Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Similar presentations


Presentation on theme: "Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)"— Presentation transcript:

1 Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

2 Y. Unno, 2007/2/26 ATLAS06J fabrication Masks are done Fabrication is on- going –p-FZ(100) –p-MCZ(100) –3 wafers each Delivery –April Irradiation –End April –70 (or 80) MeV p

3 Y. Unno, 2007/2/26 ATLAS07 150mm wafer –p-FZ(100) n-strip isolation –Individual p-stop 4 segments –SS: as is –LS: wire-bond segments

4 Y. Unno, 2007/2/26 Stereo?

5 Y. Unno, 2007/2/26 Edge stereo connection

6 Y. Unno, 2007/2/26 ATLAS07 specification

7 Y. Unno, 2007/2/26 ATLAS07 Design –2 months+? –by May? Fabrication –a few months –depends on quantity Financing –Mask cost to be shared –No. wafers=Cost share –Invoices Japan: KEK Outside Japan: CERN TID My big question mark –Readout ASIC? Irradiation campaign –CYRIC (70-80 MeV p) (April), Aug, Nov,Mar –PSI (pions) –Neutrons Dummy ATLAS07 –Al metal only –Who are interested? –How many? –Financing with same model

8 Y. Unno, 2007/2/26 ATLASxx plan 2007 3-5 Design of pre-prototype (Barrels) 2007 6-9 Fabrication of pre-prototype 2007 9- Irradiation, Module fabrication and evaluation 2008 3-6 Design of prototype (Barrels, Endcaps) 2008 6-10 Fabrication of prototypes 2008 10-Irradiation, Module fabrication and evaluation, beamtests 2010 2 TDR

9 Y. Unno, 2007/2/26 Sensor parameters for ASIC 1-MeV n eq /cm 2 Fluence by particles

10 Y. Unno, 2007/2/26 Sensor parameters for ASIC Constraint from HV cable rating –500 V –(1 kV tested) Sensor operation –<500 V Parameters for ASIC –at 500 V –Preliminary

11 Y. Unno, 2007/2/26 Sensor parameters for ASIC Preliminary!!!

12 Y. Unno, 2007/2/26 Module plan Modules –have to have –ABCN when? –hybrids develop along with ABCN –fabrication of modules time scale uncertain Staves –?