2 Radius prepaid billing system is a vital component of the ecosystem. Reliability and credibility is of utmost importance. Robust and transparent system lost it credibility and reliability - Poor maintenance and upkeep - a) Problem of Updating of meter reading - Billing System affected resulting in abrupt deduction. b) Lack of Low Balance Information. c) Problem is DG sensing, DG Consumption units were being billed in Grid. d) ACs running in DG resulting in DG Over loading and frequent trips d) Difficulty in identifying faulty meters resulting in high T&D Loss. Steps taken: AGRWA rectified 22 faulty meters- Currently it is less than 4 Radius pointed out the following limitations. 1. DG Sensing Cable is ruptured in a no. of Place. 2. Difficulty in repairing of Load Monitor cards and communication modules due to non availability. 3. Poor maintenance due to reluctance of AGRWA to review the AMC charges since 2011. In view above issues and also installation of new DG sets, it is imperative that we fix the prepaid billing systems. AGRWA studied the proposal submitted by Radius to previous managing committee.  Why Upgradation of Radius Prepaid Billing System ?

3 The new system proposes to do away with all cable and wiring systems for DG sensing, individual meter reading and load regulation. The entire network will be based on Wi-Fi system.

4  Proposal study and negotiation: Year18.6.201419.8.1425.9.2014 Lump sum payment for prepaid system 1575000/- ( Rs. 3500 per flat ) 13,50,000/- (Rs. 3000/- per flat) Rs. 11, 25,000/- (Rs. 2500/- per flat) Intercom 439800/- Intercom included Maintenance for one year 3,78,000/- Rs. 70/- per flat/month 3,78,000/- Rs 70/- per flat /month 3,78,000/- Rs 70/- per flat/months Maintenance for 2 nd & 3rd Year 10,69,200/- Rs. 99/- per flat/month 16, 09,200/- Rs.149/- per flat/month Rs. 7,56,000/- Rs.70/- per flat/months Total 34, 62,000/-Rs. 33,37,200/-Rs, 22,59,000/- Based on the above negotiation there has been significant reduction in the cost of over all up gradation if we take into account over a period of three years.

5 Study of the cost of up gradation vs continuing with the existing system. - If we choose to continue with the current system and also considering an annual increase of 5% in the AMC as agreed in the agreement dated 30/11/2009, it will be costing us 40000/- more. In essence we will be saving Rs. 40000/- in 3 years time by upgrading the latest pre-paid billing system apart from the resolving the issues currently being faced by the residents. There will also be significant improvement f quality of service and experience for the residents.  What if the system is not upgraded and continued as it is ? Year2008-20092010-20112012-20132014-20152016-20172018-2019 Per Flat100.00110.00121.00133.10146.41161.05 Monthly45000.0049500.0054450.0059895.0065884.5072472.95 Total Yearly1080000.001188000.001306800.001437480.001581228.001739350.00 This cost of maintenance as projected is corroborated from the fact that M/s Radius on 1.6.2013 had proposed for AMC of Rs. 61,744/- per month and on 11.6.2014 had proposed AMC of Rs. 68,820/-. From the above its clear that the total cost of AMC for these three years would be Rs. 22, 99,968/- ( Rs 7, 18,740/- for 2015, and Rs 1581228/- for 2016 and 2017). The cost of up gradation is thus effectively -- Rs 50000/-