Matthew Watkins 11/21/2006Program CodeEric Robbins 12/01/2006Technical Report & User Manual Libby John Completed In Progress Not Started Behind 11/21 Program Code 10/9 Communications Documentation 12/1 Technical Report and User Manual 9/4 Summary of Research 10/1 LON Module 11/15 PCB #2 9/27 PCB#1

3 Milestones 2006 Due DateMilestonesStatus 09/13/2006Primary Research Completed 09/20/2006Schematic and PCB Layout 09/27/2006Prototype Demo 10/04/2006TV Tuner Module 10/11/2006Setpoint Feedback 10/18/2006Enclosure Options 10/25//2006GUI Presentation 11/1/2006 System Demonstration 11/8/20062 nd PCB 11/15/2006PCB Populated Completed In Progress Not Started Behind

4 Open Actions Status What action: Communications Documentation Who has responsibility: Libby What is status: In Progress Expected Date: 10-9-06

5 Open Actions Status What action: Full Integration with out LON Who has responsibility: Eric What is status: In Progress Expected Date: 10-9-06

6 Open Actions Status What action: Setpoint Feedback to µc Who has responsibility: Larry What is status: Behind Schedule Expected Date: 10-9-06

7 Open Actions Status What action: Engineering changes on first PCB Who has responsibility: Matt What is status: In Progress Expected Date: 10-9-06

8 Earned Value Total Number of hours worked: __90/444__ Estimate of manpower needed: __800__ Total Baseline hours: _1000_ SPI:.5 CPI:.32 Projection: –Scope: No change –Time: On time –Cost: Below Cost

9 Technical Assistance Proposed Solutions 1.Short Stack API development kit Capture LON packets from the network LON to serial gateway 2. LCD decode Decode data that is sent from the µ c of the LON module to the on board LCD

10 Short Stack API Development Kit Uses the current microcontroller. Data is captured over the LON network. When data is received the current process is interrupted to call the Short Stack API, which then acknowledges to that data has been received. Cost of Item: $200.00 Student Development Kit: Free

11 PIC 16F690 Application Short Stack API Driver SPI Interface Short Stack Micro server TP/FT-10F LON Network Block Diagram

12 LON Daughter Board TP/FT-10F Flash Free Topology Twisted Pair Control Module Echelon part# 55020-10


Download ppt "Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr."

Similar presentations


Ads by Google